Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Protection-Treatment work on chronic land slide zone on Khairna-Ranikhet MR Work Completed
Project: UEAP-RB UID: 5824 Sanction Cost: 1121.00  lakh Length: 0.350 KM.
District: Almora Block: Tarikhet Constituency: Ranikhet Circle:
DEA: DEA UEAP Nainital DSC: CCEE Group India Pvt.Ltd DSC Scope: Design and Supervision Type: SH
Procurement:
Package No.: 1080        Package Name:  UEAP/PWD/C-76        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 04-02-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C-76      Contractor Name: Bharat Construction
Start Date:  25-02-2016      Intended Completion Date:  31-05-2017      Original End Date:  25-02-2017
Total Bond Cost: 62674569 (626.75 lakh)        Variation Cost: 49425431.00 (494.25 lakh)    Hence Total Bond Cost is   112100000 (1121 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works273.00 m1077.1425-02-201625-05-2017273.00 m273.00 m99.341000.00
2.Cause Way0.00 No0.0025-04-201725-04-20170.00 No0.00 No00.00
3.longitudinal Drain275.00 m4.9515-04-201725-05-2017275.00 m275.00 m0.464.95
4.Parapet60.00 No2.2325-04-201722-08-201760.00 No60.00 No0.212.23
Total Amount: 1084.32 100   1007.18
Remarks: No Remarks       Work Program Made On: 14-07-2016        Updation of work program on: 12-10-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.24-June-2016313.16  lakh
2.28-October-2016142.61  lakh
3.21-January-2017122.59  lakh
4.23-March-2017202.72  lakh
5.25-April-201732.30  lakh
6.31-May-201743.84  lakh
7.29-June-201741.46  lakh
Total 898.68  lakh
% Payment 80.17 %
Advance Amount:  62.67  lakh        Recovered Amount:  62.67  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 3474   No. of Test Done : 3480    No. of Test Passed : 3450   No. of Test Failed : 11   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 87.50
Number of Notice(s) issued: 55

Mobile Pic Upload

Number of Pics Available on Web Repository: 39
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.15-07-2017Chronic slip zone at Khairna Ranikhet motor road km 1Cladding work in progress in chainage 214-230Rajiv GururaniEEUEAP R&B Nainital See Pic
2.10-06-2017Chronic slip zone treatment work at Khairna Ranikhet motor road from other sideInspection of treatment work by Mr Vikas Chauhan Sr Manager THDC RishikeshRajiv GururaniEEUEAP R&B Nainital See Pic
3.09-06-2017Chronic Slip Zone treatment work at Khairna Ranikhet motor road km 1Sr manager THDC mr Vikas Chauhan visit of siteRajiv GururaniEEUEAP R&B Nainital See Pic
4.09-06-2017Chronic Slip zone treatment work at Khairna Ranikhet motor km 1Site visit of Sr Manager THDC Mr Vikas Chauhan inspecting High Tensile Steel wire meshRajiv GururaniEEUEAP R&B Nainital See Pic
5.29-05-2017Chronic slip zone treatment work at Khairna Ranikhet motor road km 1Site inspection of treatment work by the ADB officials Dr P Sahu & Dr Raju with SE UEAP AlmoraRajiv GururaniEEUEAP R&B Nainital See Pic
6.07-05-2017Gabbion drain work at ch 235 at pkg C-76Chronic landslide zone at khairna Ranikhet motor road km-1 Pkg C-76Rajendra GiriJEUEAP R&B Nainital See Pic
7.07-05-2017Gabbion cladding at hill side chronic landslide zone at pkg C-76Chronic land slide zone Pkg C-76Rajendra GiriJEUEAP R&B Nainital See Pic
8.28-04-2017Gabbion drain at ch 236 at pkg c-76Chronic landslide zone at km 1 Khairna Ranikhet motor roadRajendra GiriJEUEAP R&B Nainital See Pic
9.28-04-2017Gabbion drain at ch 236 at pkg c-76Chronic land slide zone at khairna Ranikhet road km-1Rajendra GiriJEUEAP R&B Nainital See Pic
10.28-04-2017Concrete cladding work at ch 140 to 249 At pkg c-76Chronic land slide zone at khairna Ranikhet road km 1Rajendra GiriJEUEAP R&B Nainital See Pic
11.22-03-2017Chronic slip zone at KhairnaChecking of land record by tahsildar and patwari and other revenue staff to resolve the issues An open meeting organised there as per instruction of DM Almora ADM Almora SDM Ranikhet also thereRajiv GururaniEEUEAP R&B Nainital See Pic
12.22-03-2017Chronic slip zone treatment work at km 1 of Khairna Ranikhet motor roadAlong with SDM Ranikhet to resolve the issues of QuerryRajiv GururaniEEUEAP R&B Nainital See Pic
13.09-03-2017Chronic slip zone treatment work at km 1 of Khairna Ranikhet motor roadMeasurements of land of QueryRajiv GururaniEEUEAP R&B Nainital See Pic
14.04-03-2017Chronic slip zone treatment work near KhairnaGabian walling is in progressRajiv GururaniEEUEAP R&B Nainital See Pic
15.07-02-2017Chronic slip zone treatment work in progress at Khairna Ranikhet motor road km 1Inspection of workRajiv GururaniEEUEAP R&B Nainital See Pic
16.07-02-2017Chronic Slip Zone at Khairna Ranikhet motor road km 1Inspection of work by THDC officer Mr Ajay ConsulRajiv GururaniEEUEAP R&B Nainital See Pic
17.07-02-2017Chronic slip zone at Khairna Ranikhet motor road km 1site visit and inspection of THDC TA shri Ajay Consul jiRajiv GururaniEEUEAP R&B Nainital See Pic
18.07-02-2017Chronic Slip Zone treatment work in progress at km 1 of Khairna Ranikhet motor roadwork in progressRajiv GururaniEEUEAP R&B Nainital See Pic
19.22-12-2016Chainage +0130 to +0140Concreting work in progressRajiv GururaniEEUEAP R&B Nainital See Pic
20.08-11-2016Chronic slip zone site km1chronic slip zone treatment work inspection by Mr Sanjay Shinghal Dy G M THDC RishikeshRajiv GururaniEEUEAP R&B Nainital See Pic