Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Nainital-Kaladhungi- Bajpur Doraha Road Work Completed
Project: UEAP-RB UID: 5902 Sanction Cost: 620.00  lakh Length: 21.500 KM.
District: Nainital Block: Bhimtal Constituency: Nainital Circle:
DEA: DEA UEAP Nainital DSC: CCEE Group India Pvt.Ltd DSC Scope: Design & Supervision Type: MDR
Procurement:
Package No.: 1001        Package Name:  UEAP/PWD/C1        Tender Date: 13-01-2014        Current Status: Agreement signed        Achieved on Date: 21-04-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C1      Contractor Name: Woodhill Infrastructure Ltd
Start Date:  16-06-2014      Intended Completion Date:  18-01-2016      Original End Date:  18-09-2015
Total Bond Cost: 58834744.2 (588.35 lakh)        Variation Cost: 8740028.90 (87.4 lakh)    Hence Total Bond Cost is   67574773.1 (675.75 lakh) 
Sub Project Cost: 570.75  lakh       
LD Analysis for Milestone1: calculated LD is Rs 1000178 for 34 days        LD Analysis for Milestone2: calculated LD is Rs 1706186 for 58 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.34 KM0.9725-09-201529-09-20150.34 KM0.34 KM0.280.97
2.R/Wall, B/ Wall Type Protection works910.00 m56.8909-09-201425-10-20152773.00 m2773.00 m16.3956.89
3.BM i/c Prime Coat, Tack Coat1.44 KM27.1509-09-201427-06-20150.83 KM0.83 KM7.8327.15
4.SDBC i/c Tackcoat15.05 KM212.0909-09-201418-10-201515.55 KM15.55 KM61.12212.09
5.Cause Way4.00 No7.5220-04-201512-08-20154.00 No4.00 No2.177.52
6.Culverts/Scupper 4.00 No8.8215-02-201530-11-20155.00 No5.00 No2.548.82
7.longitudinal Drain15113.00 m1.3621-07-201410-01-201615580.00 m15580.00 m0.391.36
8.Road Furniture136.00 No32.2117-06-201519-12-2015136.00 No136.00 No9.2832.21
Total Amount: 347.01 100   347.01
Remarks: No Remarks       Work Program Made On: 17-04-2015        Updation of work program on: 25-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.27-April-2015141.00  lakh
2.27-June-2015111.40  lakh
3.30-October-2015113.43  lakh
4.21-March-2016129.35  lakh
5.15-June-201751.69  lakh
Total 546.87  lakh
% Payment95.82 %
Advance Amount:  58.00  lakh        Recovered Amount:  58.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 68   No. of Test Done : 68    No. of Test Passed : 66   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 27
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.01-10-201500-850BC work in progressAnil KumarJEUEAP R&B Nainital See Pic
2.22-07-201528-800R/w-damaj do to rainAnil KumarJEUEAP R&B Nainital See Pic
3.22-07-201525-650R/w-damaj do to rainAnil KumarJEUEAP R&B Nainital See Pic
4.09-07-201529+550B/W damaged by running slipLalit TiwariAEDEA ADB Nainital See Pic
5.09-07-201529+650Excavation for B/WLalit TiwariAEDEA ADB Nainital See Pic
6.20-06-2015Near University GateSDBC layingLalit TiwariAEDEA ADB Nainital See Pic
7.20-06-2015Near Eco cave park nainitalCompaction of BMLalit TiwariAEDEA ADB Nainital See Pic
8.19-06-20150+200Rolling of SDBCLalit TiwariAEDEA ADB Nainital See Pic
9.19-06-2015Chainage 0 + 350SDBC laying near TRC Sukhatal NainitalRajiv GururaniEEDEA ADB Nainital See Pic
10.19-06-2015Chainage 0+200SDBC laying in the start point of Nainital Kaladhungi Motor RoadRajiv GururaniEEDEA ADB Nainital See Pic
11.17-06-2015Chainage 0+120BM work in Nainital kaladhungi Motor Road start pointRajiv GururaniEEDEA ADB Nainital See Pic
12.17-06-2015Chainage 0+100BM started in the start point of Nainital Kaladhungi Motor RoadRajiv GururaniEEDEA ADB Nainital See Pic
13.26-05-2015Chainage Km 24.250K c drRajiv GururaniEEDEA ADB Nainital See Pic
14.21-05-201514+125Construction of B/WLalit TiwariAEDEA ADB Nainital See Pic
15.10-05-2015Chanage 26.500S D B C work in progressRajiv GururaniEEDEA ADB Nainital See Pic
16.10-05-2015Chainage 26.450S D B C work in progressRajiv GururaniEEDEA ADB Nainital See Pic
17.09-05-2015Chainge 23.700S D B C work in progressRajiv GururaniEEDEA ADB Nainital See Pic
18.09-05-2015Chainage 23.700S D B C work near Ghatgarh in Nainital kaladhungi road in progressRajiv GururaniEEDEA ADB Nainital See Pic
19.20-03-2015Km 15.250Inspection of road by C E Haldwani Er B C Binwal jiRajiv GururaniEEDEA ADB Nainital See Pic
20.25-02-2015Km 13.000Dimantling the rejected work of drain due to slope issueRajiv GururaniEEDEA ADB Nainital See Pic