Ratighat-Betalghat Motor Road
Work Completed
|
Project: |
UEAP-RB |
UID: |
5905 |
Sanction Cost: |
1226.00 lakh |
Length:
|
19.000 KM. |
District: |
Nainital |
Block: |
Betalghat |
Constituency: |
Nainital |
Circle: |
|
DEA: |
DEA UEAP Nainital |
DSC: |
CCEE Group India Pvt.Ltd |
DSC Scope: |
Design & Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1077
Package Name: 
UEAP/PWD/C-73
Tender Date: 06-01-2015
Current Status: Agreement signed
Achieved on Date: 13-04-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C-73
Contractor Name: Woodhill Infrastructure Ltd
|
Start Date: 07-05-2015
Intended Completion Date: 06-11-2016
|
Total Bond Cost: 106054285 (1060.54 lakh)
Variation Cost: 15772285.00 (157.72 lakh) Hence Total Bond Cost is 121826570 (1218.27 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 159081 for 3 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.40 KM | 8.50 | 29-05-2015 | 03-09-2016 | 0.58 KM | 0.58 KM | 0.9 | 8.50 | 2. | R/Wall, B/ Wall Type Protection works | 1523.00 m | 71.25 | 16-05-2015 | 03-11-2016 | 1874.00 m | 1874.00 m | 7.58 | 71.25 | 3. | GSB/RBI/G-1 | 0.40 KM | 2.15 | 01-09-2015 | 29-12-2015 | 0.20 KM | 0.20 KM | 0.23 | 2.15 | 4. | G-2 | 0.48 KM | 6.57 | 01-09-2015 | 01-10-2015 | 1.50 KM | 1.50 KM | 0.7 | 6.57 | 5. | G-3 | 5.88 KM | 31.77 | 01-09-2015 | 13-12-2016 | 7.60 KM | 7.60 KM | 3.38 | 31.77 | 6. | BM i/c Prime Coat, Tack Coat | 19.00 KM | 283.87 | 01-10-2015 | 21-06-2016 | 19.00 KM | 19.00 KM | 30.19 | 283.87 | 7. | SDBC i/c Tackcoat | 19.00 KM | 249.57 | 15-10-2015 | 26-06-2016 | 19.00 KM | 19.00 KM | 26.54 | 249.57 | 8. | Cause Way | 11.00 No | 40.02 | 11-06-2015 | 02-11-2016 | 10.00 No | 10.00 No | 4.26 | 40.02 | 9. | Culverts/Scupper | 25.00 No | 38.51 | 16-05-2015 | 11-08-2016 | 25.00 No | 25.00 No | 4.1 | 38.51 | 10. | longitudinal Drain | 6518.00 m | 58.66 | 01-07-2015 | 23-10-2016 | 7047.00 m | 7047.00 m | 6.24 | 58.66 | 11. | Crash Barrier | 2732.00 m | 84.69 | 01-01-2016 | 25-10-2016 | 2732.00 m | 2732.00 m | 9.01 | 84.69 | 12. | Parapet | 603.00 No | 54.24 | 01-06-2016 | 29-10-2016 | 250.00 No | 250.00 No | 5.77 | 54.24 | 13. | Road Furniture | 48.00 No | 2.53 | 15-06-2016 | 30-10-2016 | 186.00 No | 186.00 No | 0.27 | 2.53 | 14. | Other Allied Works & Finishing Work | 9.00 Job | 8.00 | 01-06-2016 | 30-09-2016 | 9.00 Job | 9.00 Job | 0.85 | 8.00 |
Total Amount: |
940.33 |
|
100 |
940.33 |
|
Remarks:
No Remarks
Work Program Made On:
31-07-2015 } ?>
Updation of work program on:
25-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 25-July-2015 | 42.26 lakh | 2. | 19-September-2015 | 60.97 lakh | 3. | 20-October-2015 | 70.85 lakh | 4. | 28-November-2015 | 72.55 lakh | 5. | 31-December-2015 | 32.42 lakh | 6. | 29-February-2016 | 35.65 lakh | 7. | 31-March-2016 | 84.21 lakh | 8. | 29-April-2016 | 107.49 lakh | 9. | 23-May-2016 | 117.90 lakh | 10. | 20-June-2016 | 142.72 lakh | 11. | 26-July-2016 | 152.64 lakh | 12. | 29-September-2016 | 71.56 lakh | 13. | 27-October-2016 | 21.58 lakh | 14. | 28-February-2017 | 24.64 lakh | 15. | 19-June-2017 | 35.35 lakh | 16. | 11-October-2017 | 15.48 lakh |
Total |
1088.27 lakh |
% Payment |
89.32 % |
|
Advance Amount: 105.00 lakh
Recovered Amount: 105.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1144 No. of Test Done : 1146 No. of Test Passed : 1111 No. of Test Failed : 27 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.46 |
Number of Notice(s) issued: 73 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 46 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 02-11-2016 | 23+400 | BM laying in progress | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
2. | 28-06-2016 | Chainage 30+700 | Road after B C | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
3. | 28-06-2016 | Chainage 31+400 | Road after completion | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
4. | 29-05-2016 | Chainage 18+200 | Plum concrete at cause way | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
5. | 13-05-2016 | | BM work in progress | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
6. | 13-05-2016 | 21+350 | B C work with side kutcha drain | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
7. | 18-03-2016 | 19+800 | BM Laying | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
8. | 18-03-2016 | 18+600 | Plum wall | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
9. | 17-03-2016 | Chainage 19+950 | B M work started from km 20 | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
10. | 17-03-2016 | Chainage 19+850 | BM work in progress | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
11. | 04-03-2016 | Chainage15+200 | Sprinkling water on W B M | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
12. | 13-01-2016 | Chainage 15+600 | Sub Base preparation for B M at undulations & depressed portion | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
13. | 19-08-2015 | Chainage 0+200 | B/wall construction | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
14. | 11-08-2015 | 23+000 | Construction of B/W | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
15. | 11-08-2015 | 16+450 | Construction of R/W | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
16. | 11-08-2015 | 15+025 | Construction of U Type Side Drain | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
17. | 10-08-2015 | 0+230 | Construction of B/W | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
18. | 24-07-2015 | 24-650 | Selep clering | Anil Kumar | JE | UEAP R&B Nainital | See Pic |
19. | 22-07-2015 | 21-200 | Selep clering | Anil Kumar | JE | UEAP R&B Nainital | See Pic |
20. | 16-07-2015 | 21.200 | Land slide/slip clrarence/Opening communication | Rajendra Prasad Sati | JE | UEAP R&B Nainital | See Pic |
|
|