Ranibag Bhimtal Khutani Padampuri Motiyapathar Lohaghat Motor Road
Work Completed
|
Project: |
UEAP-RB |
UID: |
5908 |
Sanction Cost: |
2462.00 lakh |
Length:
|
51.000 KM. |
District: |
Nainital |
Block: |
Dhari |
Constituency: |
Bhimtal |
Circle: |
|
DEA: |
DEA UEAP Nainital |
DSC: |
CCEE Group India Pvt.Ltd |
DSC Scope: |
Design & Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1078
Package Name: 
UEAP/PWD/C-74
Tender Date: 06-01-2015
Current Status: Agreement signed
Achieved on Date: 30-05-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C-74
Contractor Name: Woodhill Infrastructure Ltd
|
Start Date: 20-06-2015
Intended Completion Date: 19-03-2017
|
Total Bond Cost: 192214376 (1922.14 lakh)
Variation Cost: 47106892.06 (471.07 lakh) Hence Total Bond Cost is 239321268.06 (2393.21 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 1633819 for 17 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.19 KM | 4.06 | 01-10-2015 | 28-10-2016 | 0.19 KM | 0.19 KM | 0.17 | 4.06 | 2. | R/Wall, B/ Wall Type Protection works | 3040.00 m | 208.12 | 20-06-2015 | 15-02-2017 | 3040.00 m | 3040.00 m | 8.76 | 208.12 | 3. | GSB/RBI/G-1 | 0.35 KM | 1.80 | 10-01-2016 | 16-09-2016 | 0.35 KM | 0.35 KM | 0.08 | 1.80 | 4. | G-2 | 1.88 KM | 11.50 | 10-01-2016 | 10-10-2016 | 1.40 KM | 1.40 KM | 0.48 | 11.50 | 5. | G-3 | 2.00 KM | 11.29 | 10-01-2016 | 15-10-2016 | 1.40 KM | 1.40 KM | 0.48 | 11.29 | 6. | BM i/c Prime Coat, Tack Coat | 23.00 KM | 487.37 | 01-04-2016 | 15-10-2016 | 23.00 KM | 23.00 KM | 20.52 | 487.37 | 7. | SDBC i/c Tackcoat | 46.50 KM | 723.70 | 01-10-2015 | 20-10-2016 | 47.50 KM | 47.50 KM | 30.48 | 723.70 | 8. | Cause Way | 11.00 No | 36.50 | 01-09-2015 | 10-10-2016 | 11.00 No | 11.00 No | 1.54 | 36.50 | 9. | Culverts/Scupper | 16.00 No | 32.00 | 01-09-2015 | 20-09-2016 | 16.00 No | 16.00 No | 1.35 | 32.00 | 10. | longitudinal Drain | 46000.00 m | 468.00 | 01-09-2015 | 15-02-2017 | 46733.00 m | 46733.00 m | 19.71 | 468.00 | 11. | Crash Barrier | 7406.00 m | 207.37 | 01-04-2016 | 15-02-2017 | 4827.00 m | 4827.00 m | 8.73 | 207.37 | 12. | Parapet | 200.00 No | 8.00 | 01-05-2016 | 31-01-2017 | 41.00 No | 41.00 No | 0.34 | 8.00 | 13. | Road Furniture | 11500.00 No | 75.00 | 15-10-2016 | 15-03-2017 | 5163.00 No | 5163.00 No | 3.16 | 75.00 | 14. | Other Allied Works & Finishing Work | 5.00 Job | 100.00 | 30-10-2016 | 15-03-2017 | 105.00 Job | 105.00 Job | 4.21 | 100.00 |
Total Amount: |
2374.71 |
|
100 |
2374.71 |
|
Remarks:
No Remarks
Work Program Made On:
31-07-2015 } ?>
Updation of work program on:
21-06-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 15-September-2015 | 41.05 lakh | 2. | 29-October-2015 | 131.57 lakh | 3. | 30-November-2015 | 88.07 lakh | 4. | 31-December-2015 | 35.34 lakh | 5. | 30-January-2016 | 61.37 lakh | 6. | 29-February-2016 | 141.01 lakh | 7. | 21-March-2016 | 112.33 lakh | 8. | 31-March-2016 | 135.71 lakh | 9. | 29-April-2016 | 68.21 lakh | 10. | 06-June-2016 | 214.95 lakh | 11. | 28-July-2016 | 266.93 lakh | 12. | 31-August-2016 | 155.64 lakh | 13. | 26-October-2016 | 481.16 lakh | 14. | 28-November-2016 | 54.66 lakh | 15. | 16-December-2016 | 86.74 lakh | 16. | 27-February-2017 | 118.71 lakh | 17. | 24-April-2017 | 92.56 lakh | 18. | 30-May-2017 | 45.82 lakh | 19. | 28-July-2017 | 50.52 lakh | 20. | 25-September-2017 | 9.44 lakh |
Total |
2391.79 lakh |
% Payment |
99.92 % |
|
Advance Amount: 190.00 lakh
Recovered Amount: 190.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 6687 No. of Test Done : 6717 No. of Test Passed : 6630 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.97 |
Number of Notice(s) issued: 73 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 96 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 07-02-2017 | Chainage 6+400 | Work after completion at Salri | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
2. | 07-02-2017 | Chainage 27+850 | Slip zone treatment with wire crate & flexeble interlocking tiles | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
3. | 22-12-2016 | Chainage 6× | Jacketing work in progress at Salari | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
4. | 29-11-2016 | 39.062 | Road Inspection and checking by NH Chief Haldwani E.AyzazAhmad | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
5. | 08-11-2016 | Ch 6+300 | RCC jacketing in progress | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
6. | 02-11-2016 | 32+200 | BC laying in Progress | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
7. | 02-11-2016 | At plant | Bitumen Test By DSC staff | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
8. | 02-11-2016 | 21+800 | SE sir Site Inspection of Road | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
9. | 14-10-2016 | inspection of protection work at sladi Chainage 6+150 | SE C C Joshi inspection | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
10. | 06-10-2016 | Chainage 6+300 | Checking of concrete pavement by En S K Birla CE | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
11. | 20-09-2016 | Chainage 19+500 | shoulder protection work in progress | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
12. | 15-09-2016 | Chainage 19+700 | Shoulder protection work in progress | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
13. | 15-09-2016 | Chainage 23+100 | Approach of cause way in progress | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
14. | 15-09-2016 | chainage 19+950 | K C Drain with Sholder concrete started near Khutani | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
15. | 24-08-2016 | chainage 50+270 | core cutting for thickness checking thickness found 30mm in this core | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
16. | 14-07-2016 | Chainage 6+400 | Rectification of damaged concrete panel (removal of concrete) | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
17. | 07-07-2016 | Chainage 52.150 | SE sir Checking thickness of B C surface | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
18. | 06-06-2016 | Chainage 6+520 | Concreting work is on in Salari | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
19. | 06-06-2016 | Chainage 11+950 | Construction of R/Wall damaged in the heavy rains on 29th may 2016 | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
20. | 02-06-2016 | Chainage 20+500 | B C laying in progress | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
|
|