Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Ramnagar Kaladungi Haldwani Kathgodam Chorgaliya Sitarganj Bijti MR Phase 4 (Km. 77 to 87.30) Work Completed
Project: UEAP-RB UID: 5915 Sanction Cost: 1787.00  lakh Length: 11.300 KM.
District: Nainital Block: Haldwani Constituency: Lalkuan Circle:
DEA: DEA UEAP Nainital DSC: Sheladia Associates DSC Scope: Design and Supervision Type: SH
Procurement:
Package No.: 1098        Package Name:  UEAP/PWD/C-83B        Tender Date: 30-01-2016        Current Status: Agreement signed        Achieved on Date: 02-04-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C-83B      Contractor Name: Raj Shyama Constructions Pvt. Ltd
Start Date:  12-04-2016      Intended Completion Date:  11-12-2016     
Total Bond Cost: 114675232 (1146.75 lakh)        Variation Cost: 32316921.45 (323.17 lakh)    Hence Total Bond Cost is   146992153.45 (1469.92 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works3360.00 m287.2813-04-201606-12-20163360.00 m3360.00 m20.76287.28
2.PC/CC i/c Prime Coat, Tack Coat3.39 KM61.7213-04-201615-10-20163.39 KM3.39 KM4.4661.72
3.BM i/c Prime Coat, Tack Coat11.30 KM687.6913-04-201611-05-201611.30 KM11.30 KM49.7687.69
4.SDBC i/c Tackcoat11.30 KM194.8515-05-201618-11-201611.30 KM11.30 KM14.08194.85
5.Cause Way3.00 No43.7101-05-201618-10-20163.00 No3.00 No3.1643.71
6.Culverts/Scupper 9.00 No77.1401-05-201627-11-20168.00 No8.00 No5.5777.14
7.Crash Barrier1310.00 m29.4801-07-201621-11-20161310.00 m1310.00 m2.1329.48
8.Road Furniture75.00 No1.8821-11-201606-12-201675.00 No75.00 No0.141.88
Total Amount: 1383.75 100   1383.75
Remarks: No Remarks       Work Program Made On: 11-07-2016        Updation of work program on: 25-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-April-2016216.45  lakh
2.31-May-2016238.78  lakh
3.02-June-2016174.85  lakh
4.23-June-2016178.18  lakh
5.31-August-201679.28  lakh
6.27-October-2016106.98  lakh
7.28-November-2016151.32  lakh
8.28-February-2017165.21  lakh
9.25-March-201759.57  lakh
10.30-May-201729.76  lakh
11.22-June-201741.62  lakh
Total 1442  lakh
% Payment 98.09 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1531   No. of Test Done : 1532    No. of Test Passed : 1521   No. of Test Failed : 3   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 93.03
Number of Notice(s) issued: 28

Mobile Pic Upload

Number of Pics Available on Web Repository: 41
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.28-12-2016Chainage 83+700Thermoplast work on the roadRajiv GururaniEEUEAP R&B Nainital See Pic
2.28-12-2016Chainage 84+900Thermoplast work on roadRajiv GururaniEEUEAP R&B Nainital See Pic
3.28-12-2016Chainage 80+400Culvert after completionRajiv GururaniEEUEAP R&B Nainital See Pic
4.28-12-2016Chainage 80+400Culvert after completionRajiv GururaniEEUEAP R&B Nainital See Pic
5.28-12-2016Chainage 76+400Thermoplast work is onRajiv GururaniEEUEAP R&B Nainital See Pic
6.29-11-2016Chainage 80+400Checking Crust & Bituminous thickness at the affected area where road damagedRajiv GururaniEEUEAP R&B Nainital See Pic
7.29-11-2016Chainage 77+400DBM work in the approaches of culverts is in progressRajiv GururaniEEUEAP R&B Nainital See Pic
8.08-11-2016Chainage 85+450Inspection of thermoplast by SE SirRajiv GururaniEEUEAP R&B Nainital See Pic
9.08-11-2016Chainage 80+425SE sir inspection of portion that become uneven due to rains last monthRajiv GururaniEEUEAP R&B Nainital See Pic
10.02-11-2016At plantBitumen Content test for BCLalit TiwariAEDEA ADB Nainital See Pic
11.02-11-201683+700Construction of CausewayLalit TiwariAEDEA ADB Nainital See Pic
12.02-11-2016At PlantCompressive LoadLalit TiwariAEDEA ADB Nainital See Pic
13.02-11-2016At LabBitumen Content testLalit TiwariAEDEA ADB Nainital See Pic
14.02-11-2016At LabConcrete cube weight .taking before loding for Compressive TestLalit TiwariAEDEA ADB Nainital See Pic
15.02-11-2016At plantTesting of BC mixLalit TiwariAEDEA ADB Nainital See Pic
16.02-11-2016At plantBitumen content testLalit TiwariAEDEA ADB Nainital See Pic
17.02-11-201683+200SE sir Site InspectionLalit TiwariAEDEA ADB Nainital See Pic
18.28-10-201679+0506.mSpan steel work in progressAnil KumarJEUEAP R&B Nainital See Pic
19.16-10-2016Chainage 80.400Inspection of Road at Chainage 80+400 by Chief Engg Haldwani which was settled during the rainy season .C E sir suggested treatment to be optedRajiv GururaniEEUEAP R&B Nainital See Pic
20.14-10-2016Chainage 80+425Checking crustRajiv GururaniEEUEAP R&B Nainital See Pic