Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Ramnagar Kaladungi Haldwani Kathgodam Chorgaliya Sitarganj Bijti MR Phase 2 (Km. 18 to 24 and Km. 29) Work Completed
Project: UEAP-RB UID: 5914 Sanction Cost: 1093.00  lakh Length: 7.200 KM.
District: Nainital Block: Kotabagh Constituency: Kaladhungi Circle:
DEA: DEA UEAP Nainital DSC: Sheladia Associates DSC Scope: Design and Supervision Type: SH
Procurement:
Package No.: 1097        Package Name:  UEAP/PWD/C-82B        Tender Date: 30-01-2016        Current Status: Agreement signed        Achieved on Date: 29-03-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C-82B      Contractor Name: PRL Projects and Infrastructure Ltd.
Start Date:  07-04-2016      Intended Completion Date:  06-12-2016     
Total Bond Cost: 65769055 (657.69 lakh)        Variation Cost: 6175143.14 (61.75 lakh)    Hence Total Bond Cost is   71944198.14 (719.44 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works200.00 m9.6101-09-201630-11-2016200.00 m200.00 m1.299.61
2.G-30.20 KM8.1001-06-201612-11-20160.20 KM0.20 KM1.098.10
3.PC/CC i/c Prime Coat, Tack Coat0.20 KM0.2401-05-201612-11-20160.20 KM0.20 KM0.030.24
4.BM i/c Prime Coat, Tack Coat8.30 KM505.2401-05-201615-11-20168.30 KM8.30 KM67.84505.24
5.SDBC i/c Tackcoat8.30 KM160.2415-10-201616-11-20168.30 KM8.30 KM21.52160.24
6.Culverts/Scupper 1.00 No5.3001-05-201615-08-20161.00 No1.00 No0.715.30
7.Crash Barrier100.00 m2.3015-08-201620-11-2016100.00 m100.00 m0.312.30
8.Road Furniture9233.00 No28.0701-11-201630-11-20169233.00 No9233.00 No3.7728.07
9.Other Allied Works & Finishing Work 1.00 Job25.6901-11-201630-11-20161.00 Job1.00 Job3.4525.69
Total Amount: 744.79 100   744.79
Remarks: No Remarks       Work Program Made On: 11-07-2016        Updation of work program on: 25-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.13-May-2016118.22  lakh
2.31-May-2016116.70  lakh
3.21-June-201658.51  lakh
4.23-July-2016155.00  lakh
5.24-October-2016135.56  lakh
6.26-November-201641.28  lakh
7.16-December-201618.08  lakh
8.27-May-201741.57  lakh
9.27-September-201733.36  lakh
Total 718.28  lakh
% Payment 99.83 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1116   No. of Test Done : 1117    No. of Test Passed : 1094   No. of Test Failed : 3   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.39
Number of Notice(s) issued: 31

Mobile Pic Upload

Number of Pics Available on Web Repository: 33
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.09-06-2017Chainage 77.000Inspection of road by ADB officialsRajiv GururaniEEUEAP R&B Nainital See Pic
2.30-12-2016Chainage 19+900Excavation is being done for OFC for which permission accorded by Civil division. May damage the surface as of stacking of excavated material on road surface implementing agency as well as E E C D PWD informed accordingly for restoration of damages & to Rajiv GururaniEEUEAP R&B Nainital See Pic
3.30-12-2016Chainage 18+600Thermoplast workRajiv GururaniEEUEAP R&B Nainital See Pic
4.20-12-2016Chainage 19+500Thermoplast workRajiv GururaniEEUEAP R&B Nainital See Pic
5.09-12-201615.325Tile work inshoulderRajendra Prasad SatiJEUEAP R&B Nainital See Pic
6.08-12-2016Ch.23.400 R/SThermoplastic work on edge line in progressPrakash Chandra TewariAEUEAP R&B Nainital See Pic
7.05-12-2016Chronic Slip zone in km 1.00 of Ntl Bhowali Motor roadConcreting work in progress at 2nd lift at Chainage 0.02Rajiv GururaniEEUEAP R&B Nainital See Pic
8.23-11-2016Chainage 85+400Hume pipe laid in the affected portion as per instruction given by C E Hld sirRajiv GururaniEEUEAP R&B Nainital See Pic
9.08-11-2016Chainage 73+800S E sir inspection of worksRajiv GururaniEEUEAP R&B Nainital See Pic
10.14-10-2016Chainage 71+250Checking of camber by SE C C JoshiRajiv GururaniEEUEAP R&B Nainital See Pic
11.14-10-2016Chainage 71+250C C Joshi S E inspecting ongoing work of B CRajiv GururaniEEUEAP R&B Nainital See Pic
12.14-10-2016Chainage 68+050Inspection of Road by SE C C JoshiRajiv GururaniEEUEAP R&B Nainital See Pic
13.14-10-2016Chainage 68+000interlocking tiling work inspection by En C C Joshi S ERajiv GururaniEEUEAP R&B Nainital See Pic
14.13-10-201623.950BC workRajendra Prasad SatiJEUEAP R&B Nainital See Pic
15.11-10-201622.325BC workRajendra Prasad SatiJEUEAP R&B Nainital See Pic
16.06-10-2016Chainage 68+900Environmental test for ambient air monitoringRajiv GururaniEEUEAP R&B Nainital See Pic
17.06-10-2016Chainage 66+500B C laying in progressRajiv GururaniEEUEAP R&B Nainital See Pic
18.28-09-2016HMP at DineshpurB C mix checking at plantRajiv GururaniEEUEAP R&B Nainital See Pic
19.22-09-2016chainage 68+100Interlocking tiling work in progress at Kuwar pur ChaurahaRajiv GururaniEEUEAP R&B Nainital See Pic
20.15-09-2016Chainage 72+650DBM 2nd layer laying started from todayRajiv GururaniEEUEAP R&B Nainital See Pic