Ramnagar Kaladungi Haldwani Kathgodam Chorgaliya Sitarganj Bijti MR Phase 2 (Km. 18 to 24 and Km. 29)
Work Completed
|
Project: |
UEAP-RB |
UID: |
5914 |
Sanction Cost: |
1093.00 lakh |
Length:
|
7.200 KM. |
District: |
Nainital |
Block: |
Kotabagh |
Constituency: |
Kaladhungi |
Circle: |
|
DEA: |
DEA UEAP Nainital |
DSC: |
Sheladia Associates |
DSC Scope: |
Design and Supervision |
Type: |
SH |
|
Procurement: |
Package No.: 1097
Package Name: 
UEAP/PWD/C-82B
Tender Date: 30-01-2016
Current Status: Agreement signed
Achieved on Date: 29-03-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C-82B
Contractor Name: PRL Projects and Infrastructure Ltd.
|
Start Date: 07-04-2016
Intended Completion Date: 06-12-2016
|
Total Bond Cost: 65769055 (657.69 lakh)
Variation Cost: 6175143.14 (61.75 lakh) Hence Total Bond Cost is 71944198.14 (719.44 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 200.00 m | 9.61 | 01-09-2016 | 30-11-2016 | 200.00 m | 200.00 m | 1.29 | 9.61 | 2. | G-3 | 0.20 KM | 8.10 | 01-06-2016 | 12-11-2016 | 0.20 KM | 0.20 KM | 1.09 | 8.10 | 3. | PC/CC i/c Prime Coat, Tack Coat | 0.20 KM | 0.24 | 01-05-2016 | 12-11-2016 | 0.20 KM | 0.20 KM | 0.03 | 0.24 | 4. | BM i/c Prime Coat, Tack Coat | 8.30 KM | 505.24 | 01-05-2016 | 15-11-2016 | 8.30 KM | 8.30 KM | 67.84 | 505.24 | 5. | SDBC i/c Tackcoat | 8.30 KM | 160.24 | 15-10-2016 | 16-11-2016 | 8.30 KM | 8.30 KM | 21.52 | 160.24 | 6. | Culverts/Scupper | 1.00 No | 5.30 | 01-05-2016 | 15-08-2016 | 1.00 No | 1.00 No | 0.71 | 5.30 | 7. | Crash Barrier | 100.00 m | 2.30 | 15-08-2016 | 20-11-2016 | 100.00 m | 100.00 m | 0.31 | 2.30 | 8. | Road Furniture | 9233.00 No | 28.07 | 01-11-2016 | 30-11-2016 | 9233.00 No | 9233.00 No | 3.77 | 28.07 | 9. | Other Allied Works & Finishing Work | 1.00 Job | 25.69 | 01-11-2016 | 30-11-2016 | 1.00 Job | 1.00 Job | 3.45 | 25.69 |
Total Amount: |
744.79 |
|
100 |
744.79 |
|
Remarks:
No Remarks
Work Program Made On:
11-07-2016 } ?>
Updation of work program on:
25-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 13-May-2016 | 118.22 lakh | 2. | 31-May-2016 | 116.70 lakh | 3. | 21-June-2016 | 58.51 lakh | 4. | 23-July-2016 | 155.00 lakh | 5. | 24-October-2016 | 135.56 lakh | 6. | 26-November-2016 | 41.28 lakh | 7. | 16-December-2016 | 18.08 lakh | 8. | 27-May-2017 | 41.57 lakh | 9. | 27-September-2017 | 33.36 lakh |
Total |
718.28 lakh |
% Payment |
99.83 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1116 No. of Test Done : 1117 No. of Test Passed : 1094 No. of Test Failed : 3 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.39 |
Number of Notice(s) issued: 31 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 33 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 09-06-2017 | Chainage 77.000 | Inspection of road by ADB officials | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
2. | 30-12-2016 | Chainage 19+900 | Excavation is being done for OFC for which permission accorded by Civil division.
May damage the surface as of stacking of excavated material on road surface
implementing agency as well as E E C D PWD informed accordingly for restoration of damages & to | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
3. | 30-12-2016 | Chainage 18+600 | Thermoplast work | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
4. | 20-12-2016 | Chainage 19+500 | Thermoplast work | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
5. | 09-12-2016 | 15.325 | Tile work inshoulder | Rajendra Prasad Sati | JE | UEAP R&B Nainital | See Pic |
6. | 08-12-2016 | Ch.23.400 R/S | Thermoplastic work on edge line in progress | Prakash Chandra Tewari | AE | UEAP R&B Nainital | See Pic |
7. | 05-12-2016 | Chronic Slip zone in km 1.00 of Ntl Bhowali Motor road | Concreting work in progress at 2nd lift at Chainage 0.02 | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
8. | 23-11-2016 | Chainage 85+400 | Hume pipe laid in the affected portion as per instruction given by C E Hld sir | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
9. | 08-11-2016 | Chainage 73+800 | S E sir inspection of works | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
10. | 14-10-2016 | Chainage 71+250 | Checking of camber by SE C C Joshi | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
11. | 14-10-2016 | Chainage 71+250 | C C Joshi S E inspecting ongoing work of B C | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
12. | 14-10-2016 | Chainage 68+050 | Inspection of Road by SE C C Joshi | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
13. | 14-10-2016 | Chainage 68+000 | interlocking tiling work inspection by En C C Joshi S E | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
14. | 13-10-2016 | 23.950 | BC work | Rajendra Prasad Sati | JE | UEAP R&B Nainital | See Pic |
15. | 11-10-2016 | 22.325 | BC work | Rajendra Prasad Sati | JE | UEAP R&B Nainital | See Pic |
16. | 06-10-2016 | Chainage 68+900 | Environmental test for ambient air monitoring | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
17. | 06-10-2016 | Chainage 66+500 | B C laying in progress | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
18. | 28-09-2016 | HMP at Dineshpur | B C mix checking at plant | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
19. | 22-09-2016 | chainage 68+100 | Interlocking tiling work in progress at Kuwar pur Chauraha | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
20. | 15-09-2016 | Chainage 72+650 | DBM 2nd layer laying started from today | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
|
|