Ramnagar Kaladungi Haldwani Kathgodam Chorgaliya Sitarganj Bijti MR Phase 4 (Km. 77 to 87.30)
Work Completed
|
Project: |
UEAP-RB |
UID: |
5915 |
Sanction Cost: |
1787.00 lakh |
Length:
|
11.300 KM. |
District: |
Nainital |
Block: |
Haldwani |
Constituency: |
Lalkuan |
Circle: |
|
DEA: |
DEA UEAP Nainital |
DSC: |
Sheladia Associates |
DSC Scope: |
Design and Supervision |
Type: |
SH |
|
Procurement: |
Package No.: 1098
Package Name: 
UEAP/PWD/C-83B
Tender Date: 30-01-2016
Current Status: Agreement signed
Achieved on Date: 02-04-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C-83B
Contractor Name: Raj Shyama Constructions Pvt. Ltd
|
Start Date: 12-04-2016
Intended Completion Date: 11-12-2016
|
Total Bond Cost: 114675232 (1146.75 lakh)
Variation Cost: 32316921.45 (323.17 lakh) Hence Total Bond Cost is 146992153.45 (1469.92 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 3360.00 m | 287.28 | 13-04-2016 | 06-12-2016 | 3360.00 m | 3360.00 m | 20.76 | 287.28 | 2. | PC/CC i/c Prime Coat, Tack Coat | 3.39 KM | 61.72 | 13-04-2016 | 15-10-2016 | 3.39 KM | 3.39 KM | 4.46 | 61.72 | 3. | BM i/c Prime Coat, Tack Coat | 11.30 KM | 687.69 | 13-04-2016 | 11-05-2016 | 11.30 KM | 11.30 KM | 49.7 | 687.69 | 4. | SDBC i/c Tackcoat | 11.30 KM | 194.85 | 15-05-2016 | 18-11-2016 | 11.30 KM | 11.30 KM | 14.08 | 194.85 | 5. | Cause Way | 3.00 No | 43.71 | 01-05-2016 | 18-10-2016 | 3.00 No | 3.00 No | 3.16 | 43.71 | 6. | Culverts/Scupper | 9.00 No | 77.14 | 01-05-2016 | 27-11-2016 | 8.00 No | 8.00 No | 5.57 | 77.14 | 7. | Crash Barrier | 1310.00 m | 29.48 | 01-07-2016 | 21-11-2016 | 1310.00 m | 1310.00 m | 2.13 | 29.48 | 8. | Road Furniture | 75.00 No | 1.88 | 21-11-2016 | 06-12-2016 | 75.00 No | 75.00 No | 0.14 | 1.88 |
Total Amount: |
1383.75 |
|
100 |
1383.75 |
|
Remarks:
No Remarks
Work Program Made On:
11-07-2016 } ?>
Updation of work program on:
25-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-April-2016 | 216.45 lakh | 2. | 31-May-2016 | 238.78 lakh | 3. | 02-June-2016 | 174.85 lakh | 4. | 23-June-2016 | 178.18 lakh | 5. | 31-August-2016 | 79.28 lakh | 6. | 27-October-2016 | 106.98 lakh | 7. | 28-November-2016 | 151.32 lakh | 8. | 28-February-2017 | 165.21 lakh | 9. | 25-March-2017 | 59.57 lakh | 10. | 30-May-2017 | 29.76 lakh | 11. | 22-June-2017 | 41.62 lakh |
Total |
1442 lakh |
% Payment |
98.09 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1531 No. of Test Done : 1532 No. of Test Passed : 1521 No. of Test Failed : 3 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 93.03 |
Number of Notice(s) issued: 28 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 41 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 28-12-2016 | Chainage 83+700 | Thermoplast work on the road | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
2. | 28-12-2016 | Chainage 84+900 | Thermoplast work on road | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
3. | 28-12-2016 | Chainage 80+400 | Culvert after completion | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
4. | 28-12-2016 | Chainage 80+400 | Culvert after completion | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
5. | 28-12-2016 | Chainage 76+400 | Thermoplast work is on | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
6. | 29-11-2016 | Chainage 80+400 | Checking Crust & Bituminous thickness at the affected area where road damaged | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
7. | 29-11-2016 | Chainage 77+400 | DBM work in the approaches of culverts is in progress | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
8. | 08-11-2016 | Chainage 85+450 | Inspection of thermoplast by SE Sir | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
9. | 08-11-2016 | Chainage 80+425 | SE sir inspection of portion that become uneven due to rains last month | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
10. | 02-11-2016 | At plant | Bitumen Content test for BC | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
11. | 02-11-2016 | 83+700 | Construction of Causeway | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
12. | 02-11-2016 | At Plant | Compressive Load | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
13. | 02-11-2016 | At Lab | Bitumen Content test | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
14. | 02-11-2016 | At Lab | Concrete cube weight .taking before loding for Compressive Test | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
15. | 02-11-2016 | At plant | Testing of BC mix | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
16. | 02-11-2016 | At plant | Bitumen content test | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
17. | 02-11-2016 | 83+200 | SE sir Site Inspection | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
18. | 28-10-2016 | 79+050 | 6.mSpan steel work in progress | Anil Kumar | JE | UEAP R&B Nainital | See Pic |
19. | 16-10-2016 | Chainage 80.400 | Inspection of Road at Chainage 80+400 by Chief Engg Haldwani which was settled during the rainy season .C E sir suggested treatment to be opted | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
20. | 14-10-2016 | Chainage 80+425 | Checking crust | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
|
|