Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Ratighat-Betalghat Motor Road Work Completed
Project: UEAP-RB UID: 5905 Sanction Cost: 1226.00  lakh Length: 19.000 KM.
District: Nainital Block: Betalghat Constituency: Nainital Circle:
DEA: DEA UEAP Nainital DSC: CCEE Group India Pvt.Ltd DSC Scope: Design & Supervision Type: MDR
Procurement:
Package No.: 1077        Package Name:  UEAP/PWD/C-73        Tender Date: 06-01-2015        Current Status: Agreement signed        Achieved on Date: 13-04-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C-73      Contractor Name: Woodhill Infrastructure Ltd
Start Date:  07-05-2015      Intended Completion Date:  06-11-2016     
Total Bond Cost: 106054285 (1060.54 lakh)        Variation Cost: 15772285.00 (157.72 lakh)    Hence Total Bond Cost is   121826570 (1218.27 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 159081 for 3 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.40 KM8.5029-05-201503-09-20160.58 KM0.58 KM0.98.50
2.R/Wall, B/ Wall Type Protection works1523.00 m71.2516-05-201503-11-20161874.00 m1874.00 m7.5871.25
3.GSB/RBI/G-10.40 KM2.1501-09-201529-12-20150.20 KM0.20 KM0.232.15
4.G-20.48 KM6.5701-09-201501-10-20151.50 KM1.50 KM0.76.57
5.G-35.88 KM31.7701-09-201513-12-20167.60 KM7.60 KM3.3831.77
6.BM i/c Prime Coat, Tack Coat19.00 KM283.8701-10-201521-06-201619.00 KM19.00 KM30.19283.87
7.SDBC i/c Tackcoat19.00 KM249.5715-10-201526-06-201619.00 KM19.00 KM26.54249.57
8.Cause Way11.00 No40.0211-06-201502-11-201610.00 No10.00 No4.2640.02
9.Culverts/Scupper 25.00 No38.5116-05-201511-08-201625.00 No25.00 No4.138.51
10.longitudinal Drain6518.00 m58.6601-07-201523-10-20167047.00 m7047.00 m6.2458.66
11.Crash Barrier2732.00 m84.6901-01-201625-10-20162732.00 m2732.00 m9.0184.69
12.Parapet603.00 No54.2401-06-201629-10-2016250.00 No250.00 No5.7754.24
13.Road Furniture48.00 No2.5315-06-201630-10-2016186.00 No186.00 No0.272.53
14.Other Allied Works & Finishing Work 9.00 Job8.0001-06-201630-09-20169.00 Job9.00 Job0.858.00
Total Amount: 940.33 100   940.33
Remarks: No Remarks       Work Program Made On: 31-07-2015        Updation of work program on: 25-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.25-July-201542.26  lakh
2.19-September-201560.97  lakh
3.20-October-201570.85  lakh
4.28-November-201572.55  lakh
5.31-December-201532.42  lakh
6.29-February-201635.65  lakh
7.31-March-201684.21  lakh
8.29-April-2016107.49  lakh
9.23-May-2016117.90  lakh
10.20-June-2016142.72  lakh
11.26-July-2016152.64  lakh
12.29-September-201671.56  lakh
13.27-October-201621.58  lakh
14.28-February-201724.64  lakh
15.19-June-201735.35  lakh
16.11-October-201715.48  lakh
Total 1088.27  lakh
% Payment 89.32 %
Advance Amount:  105.00  lakh        Recovered Amount:  105.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1144   No. of Test Done : 1146    No. of Test Passed : 1111   No. of Test Failed : 27   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.46
Number of Notice(s) issued: 73

Mobile Pic Upload

Number of Pics Available on Web Repository: 46
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.02-11-201623+400BM laying in progressLalit TiwariAEDEA ADB Nainital See Pic
2.28-06-2016Chainage 30+700Road after B CRajiv GururaniEEUEAP R&B Nainital See Pic
3.28-06-2016Chainage 31+400Road after completionRajiv GururaniEEUEAP R&B Nainital See Pic
4.29-05-2016Chainage 18+200Plum concrete at cause wayRajiv GururaniEEUEAP R&B Nainital See Pic
5.13-05-2016BM work in progressLalit TiwariAEDEA ADB Nainital See Pic
6.13-05-201621+350B C work with side kutcha drainLalit TiwariAEDEA ADB Nainital See Pic
7.18-03-201619+800BM LayingLalit TiwariAEDEA ADB Nainital See Pic
8.18-03-201618+600Plum wallLalit TiwariAEDEA ADB Nainital See Pic
9.17-03-2016Chainage 19+950B M work started from km 20Rajiv GururaniEEUEAP R&B Nainital See Pic
10.17-03-2016Chainage 19+850BM work in progressRajiv GururaniEEUEAP R&B Nainital See Pic
11.04-03-2016Chainage15+200Sprinkling water on W B MRajiv GururaniEEUEAP R&B Nainital See Pic
12.13-01-2016Chainage 15+600Sub Base preparation for B M at undulations & depressed portionRajiv GururaniEEDEA ADB Nainital See Pic
13.19-08-2015Chainage 0+200B/wall constructionRajiv GururaniEEDEA ADB Nainital See Pic
14.11-08-201523+000Construction of B/WLalit TiwariAEDEA ADB Nainital See Pic
15.11-08-201516+450Construction of R/WLalit TiwariAEDEA ADB Nainital See Pic
16.11-08-201515+025Construction of U Type Side DrainLalit TiwariAEDEA ADB Nainital See Pic
17.10-08-20150+230Construction of B/WLalit TiwariAEDEA ADB Nainital See Pic
18.24-07-201524-650Selep cleringAnil KumarJEUEAP R&B Nainital See Pic
19.22-07-201521-200Selep cleringAnil KumarJEUEAP R&B Nainital See Pic
20.16-07-201521.200Land slide/slip clrarence/Opening communicationRajendra Prasad SatiJEUEAP R&B Nainital See Pic