Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Khairna-Ranikhet Motor Road Work Completed
Project: UEAP-RB UID: 5823 Sanction Cost: 1386.00  lakh Length: 26.000 KM.
District: Almora Block: Tarikhet Constituency: Ranikhet Circle:
DEA: DEA UEAP Nainital DSC: CCEE Group India Pvt.Ltd DSC Scope: Design and Supervision Type: SH
Procurement:
Package No.: 1068        Package Name:  UEAP/PWD/C64        Tender Date: 28-10-2014        Current Status: Agreement signed        Achieved on Date: 12-02-2015

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C64      Contractor Name: N P Buildwell Pvt. Ltd
Start Date:  01-03-2015      Intended Completion Date:  30-08-2016     
Total Bond Cost: 89156104.6 (891.56 lakh)        Variation Cost: 42457690.19 (424.58 lakh)    Hence Total Bond Cost is   131613794.79 (1316.14 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.43 KM0.6501-05-201515-05-20150.43 KM0.43 KM0.080.65
2.R/Wall, B/ Wall Type Protection works590.00 m121.7001-04-201515-12-2015590.00 m590.00 m15.44121.70
3.G-30.36 KM3.5521-03-201521-05-20150.36 KM0.36 KM0.453.55
4.BM i/c Prime Coat, Tack Coat10.50 KM236.9221-03-201525-05-201510.50 KM10.50 KM30.06236.92
5.SDBC i/c Tackcoat23.00 KM244.9701-04-201530-05-201523.00 KM23.00 KM31.08244.97
6.Cause Way2.00 No17.5515-04-201515-06-20152.00 No2.00 No2.2317.55
7.Culverts/Scupper 4.00 No43.5501-05-201501-05-20164.00 No4.00 No5.5343.55
8.longitudinal Drain20600.00 m45.7315-04-201515-02-201620600.00 m20600.00 m5.845.73
9.Crash Barrier1587.00 m32.6401-10-201501-02-20161587.00 m1587.00 m4.1432.64
10.Parapet1100.00 No37.3601-10-201501-02-20161100.00 No1100.00 No4.7437.36
11.Road Furniture1587.00 No3.4601-03-201601-04-20161587.00 No1587.00 No0.443.46
Total Amount: 788.08 100   788.08
Remarks: No Remarks       Work Program Made On: 07-05-2015        Updation of work program on: 13-09-2016       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-May-2015389.59  lakh
2.01-June-2015224.28  lakh
3.27-June-2015110.70  lakh
4.18-September-201557.71  lakh
5.30-October-201597.03  lakh
6.30-November-2015150.55  lakh
7.08-January-201693.04  lakh
8.19-March-2016142.48  lakh
9.30-June-201626.01  lakh
Total 1291.39  lakh
% Payment 98.12 %
Advance Amount:  89.00  lakh        Recovered Amount:  89.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 724   No. of Test Done : 727    No. of Test Passed : 717   No. of Test Failed : 5   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 88.23
Number of Notice(s) issued: 76

Mobile Pic Upload

Number of Pics Available on Web Repository: 63
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.09-06-2017Khairna Ranikhet motor road km 7Inspection of Khairna Ranikhet motor road by ADB teamRajiv GururaniEEUEAP R&B Nainital See Pic
2.02-11-20169+350Core cutting of BCLalit TiwariAEDEA ADB Nainital See Pic
3.02-11-20164+750Road appearance.Lalit TiwariAEDEA ADB Nainital See Pic
4.02-11-20163+950OFC laying in progress after permission of E E P. D. PWD Ranikhet in total length of Road ,(may damage the Road Surface)Lalit TiwariAEDEA ADB Nainital See Pic
5.24-08-20168+200R/wallAnil KumarJEUEAP R&B Nainital See Pic
6.24-08-20167+300R/wallAnil KumarJEUEAP R&B Nainital See Pic
7.24-08-20167+050R/wallAnil KumarJEUEAP R&B Nainital See Pic
8.24-08-20166+240R/wallAnil KumarJEUEAP R&B Nainital See Pic
9.21-07-2016Chainage 2+800Inspection of C64 package by SE UEAP Almora Excavated material after laying of OFC cable left indisposed causes damages to road P D Ranikhet to be intimated for thisRajiv GururaniEEUEAP R&B Nainital See Pic
10.20-07-2016Chainage 2+900S E Sir inspection of Khairna Ranikhet motor road regarding laying of OFC cable which damages the road surfaceRajiv GururaniEEUEAP R&B Nainital See Pic
11.28-06-2016Chronic slip zone treatment work at KhairnaTreatment workRajiv GururaniEEUEAP R&B Nainital See Pic
12.28-06-2016Chronic slip zone treatment work is on as per THDC drawingWork is onRajiv GururaniEEUEAP R&B Nainital See Pic
13.07-06-2016Chainage 9+800Road after BC layingRajiv GururaniEEUEAP R&B Nainital See Pic
14.14-04-20162+900Construction of RWLalit TiwariAEDEA ADB Nainital See Pic
15.14-04-20162+900Construction of RWLalit TiwariAEDEA ADB Nainital See Pic
16.08-03-2016Chainage 5+740Scupper in progressRajiv GururaniEEUEAP R&B Nainital See Pic
17.08-03-2016Chainage 2+900R/Wall in progressRajiv GururaniEEUEAP R&B Nainital See Pic
18.03-03-20169 + 350BCBhavya KambojAAEUEAP R&B Nainital See Pic
19.23-02-20166+850Construction of scupperLalit TiwariAEDEA ADB Nainital See Pic
20.11-10-2015Chainage 15+800Checking of SDBC by S E 2nd circle P W D NainitalRajiv GururaniEEDEA ADB Nainital See Pic