Nathuwakhan-Suyalbari Work Completed
Project: UEAP-RB UID: 5904 Sanction Cost: 198.00  lakh Length: 26.000 KM.
District: Nainital Block: Ramgarh Constituency: Nainital Circle:
DEA: DEA UEAP Nainital DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design & Supervision Type: VR
Procurement:
Package No.: 1005        Package Name:  UEAP/PWD/C3        Tender Date: 01-05-2014        Current Status: Agreement signed        Achieved on Date: 15-12-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C3      Contractor Name: Woodhill Infrastructure Ltd
Start Date:  04-01-2015      Intended Completion Date:  03-04-2016     
Total Bond Cost: 21874812.6 (218.75 lakh)        Variation Cost: 4182396.10 (41.82 lakh)    Hence Total Bond Cost is   26057208.7 (260.57 lakh) 
Sub Project Cost: 198.00  lakh       
LD Analysis for Milestone1: calculated LD is Rs 120307 for 11 days        LD Analysis for Milestone2: calculated LD is Rs 218740 for 20 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.44 KM1.6705-08-201515-09-20150.44 KM0.44 KM1.021.67
2.R/Wall, B/ Wall Type Protection works225.00 m34.1020-08-201530-11-2015225.00 m225.00 m20.8334.10
3.G-20.00 KM0.0001-04-201501-05-20150.00 KM0.00 KM00.00
4.G-30.90 KM2.1025-08-201530-09-20150.90 KM0.90 KM1.282.10
5.PC/CC i/c Prime Coat, Tack Coat10.10 KM106.0901-10-201515-03-201610.10 KM10.10 KM64.79106.09
6.Cause Way2.00 No2.6301-09-201531-10-20152.00 No2.00 No1.62.63
7.Culverts/Scupper 104.00 No4.1625-08-201525-11-2015104.00 No104.00 No2.544.16
8.longitudinal Drain13000.00 m13.0015-01-201620-03-201613000.00 m13000.00 m7.9413.00
Total Amount: 163.75 100   163.75
Remarks: No Remarks       Work Program Made On: 16-04-2015        Updation of work program on: 03-09-2016       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.26-October-201556.41  lakh
2.30-November-201520.48  lakh
3.02-September-201688.27  lakh
4.25-September-20176.20  lakh
Total 171.36  lakh
% Payment86.55 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 32   No. of Test Done : 32    No. of Test Passed : 31   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 85.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 7
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.06-11-2015Chainage 10+000Premix carpet work startedGulab RamSEADB Circle See Pic
2.06-11-2015Chainage 1+460Damaged R/Wall contructionGulab RamSEADB Circle See Pic
3.30-09-20153+000Construction of B/W and side kuccha drainLalit TiwariAEDEA ADB Nainital See Pic
4.19-08-2015Chainage 24+600R/Wall damaged this mansoon SRMD 2015-16Rajiv GururaniEEDEA ADB Nainital See Pic
5.19-08-2015Chainage 1+450R/Wall construction which damaged this year's mansoon SRMD 2015-16Rajiv GururaniEEDEA ADB Nainital See Pic
6.20-07-20153+200Slip and B/W requiredLalit TiwariAEDEA ADB Nainital See Pic
7.20-07-20151+400Damaged R/WLalit TiwariAEDEA ADB Nainital See Pic