Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Artola Jageshwar Naini Motor Raod Work Completed
Project: UEAP-RB UID: 5822 Sanction Cost: 435.00  lakh Length: KM.
District: Almora Block: Dhauladevi Constituency: Jageshwar Circle:
DEA: DEA UEAP Almora DSC: CCEE Group India Pvt.Ltd DSC Scope: Design and Supervision Type: MDR
Procurement:
Package No.: 1067        Package Name:  UEAP/PWD/C63        Tender Date: 28-10-2014        Current Status: Agreement signed        Achieved on Date: 13-02-2015

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C63      Contractor Name: Jagdish Saran
Start Date:  06-03-2015      Intended Completion Date:  05-09-2016     
Total Bond Cost: 36500185.62 (365 lakh)        Variation Cost: 11208008.28 (112.08 lakh)    Hence Total Bond Cost is   47708193.9 (477.08 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 1295750 for 71 days        LD Analysis for Milestone2: calculated LD is Rs 529250 for 29 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence7.00 KM5.1910-08-201512-08-20167.00 KM7.00 KM1.15.19
2.R/Wall, B/ Wall Type Protection works850.00 m137.1210-08-201530-07-2016850.00 m850.00 m29.14137.12
3.GSB/RBI/G-10.03 KM0.4715-12-201530-04-20160.03 KM0.03 KM0.10.47
4.G-20.13 KM0.5801-01-201620-05-20160.13 KM0.13 KM0.120.58
5.G-38.00 KM8.0501-02-201631-05-20168.00 KM8.00 KM1.718.05
6.PC/CC i/c Prime Coat, Tack Coat0.67 KM5.8201-04-201610-06-20160.67 KM0.67 KM1.245.82
7.BM i/c Prime Coat, Tack Coat4.00 KM61.7201-04-201631-05-20164.00 KM4.00 KM13.1161.72
8.SDBC i/c Tackcoat6.00 KM79.6712-04-201630-06-20166.00 KM6.00 KM16.9379.67
9.Cause Way2.00 No4.0601-10-201531-12-20152.00 No2.00 No0.864.06
10.Culverts/Scupper 46.00 No27.9001-09-201501-02-201646.00 No46.00 No5.9327.90
11.longitudinal Drain15570.00 m77.5101-09-201510-08-201615570.00 m15570.00 m16.4777.51
12.Crash Barrier990.00 m21.1101-03-201631-05-2016990.00 m990.00 m4.4921.11
13.Parapet693.00 No26.7701-04-201631-07-2016693.00 No693.00 No5.6926.77
14.Road Furniture75.00 No6.0401-04-201612-08-201675.00 No75.00 No1.286.04
15.Other Allied Works & Finishing Work 1.00 Job8.6306-03-201516-08-20161.00 Job1.00 Job1.838.63
Total Amount: 470.64 100   470.64
Remarks:        Work Program Made On: 24-08-2015        Updation of work program on: 25-09-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.20-October-201553.20  lakh
2.30-December-201553.49  lakh
3.29-February-201648.33  lakh
4.31-March-201625.26  lakh
5.30-April-201615.34  lakh
6.01-June-201612.87  lakh
7.24-June-2016109.15  lakh
8.09-August-201685.23  lakh
9.25-October-201624.48  lakh
10.28-February-201738.96  lakh
11.29-September-20176.84  lakh
Total 473.15  lakh
% Payment 99.17 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 390   No. of Test Done : 410    No. of Test Passed : 394   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.17
Number of Notice(s) issued: 64

Mobile Pic Upload

Number of Pics Available on Web Repository: 21
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.02-09-2016Ch 6+850Core cutting of B M/BC workRavi Shankar JoshiAEUEAP R&B Almora See Pic
2.28-08-2016Ch7.850Laying of B M work is in progressRavi Shankar JoshiAEUEAP R&B Almora See Pic
3.28-08-2016Ch16.275R wall is in progressRavi Shankar JoshiAEUEAP R&B Almora See Pic
4.28-08-2016Ch16.275R wall is in progressRavi Shankar JoshiAEUEAP R&B Almora See Pic
5.07-06-2016Ch7+575Rolling of B MRavi Shankar JoshiAEUEAP R&B Almora See Pic
6.04-06-2016Ch6+850Drain work completed before bituminous work.Ravi Shankar JoshiAEUEAP R&B Almora See Pic
7.04-05-2016Ch14.600Perapit work is in progressRavi Shankar JoshiAEUEAP R&B Almora See Pic
8.19-04-2016CH 8.350Excavation in progress for shoulder protectionRavi Shankar JoshiAEUEAP R&B Almora See Pic
9.09-04-2016km 6.450Artola Jageswar motor road marking for G3 pkg c-63Shahnawaz AliJEUEAP R&B Almora See Pic
10.09-04-2016km ch 5.075Artola jageswar Naini motor road pkg c-63 marking for G3.Shahnawaz AliJEUEAP R&B Almora See Pic
11.30-03-2016KM.19.850Retaing wall 1:5 and scupperShahnawaz AliJEUEAP R&B Almora See Pic
12.30-03-2016KM 12.375K C Type DrainShahnawaz AliJEUEAP R&B Almora See Pic
13.30-03-201614.500Toe wall and retaing wall in dry masonaryShahnawaz AliJEUEAP R&B Almora See Pic
14.30-03-201613.500Plum masonary and brest wallShahnawaz AliJEUEAP R&B Almora See Pic
15.30-03-201613.125Bended wall with toe wallShahnawaz AliJEUEAP R&B Almora See Pic
16.30-03-2016KM 11.600KC type drain workShahnawaz AliJEUEAP R&B Almora See Pic
17.30-03-2016Km. 10.050Artola Jageswar motor road perapet and Retaing wall workShahnawaz AliJEUEAP R&B Almora See Pic
18.30-03-2016Km 8.250KC type DRAIN Breast wall Plum Masonary workShahnawaz AliJEUEAP R&B Almora See Pic
19.30-03-2016Artola Jageswar motor road km 6.875K C TYPE DRAINShahnawaz AliJEUEAP R&B Almora See Pic
20.30-03-20166.800Artola Jageswar motor road pkg c 63 Retaing Wall workShahnawaz AliJEUEAP R&B Almora See Pic