Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Nainital Bhowali Motor Road (Chronic Slip Zone) Work Completed
Project: UEAP-RB UID: 5913 Sanction Cost: 274.00  lakh Length: 0.060 KM.
District: Nainital Block: Bhimtal Constituency: Nainital Circle:
DEA: DEA UEAP Nainital DSC: CCEE Group India Pvt.Ltd DSC Scope: Design and Supervision Type: ODR
Procurement:
Package No.: 1093        Package Name:  UEAP/PWD/C89        Tender Date: 03-09-2015        Current Status: Agreement signed        Achieved on Date: 02-04-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C89      Contractor Name: Bharat Construction
Start Date:  23-04-2016      Intended Completion Date:  31-05-2017      Original End Date:  22-02-2017
Total Bond Cost: 26158475 (261.58 lakh)        Variation Cost: -252579.59 (-2.53 lakh)    Hence Total Bond Cost is   25905895.41 (259.06 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 353133 for 27 days        LD Analysis for Milestone2: calculated LD is Rs 797819 for 61 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works40.00 m233.0112-09-201620-03-201740.00 m40.00 m89.67233.01
2.longitudinal Drain100.00 m6.0015-01-201725-05-2017100.00 m100.00 m2.316.00
3.Other Allied Works & Finishing Work 29.00 Job20.8315-04-201730-05-201729.00 Job29.00 Job8.0220.83
Total Amount: 259.84 100   259.84
Remarks: No Remarks       Work Program Made On: 05-09-2016        Updation of work program on: 20-07-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.14-December-201695.63  lakh
2.04-February-201763.14  lakh
3.24-March-201729.78  lakh
4.22-April-201724.95  lakh
5.27-June-201719.62  lakh
Total 233.12  lakh
% Payment 89.98 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 72   No. of Test Done : 72    No. of Test Passed : 72   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 87.50
Number of Notice(s) issued: 49

Mobile Pic Upload

Number of Pics Available on Web Repository: 26
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.10-06-2017Chronic Slip Zone treatment work at Ntl Bhowali motor road km 1Inspection of site by Sr Manager Mr Vikas Chauhan THDC RishikeshRajiv GururaniEEUEAP R&B Nainital See Pic
2.29-05-2017Chronic Slip zone treatment work at Nainital Bhowali motor road km 1Site inspection of treatment work by the team of ADB officials Dr P Sahu & Dr RajuRajiv GururaniEEUEAP R&B Nainital See Pic
3.28-05-2017Chronic slip zone treatment work at Ntl Bhowali motor road km1Site inspection of works by THDC officials Mr Vikash Chauhan & Mr J R KothariRajiv GururaniEEUEAP R&B Nainital See Pic
4.23-05-2017Chronic Slip Zone treatment work Ntl Bhowali Motor road Km 1Excavation in progress for toe wallRajiv GururaniEEUEAP R&B Nainital See Pic
5.27-03-2017Chronic Slip Zone treatment work at Ntl Bhowali motor road package C -89RETAINING WALL WORK IN PROGRESSRajiv GururaniEEUEAP R&B Nainital See Pic
6.04-03-2017Chronic slip zone treatment work at km 1 of Nainital Bhowali motor roadInspection of worksRajiv GururaniEEUEAP R&B Nainital See Pic
7.17-02-2017Chronic slip zone treatment work at km 1 of Ntl Bhowali motor roadInspection of site & Layout for R/WallRajiv GururaniEEUEAP R&B Nainital See Pic
8.10-02-2017Chronic Slip zone treatment work in km 1 of Ntl Bhowali motor roadPull out test for anchor bars grouted deep 9.00 m in rockRajiv GururaniEEUEAP R&B Nainital See Pic
9.10-02-2017Chronic Slip zone treatment at Ntl Bhowali motor road km1Pull out test being carried out for the grouted 32 mm dia bar 9.00 m deep in hill sideRajiv GururaniEEUEAP R&B Nainital See Pic
10.07-02-2017Chronic Slip Zone at NTL Bhowali motor roadInspection by SE PIU Er CCJoshiRajiv GururaniEEUEAP R&B Nainital See Pic
11.07-02-2017Chronic Slip Zone at NTL Bhowali motor roadwork in progressRajiv GururaniEEUEAP R&B Nainital See Pic
12.07-02-2017Chronic slip zone treatment in NTL Bhowali motor road km1Inspection of worksRajiv GururaniEEUEAP R&B Nainital See Pic
13.29-12-20161+040Concrete work in progressAnil KumarJEUEAP R&B Nainital See Pic
14.28-12-2016Chronic Slip Zone at NTL Bhowali motor roadConcreting work in progressRajiv GururaniEEUEAP R&B Nainital See Pic
15.15-12-2016Chainage 0+010preparayion for Concreting work at the lowest point 22.00 below the road levelRajiv GururaniEEUEAP R&B Nainital See Pic
16.29-11-2016Chronic slip zone at Bhowali roadfixing of 32mm dia anchor bar in rockRajiv GururaniEEUEAP R&B Nainital See Pic
17.24-11-2016Chronic Slip zone Ntl - Bhowali Motor Roadinspection of worksRajiv GururaniEEUEAP R&B Nainital See Pic
18.21-11-2016Chronic slip zone site at km 1.00 in Nainital Bhowali Motor RoadPreparation of shuttering work for concretingRajiv GururaniEEUEAP R&B Nainital See Pic
19.08-11-2016chronic slip zone site Nainital Bhowali Motor RoadSE sir visit of site for inspecting drilling workRajiv GururaniEEUEAP R&B Nainital See Pic
20.27-10-2016Chainage km 1Inspection of ongoing work by Mr Sanjay Shinghal from THDC RishikeshRajiv GururaniEEUEAP R&B Nainital See Pic