Khairna-Ranikhet Motor Road
Work Completed
|
Project: |
UEAP-RB |
UID: |
5823 |
Sanction Cost: |
1386.00 lakh |
Length:
|
26.000 KM. |
District: |
Almora |
Block: |
Tarikhet |
Constituency: |
Ranikhet |
Circle: |
|
DEA: |
DEA UEAP Nainital |
DSC: |
CCEE Group India Pvt.Ltd |
DSC Scope: |
Design and Supervision |
Type: |
SH |
|
Procurement: |
Package No.: 1068
Package Name: 
UEAP/PWD/C64
Tender Date: 28-10-2014
Current Status: Agreement signed
Achieved on Date: 12-02-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C64
Contractor Name: N P Buildwell Pvt. Ltd
|
Start Date: 01-03-2015
Intended Completion Date: 30-08-2016
|
Total Bond Cost: 89156104.6 (891.56 lakh)
Variation Cost: 42457690.19 (424.58 lakh) Hence Total Bond Cost is 131613794.79 (1316.14 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.43 KM | 0.65 | 01-05-2015 | 15-05-2015 | 0.43 KM | 0.43 KM | 0.08 | 0.65 | 2. | R/Wall, B/ Wall Type Protection works | 590.00 m | 121.70 | 01-04-2015 | 15-12-2015 | 590.00 m | 590.00 m | 15.44 | 121.70 | 3. | G-3 | 0.36 KM | 3.55 | 21-03-2015 | 21-05-2015 | 0.36 KM | 0.36 KM | 0.45 | 3.55 | 4. | BM i/c Prime Coat, Tack Coat | 10.50 KM | 236.92 | 21-03-2015 | 25-05-2015 | 10.50 KM | 10.50 KM | 30.06 | 236.92 | 5. | SDBC i/c Tackcoat | 23.00 KM | 244.97 | 01-04-2015 | 30-05-2015 | 23.00 KM | 23.00 KM | 31.08 | 244.97 | 6. | Cause Way | 2.00 No | 17.55 | 15-04-2015 | 15-06-2015 | 2.00 No | 2.00 No | 2.23 | 17.55 | 7. | Culverts/Scupper | 4.00 No | 43.55 | 01-05-2015 | 01-05-2016 | 4.00 No | 4.00 No | 5.53 | 43.55 | 8. | longitudinal Drain | 20600.00 m | 45.73 | 15-04-2015 | 15-02-2016 | 20600.00 m | 20600.00 m | 5.8 | 45.73 | 9. | Crash Barrier | 1587.00 m | 32.64 | 01-10-2015 | 01-02-2016 | 1587.00 m | 1587.00 m | 4.14 | 32.64 | 10. | Parapet | 1100.00 No | 37.36 | 01-10-2015 | 01-02-2016 | 1100.00 No | 1100.00 No | 4.74 | 37.36 | 11. | Road Furniture | 1587.00 No | 3.46 | 01-03-2016 | 01-04-2016 | 1587.00 No | 1587.00 No | 0.44 | 3.46 |
Total Amount: |
788.08 |
|
100 |
788.08 |
|
Remarks:
No Remarks
Work Program Made On:
07-05-2015 } ?>
Updation of work program on:
13-09-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-May-2015 | 389.59 lakh | 2. | 01-June-2015 | 224.28 lakh | 3. | 27-June-2015 | 110.70 lakh | 4. | 18-September-2015 | 57.71 lakh | 5. | 30-October-2015 | 97.03 lakh | 6. | 30-November-2015 | 150.55 lakh | 7. | 08-January-2016 | 93.04 lakh | 8. | 19-March-2016 | 142.48 lakh | 9. | 30-June-2016 | 26.01 lakh |
Total |
1291.39 lakh |
% Payment |
98.12 % |
|
Advance Amount: 89.00 lakh
Recovered Amount: 89.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 724 No. of Test Done : 727 No. of Test Passed : 717 No. of Test Failed : 5 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.23 |
Number of Notice(s) issued: 76 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 63 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 09-06-2017 | Khairna Ranikhet motor road km 7 | Inspection of Khairna Ranikhet motor road by ADB team | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
2. | 02-11-2016 | 9+350 | Core cutting of BC | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
3. | 02-11-2016 | 4+750 | Road appearance. | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
4. | 02-11-2016 | 3+950 | OFC laying in progress after permission of E E P. D. PWD Ranikhet in total length of Road ,(may damage the Road Surface) | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
5. | 24-08-2016 | 8+200 | R/wall | Anil Kumar | JE | UEAP R&B Nainital | See Pic |
6. | 24-08-2016 | 7+300 | R/wall | Anil Kumar | JE | UEAP R&B Nainital | See Pic |
7. | 24-08-2016 | 7+050 | R/wall | Anil Kumar | JE | UEAP R&B Nainital | See Pic |
8. | 24-08-2016 | 6+240 | R/wall | Anil Kumar | JE | UEAP R&B Nainital | See Pic |
9. | 21-07-2016 | Chainage 2+800 | Inspection of C64 package by SE UEAP Almora
Excavated material after laying of OFC cable left indisposed causes damages to road
P D Ranikhet to be intimated for this | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
10. | 20-07-2016 | Chainage 2+900 | S E Sir inspection of Khairna Ranikhet motor road regarding laying of OFC cable which damages the road surface | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
11. | 28-06-2016 | Chronic slip zone treatment work at Khairna | Treatment work | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
12. | 28-06-2016 | Chronic slip zone treatment work is on as per THDC drawing | Work is on | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
13. | 07-06-2016 | Chainage 9+800 | Road after BC laying | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
14. | 14-04-2016 | 2+900 | Construction of RW | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
15. | 14-04-2016 | 2+900 | Construction of RW | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
16. | 08-03-2016 | Chainage 5+740 | Scupper in progress | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
17. | 08-03-2016 | Chainage 2+900 | R/Wall in progress | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
18. | 03-03-2016 | 9 + 350 | BC | Bhavya Kamboj | AAE | UEAP R&B Nainital | See Pic |
19. | 23-02-2016 | 6+850 | Construction of scupper | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
20. | 11-10-2015 | Chainage 15+800 | Checking of SDBC by S E 2nd circle P W D Nainital | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
|
|