Nainital-Kaladhungi- Bajpur Doraha Road
Work Completed
|
Project: |
UEAP-RB |
UID: |
5902 |
Sanction Cost: |
620.00 lakh |
Length:
|
21.500 KM. |
District: |
Nainital |
Block: |
Bhimtal |
Constituency: |
Nainital |
Circle: |
|
DEA: |
DEA UEAP Nainital |
DSC: |
CCEE Group India Pvt.Ltd |
DSC Scope: |
Design & Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1001
Package Name: 
UEAP/PWD/C1
Tender Date: 13-01-2014
Current Status: Agreement signed
Achieved on Date: 21-04-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C1
Contractor Name: Woodhill Infrastructure Ltd
|
Start Date: 16-06-2014
Intended Completion Date: 18-01-2016
Original End Date: 18-09-2015 |
Total Bond Cost: 58834744.2 (588.35 lakh)
Variation Cost: 8740028.90 (87.4 lakh) Hence Total Bond Cost is 67574773.1 (675.75 lakh)
|
Sub Project Cost: 570.75 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 1000178 for 34 days
LD Analysis for Milestone2: calculated LD is Rs 1706186 for 58 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.34 KM | 0.97 | 25-09-2015 | 29-09-2015 | 0.34 KM | 0.34 KM | 0.28 | 0.97 | 2. | R/Wall, B/ Wall Type Protection works | 910.00 m | 56.89 | 09-09-2014 | 25-10-2015 | 2773.00 m | 2773.00 m | 16.39 | 56.89 | 3. | BM i/c Prime Coat, Tack Coat | 1.44 KM | 27.15 | 09-09-2014 | 27-06-2015 | 0.83 KM | 0.83 KM | 7.83 | 27.15 | 4. | SDBC i/c Tackcoat | 15.05 KM | 212.09 | 09-09-2014 | 18-10-2015 | 15.55 KM | 15.55 KM | 61.12 | 212.09 | 5. | Cause Way | 4.00 No | 7.52 | 20-04-2015 | 12-08-2015 | 4.00 No | 4.00 No | 2.17 | 7.52 | 6. | Culverts/Scupper | 4.00 No | 8.82 | 15-02-2015 | 30-11-2015 | 5.00 No | 5.00 No | 2.54 | 8.82 | 7. | longitudinal Drain | 15113.00 m | 1.36 | 21-07-2014 | 10-01-2016 | 15580.00 m | 15580.00 m | 0.39 | 1.36 | 8. | Road Furniture | 136.00 No | 32.21 | 17-06-2015 | 19-12-2015 | 136.00 No | 136.00 No | 9.28 | 32.21 |
Total Amount: |
347.01 |
|
100 |
347.01 |
|
Remarks:
No Remarks
Work Program Made On:
17-04-2015 } ?>
Updation of work program on:
25-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 27-April-2015 | 141.00 lakh | 2. | 27-June-2015 | 111.40 lakh | 3. | 30-October-2015 | 113.43 lakh | 4. | 21-March-2016 | 129.35 lakh | 5. | 15-June-2017 | 51.69 lakh |
Total |
546.87 lakh |
% Payment | 95.82 % |
|
Advance Amount: 58.00 lakh
Recovered Amount: 58.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 68 No. of Test Done : 68 No. of Test Passed : 66 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 27 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 01-10-2015 | 00-850 | BC work in progress | Anil Kumar | JE | UEAP R&B Nainital | See Pic |
2. | 22-07-2015 | 28-800 | R/w-damaj do to rain | Anil Kumar | JE | UEAP R&B Nainital | See Pic |
3. | 22-07-2015 | 25-650 | R/w-damaj do to rain | Anil Kumar | JE | UEAP R&B Nainital | See Pic |
4. | 09-07-2015 | 29+550 | B/W damaged by running slip | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
5. | 09-07-2015 | 29+650 | Excavation for B/W | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
6. | 20-06-2015 | Near University Gate | SDBC laying | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
7. | 20-06-2015 | Near Eco cave park nainital | Compaction of BM | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
8. | 19-06-2015 | 0+200 | Rolling of SDBC | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
9. | 19-06-2015 | Chainage 0 + 350 | SDBC laying near TRC Sukhatal Nainital | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
10. | 19-06-2015 | Chainage 0+200 | SDBC laying in the start point of Nainital Kaladhungi Motor Road | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
11. | 17-06-2015 | Chainage 0+120 | BM work in Nainital kaladhungi Motor Road start point | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
12. | 17-06-2015 | Chainage 0+100 | BM started in the start point of Nainital Kaladhungi Motor Road | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
13. | 26-05-2015 | Chainage Km 24.250 | K c dr | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
14. | 21-05-2015 | 14+125 | Construction of B/W | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
15. | 10-05-2015 | Chanage 26.500 | S D B C work in progress | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
16. | 10-05-2015 | Chainage 26.450 | S D B C work in progress | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
17. | 09-05-2015 | Chainge 23.700 | S D B C work in progress | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
18. | 09-05-2015 | Chainage 23.700 | S D B C work near Ghatgarh in Nainital kaladhungi road in progress | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
19. | 20-03-2015 | Km 15.250 | Inspection of road by C E Haldwani Er B C Binwal ji | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
20. | 25-02-2015 | Km 13.000 | Dimantling the rejected work of drain due to slope issue | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
|
|