Jaspur- Dhampur Work Completed
Project: UEAP-RB UID: 6001 Sanction Cost: 520.00  lakh Length: 6.000 KM.
District: Udham Singh Nagar Block: Jaspur Constituency: Jaspur Circle:
DEA: DEA UEAP Nainital DSC: CCEE Group India Pvt.Ltd DSC Scope: Design & Supervision Type: SH
Procurement:
Package No.: 1006        Package Name:  UEAP/PWD/C4        Tender Date: 13-01-2014        Current Status: Agreement signed        Achieved on Date: 21-04-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C4      Contractor Name: Woodhill Infrastructure Ltd
Start Date:  14-06-2014      Intended Completion Date:  13-01-2016      Original End Date:  13-09-2015
Total Bond Cost: 44868136 (448.68 lakh)        Variation Cost: 6601612.80 (66.02 lakh)    Hence Total Bond Cost is   51469748.8 (514.7 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.GSB/RBI/G-10.77 KM21.0416-06-201408-10-20150.77 KM0.77 KM5.3121.04
2.G-20.77 KM12.8216-07-201418-08-20140.77 KM0.77 KM3.2412.82
3.G-30.77 KM12.4716-07-201418-08-20140.77 KM0.77 KM3.1512.47
4.BM i/c Prime Coat, Tack Coat3.99 KM133.6028-06-201405-02-20153.10 KM3.10 KM33.74133.60
5.SDBC i/c Tackcoat4.42 KM71.7228-06-201405-03-20156.00 KM6.00 KM18.1171.72
6.Culverts/Scupper 3.00 No3.9515-04-201529-11-20153.00 No3.00 No13.95
7.longitudinal Drain1950.00 m123.7601-04-201522-12-20151950.00 m1950.00 m31.26123.76
8.Road Furniture22.00 No16.6115-04-201507-01-201620.00 No20.00 No4.1916.61
Total Amount: 395.97 100   395.97
Remarks: No Remarks       Work Program Made On: 17-04-2015        Updation of work program on: 25-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.07-May-2015285.00  lakh
2.27-June-201538.45  lakh
3.03-October-201530.44  lakh
4.29-February-201649.69  lakh
5.15-June-201737.32  lakh
Total 440.9  lakh
% Payment 85.65 %
Advance Amount:  44.00  lakh        Recovered Amount:  44.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 144   No. of Test Done : 144    No. of Test Passed : 142   No. of Test Failed : 1   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 93.24
Number of Notice(s) issued: 73

Mobile Pic Upload

Number of Pics Available on Web Repository: 22
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.02-08-2015Chsinage 5+100Road Side drain near police chauki NadahiRajiv GururaniEEDEA ADB Nainital See Pic
2.02-08-2015Chainage 4+800cbRajiv GururaniEEDEA ADB Nainital See Pic
3.02-08-2015Chainage 4+880Road Side Drain near Nadhai Sugar MillRajiv GururaniEEDEA ADB Nainital See Pic
4.08-06-2015Km4Packed company bag of glass beadsLalit TiwariAEDEA ADB Nainital See Pic
5.08-06-2015KM 4Glass Beads Using in Thermoplastic Road MarkingLalit TiwariAEDEA ADB Nainital See Pic
6.08-06-2015K.M.6Edge Line MarkingLalit TiwariAEDEA ADB Nainital See Pic
7.08-06-2015KM 4Edge line markingLalit TiwariAEDEA ADB Nainital See Pic
8.20-05-2015Chainage Km 4.600Left side RCC drain work in progressRajiv GururaniEEDEA ADB Nainital See Pic
9.20-05-2015Chainage Km 4 .350Right side RCC drain work in progressRajiv GururaniEEDEA ADB Nainital See Pic
10.20-05-2015Chainage 4.700RCC road side drain in progressGulab RamSEADB Circle See Pic
11.14-05-2015chainage 5.300road side RCC drain construction work in progressRajiv GururaniEEDEA ADB Nainital See Pic
12.14-05-2015chainage 4.750ROAD SIDE RCC DRAIN WORK IN PROGRESSRajiv GururaniEEDEA ADB Nainital See Pic
13.29-04-2015Chainage 1+750Road surface after B M & S D B C workRajiv GururaniEEDEA ADB Nainital See Pic
14.29-04-2015Chainage 4+750Excavation & laying of base concrete for road side drain near Rajan's ShopRajiv GururaniEEDEA ADB Nainital See Pic
15.29-04-2015Chainage 4+650Road side drain work in progressRajiv GururaniEEDEA ADB Nainital See Pic
16.23-04-2015Km 4Final surfaceLalit TiwariAEDEA ADB Nainital See Pic
17.23-04-2015Km 6Taking final level of roadLalit TiwariAEDEA ADB Nainital See Pic
18.24-03-2015K.M.4B. M.WorkLalit Tiwariunknownunknown See Pic
19.24-03-2015K.M. 4.5B.M.work at jaspurLalit TiwariAEDEA ADB Nainital See Pic
20.12-03-2015Km 2.780R C C road side drain constructionRajiv GururaniEEDEA ADB Nainital See Pic