Ramnagar Kaladungi Haldwani Kathgodam Chorgaliya Sitarganj Bijti MR PHASE 1 (Km 5 TO 14 Km)
Work Completed
|
Project: |
UEAP-RB |
UID: |
5911 |
Sanction Cost: |
1554.00 lakh |
Length:
|
10.000 KM. |
District: |
Nainital |
Block: |
Kotabagh |
Constituency: |
Kaladhungi |
Circle: |
|
DEA: |
DEA UEAP Nainital |
DSC: |
CCEE Group India Pvt.Ltd |
DSC Scope: |
Design and Supervision |
Type: |
SH |
|
Procurement: |
Package No.: 1086
Package Name: 
UEAP/PWD/C-82A
Tender Date: 30-01-2016
Current Status: Agreement signed
Achieved on Date: 29-03-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C-82A
Contractor Name: PRL Projects and Infrastructure Ltd.
|
Start Date: 07-04-2016
Intended Completion Date: 06-12-2016
|
Total Bond Cost: 94907998 (949.08 lakh)
Variation Cost: 5673055.12 (56.73 lakh) Hence Total Bond Cost is 100581053.12 (1005.81 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 150.00 m | 10.52 | 15-09-2016 | 15-10-2016 | 150.00 m | 150.00 m | 1.18 | 10.52 | 2. | BM i/c Prime Coat, Tack Coat | 13.80 KM | 640.81 | 13-04-2016 | 04-08-2016 | 13.80 KM | 13.80 KM | 71.57 | 640.81 | 3. | SDBC i/c Tackcoat | 11.00 KM | 199.21 | 21-06-2016 | 15-10-2016 | 11.00 KM | 11.00 KM | 22.25 | 199.21 | 4. | Cause Way | 2.00 No | 8.89 | 08-04-2016 | 15-10-2016 | 2.00 No | 2.00 No | 0.99 | 8.89 | 5. | Culverts/Scupper | 3.00 No | 9.07 | 16-04-2016 | 30-06-2016 | 3.00 No | 3.00 No | 1.01 | 9.07 | 6. | Crash Barrier | 300.00 m | 6.90 | 01-10-2016 | 30-11-2016 | 300.00 m | 300.00 m | 0.77 | 6.90 | 7. | Road Furniture | 3700.00 No | 2.00 | 01-10-2016 | 30-10-2016 | 3700.00 No | 3700.00 No | 0.22 | 2.00 | 8. | Other Allied Works & Finishing Work | 110.00 Job | 18.00 | 01-10-2016 | 30-10-2016 | 110.00 Job | 110.00 Job | 2.01 | 18.00 |
Total Amount: |
895.4 |
|
100 |
895.4 |
|
Remarks:
No Remarks
Work Program Made On:
17-06-2016 } ?>
Updation of work program on:
04-11-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-April-2016 | 199.50 lakh | 2. | 13-May-2016 | 83.63 lakh | 3. | 31-May-2016 | 198.97 lakh | 4. | 21-June-2016 | 95.40 lakh | 5. | 30-September-2016 | 123.02 lakh | 6. | 10-October-2016 | 92.50 lakh | 7. | 26-November-2016 | 58.08 lakh | 8. | 16-December-2016 | 26.56 lakh | 9. | 23-February-2017 | 59.86 lakh | 10. | 30-May-2017 | 33.79 lakh | 11. | 22-June-2017 | 10.66 lakh | 12. | 26-September-2017 | 22.28 lakh |
Total |
1004.25 lakh |
% Payment |
99.83 % |
|
Advance Amount: 94.91 lakh
Recovered Amount: 94.91 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1543 No. of Test Done : 1543 No. of Test Passed : 1519 No. of Test Failed : 1 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 92.44 |
Number of Notice(s) issued: 31 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 52 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 30-12-2016 | Chainage 13+250 | Shoulder protection with Interlocking tiles | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
2. | 30-12-2016 | Chainage 12+680 | Thermoplast work at start of Belparau | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
3. | 09-12-2016 | 14..250 | Thermoplast paint | Rajendra Prasad Sati | JE | UEAP R&B Nainital | See Pic |
4. | 09-12-2016 | Ch 6.142 to 5.879 | Tile work in shoulder both side near Choi Chowk | Rajendra Prasad Sati | JE | UEAP R&B Nainital | See Pic |
5. | 09-12-2016 | Ch 5.879 to 6.142 both side near Choi | Tile work in shoulder protection near Choi | Rajendra Prasad Sati | JE | UEAP R&B Nainital | See Pic |
6. | 09-12-2016 | CH 5.879 to 6.142 in Choi | Tile work in shoulder protection | Rajendra Prasad Sati | JE | UEAP R&B Nainital | See Pic |
7. | 09-12-2016 | CH 4.775. RHS side | Tile work in shoulder protection | Rajendra Prasad Sati | JE | UEAP R&B Nainital | See Pic |
8. | 08-11-2016 | Choi Chauraha Chainage | SE sir inspection of Road | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
9. | 02-11-2016 | 11+800 | Reinforcement Binding before Concrete work checked by SE Sir UEAP Dehradun | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
10. | 02-11-2016 | 6+035 | Checking of RBM Thickness by SE sir UEAP Dehradun | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
11. | 02-11-2016 | 6+020 | Camber checking by SE sir UEAP Dehradun | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
12. | 02-11-2016 | 9+500 | Social Expert site visit | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
13. | 02-11-2016 | 9+900 | Camber Checking by Chief Engineer Sir | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
14. | 02-11-2016 | 9+950 | Chief Engineer sir visit | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
15. | 02-11-2016 | 9+930 | CE sir visit | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
16. | 02-11-2016 | 9+930 | CE sir Visit | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
17. | 02-11-2016 | At plant | BC Grading Test | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
18. | 02-11-2016 | 6+020 | Core cutting DBM | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
19. | 02-11-2016 | at kamola | Plantation on road side | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
20. | 02-11-2016 | 6+300 | Thickness checking of DB M | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
|
|