Nathuwakhan-Suyalbari
Work Completed
|
Project: |
UEAP-RB |
UID: |
5904 |
Sanction Cost: |
198.00 lakh |
Length:
|
26.000 KM. |
District: |
Nainital |
Block: |
Ramgarh |
Constituency: |
Nainital |
Circle: |
|
DEA: |
DEA UEAP Nainital |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design & Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 1005
Package Name: 
UEAP/PWD/C3
Tender Date: 01-05-2014
Current Status: Agreement signed
Achieved on Date: 15-12-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C3
Contractor Name: Woodhill Infrastructure Ltd
|
Start Date: 04-01-2015
Intended Completion Date: 03-04-2016
|
Total Bond Cost: 21874812.6 (218.75 lakh)
Variation Cost: 4182396.10 (41.82 lakh) Hence Total Bond Cost is 26057208.7 (260.57 lakh)
|
Sub Project Cost: 198.00 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 120307 for 11 days
LD Analysis for Milestone2: calculated LD is Rs 218740 for 20 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.44 KM | 1.67 | 05-08-2015 | 15-09-2015 | 0.44 KM | 0.44 KM | 1.02 | 1.67 | 2. | R/Wall, B/ Wall Type Protection works | 225.00 m | 34.10 | 20-08-2015 | 30-11-2015 | 225.00 m | 225.00 m | 20.83 | 34.10 | 3. | G-2 | 0.00 KM | 0.00 | 01-04-2015 | 01-05-2015 | 0.00 KM | 0.00 KM | 0 | 0.00 | 4. | G-3 | 0.90 KM | 2.10 | 25-08-2015 | 30-09-2015 | 0.90 KM | 0.90 KM | 1.28 | 2.10 | 5. | PC/CC i/c Prime Coat, Tack Coat | 10.10 KM | 106.09 | 01-10-2015 | 15-03-2016 | 10.10 KM | 10.10 KM | 64.79 | 106.09 | 6. | Cause Way | 2.00 No | 2.63 | 01-09-2015 | 31-10-2015 | 2.00 No | 2.00 No | 1.6 | 2.63 | 7. | Culverts/Scupper | 104.00 No | 4.16 | 25-08-2015 | 25-11-2015 | 104.00 No | 104.00 No | 2.54 | 4.16 | 8. | longitudinal Drain | 13000.00 m | 13.00 | 15-01-2016 | 20-03-2016 | 13000.00 m | 13000.00 m | 7.94 | 13.00 |
Total Amount: |
163.75 |
|
100 |
163.75 |
|
Remarks:
No Remarks
Work Program Made On:
16-04-2015 } ?>
Updation of work program on:
03-09-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-October-2015 | 56.41 lakh | 2. | 30-November-2015 | 20.48 lakh | 3. | 02-September-2016 | 88.27 lakh | 4. | 25-September-2017 | 6.20 lakh |
Total |
171.36 lakh |
% Payment | 86.55 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 32 No. of Test Done : 32 No. of Test Passed : 31 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 85.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 7 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 06-11-2015 | Chainage 10+000 | Premix carpet work started | Gulab Ram | SE | ADB Circle | See Pic |
2. | 06-11-2015 | Chainage 1+460 | Damaged R/Wall contruction | Gulab Ram | SE | ADB Circle | See Pic |
3. | 30-09-2015 | 3+000 | Construction of B/W and side kuccha drain | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
4. | 19-08-2015 | Chainage 24+600 | R/Wall damaged this mansoon SRMD 2015-16 | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
5. | 19-08-2015 | Chainage 1+450 | R/Wall construction which damaged this year's mansoon SRMD 2015-16 | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
6. | 20-07-2015 | 3+200 | Slip and B/W required | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
7. | 20-07-2015 | 1+400 | Damaged R/W | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
|
|