Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Ramnagar Kaladungi Haldwani Kathgodam Chorgaliya Sitarganj Bijti MR PHASE 1 (Km 5 TO 14 Km) Work Completed
Project: UEAP-RB UID: 5911 Sanction Cost: 1554.00  lakh Length: 10.000 KM.
District: Nainital Block: Kotabagh Constituency: Kaladhungi Circle:
DEA: DEA UEAP Nainital DSC: CCEE Group India Pvt.Ltd DSC Scope: Design and Supervision Type: SH
Procurement:
Package No.: 1086        Package Name:  UEAP/PWD/C-82A        Tender Date: 30-01-2016        Current Status: Agreement signed        Achieved on Date: 29-03-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C-82A      Contractor Name: PRL Projects and Infrastructure Ltd.
Start Date:  07-04-2016      Intended Completion Date:  06-12-2016     
Total Bond Cost: 94907998 (949.08 lakh)        Variation Cost: 5673055.12 (56.73 lakh)    Hence Total Bond Cost is   100581053.12 (1005.81 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works150.00 m10.5215-09-201615-10-2016150.00 m150.00 m1.1810.52
2.BM i/c Prime Coat, Tack Coat13.80 KM640.8113-04-201604-08-201613.80 KM13.80 KM71.57640.81
3.SDBC i/c Tackcoat11.00 KM199.2121-06-201615-10-201611.00 KM11.00 KM22.25199.21
4.Cause Way2.00 No8.8908-04-201615-10-20162.00 No2.00 No0.998.89
5.Culverts/Scupper 3.00 No9.0716-04-201630-06-20163.00 No3.00 No1.019.07
6.Crash Barrier300.00 m6.9001-10-201630-11-2016300.00 m300.00 m0.776.90
7.Road Furniture3700.00 No2.0001-10-201630-10-20163700.00 No3700.00 No0.222.00
8.Other Allied Works & Finishing Work 110.00 Job18.0001-10-201630-10-2016110.00 Job110.00 Job2.0118.00
Total Amount: 895.4 100   895.4
Remarks: No Remarks       Work Program Made On: 17-06-2016        Updation of work program on: 04-11-2016       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-April-2016199.50  lakh
2.13-May-201683.63  lakh
3.31-May-2016198.97  lakh
4.21-June-201695.40  lakh
5.30-September-2016123.02  lakh
6.10-October-201692.50  lakh
7.26-November-201658.08  lakh
8.16-December-201626.56  lakh
9.23-February-201759.86  lakh
10.30-May-201733.79  lakh
11.22-June-201710.66  lakh
12.26-September-201722.28  lakh
Total 1004.25  lakh
% Payment 99.83 %
Advance Amount:  94.91  lakh        Recovered Amount:  94.91  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1543   No. of Test Done : 1543    No. of Test Passed : 1519   No. of Test Failed : 1   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 92.44
Number of Notice(s) issued: 31

Mobile Pic Upload

Number of Pics Available on Web Repository: 52
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.30-12-2016Chainage 13+250Shoulder protection with Interlocking tilesRajiv GururaniEEUEAP R&B Nainital See Pic
2.30-12-2016Chainage 12+680Thermoplast work at start of BelparauRajiv GururaniEEUEAP R&B Nainital See Pic
3.09-12-201614..250Thermoplast paintRajendra Prasad SatiJEUEAP R&B Nainital See Pic
4.09-12-2016Ch 6.142 to 5.879Tile work in shoulder both side near Choi ChowkRajendra Prasad SatiJEUEAP R&B Nainital See Pic
5.09-12-2016Ch 5.879 to 6.142 both side near ChoiTile work in shoulder protection near ChoiRajendra Prasad SatiJEUEAP R&B Nainital See Pic
6.09-12-2016CH 5.879 to 6.142 in ChoiTile work in shoulder protectionRajendra Prasad SatiJEUEAP R&B Nainital See Pic
7.09-12-2016CH 4.775. RHS sideTile work in shoulder protectionRajendra Prasad SatiJEUEAP R&B Nainital See Pic
8.08-11-2016Choi Chauraha ChainageSE sir inspection of RoadRajiv GururaniEEUEAP R&B Nainital See Pic
9.02-11-201611+800Reinforcement Binding before Concrete work checked by SE Sir UEAP DehradunLalit TiwariAEDEA ADB Nainital See Pic
10.02-11-20166+035Checking of RBM Thickness by SE sir UEAP DehradunLalit TiwariAEDEA ADB Nainital See Pic
11.02-11-20166+020Camber checking by SE sir UEAP DehradunLalit TiwariAEDEA ADB Nainital See Pic
12.02-11-20169+500Social Expert site visitLalit TiwariAEDEA ADB Nainital See Pic
13.02-11-20169+900Camber Checking by Chief Engineer SirLalit TiwariAEDEA ADB Nainital See Pic
14.02-11-20169+950Chief Engineer sir visitLalit TiwariAEDEA ADB Nainital See Pic
15.02-11-20169+930CE sir visitLalit TiwariAEDEA ADB Nainital See Pic
16.02-11-20169+930CE sir VisitLalit TiwariAEDEA ADB Nainital See Pic
17.02-11-2016At plantBC Grading TestLalit TiwariAEDEA ADB Nainital See Pic
18.02-11-20166+020Core cutting DBMLalit TiwariAEDEA ADB Nainital See Pic
19.02-11-2016at kamolaPlantation on road sideLalit TiwariAEDEA ADB Nainital See Pic
20.02-11-20166+300Thickness checking of DB MLalit TiwariAEDEA ADB Nainital See Pic