Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Ganai-Jorasi Motor Road Work Completed
Project: UEAP-RB UID: 5821 Sanction Cost: 1313.00  lakh Length: 0.000 KM.
District: Almora Block: Chaukhutiya Constituency: Dwarahat Circle:
DEA: DEA UEAP Almora DSC: CCEE Group India Pvt.Ltd DSC Scope: Design and Supervision Type: MDR
Procurement:
Package No.: 1066        Package Name:  UEAP/PWD/C62        Tender Date: 28-10-2014        Current Status: Agreement signed        Achieved on Date: 12-02-2015

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C62      Contractor Name: Jagdish Saran
Start Date:  06-03-2015      Intended Completion Date:  05-09-2016     
Total Bond Cost: 107050979.04 (1070.51 lakh)        Variation Cost: 15534323.84 (155.34 lakh)    Hence Total Bond Cost is   122585302.88 (1225.85 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 5138400 for 96 days        LD Analysis for Milestone2: calculated LD is Rs 1873375 for 35 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence4.00 KM4.2710-07-201510-07-20164.00 KM4.00 KM0.354.27
2.R/Wall, B/ Wall Type Protection works950.00 m223.3910-07-201512-08-2016950.00 m950.00 m18.22223.39
3.GSB/RBI/G-10.12 KM1.8415-02-201609-06-20160.12 KM0.12 KM0.151.84
4.G-20.12 KM1.3115-02-201609-06-20160.12 KM0.12 KM0.111.31
5.G-35.54 KM17.6415-02-201612-06-20165.54 KM5.54 KM1.4417.64
6.PC/CC i/c Prime Coat, Tack Coat0.90 KM9.7715-02-201609-06-20160.90 KM0.90 KM0.89.77
7.BM i/c Prime Coat, Tack Coat18.87 KM277.8501-03-201615-06-201618.87 KM18.87 KM22.67277.85
8.SDBC i/c Tackcoat23.12 KM334.5115-03-201615-06-201623.12 KM23.12 KM27.29334.51
9.Cause Way17.00 No56.1801-09-201507-05-201617.00 No17.00 No4.5856.18
10.Culverts/Scupper 16.00 No32.1101-09-201507-05-201616.00 No16.00 No2.6232.11
11.longitudinal Drain23120.00 m56.6315-07-201512-08-201623120.00 m23120.00 m4.6256.63
12.Crash Barrier3360.00 m50.3601-03-201607-05-20163360.00 m3360.00 m4.1150.36
13.Parapet650.00 No110.3710-03-201612-08-2016650.00 No650.00 No9110.37
14.Road Furniture75.00 No30.8915-03-201612-08-201675.00 No75.00 No2.5230.89
15.Other Allied Works & Finishing Work 1.00 Job18.7410-07-201512-08-20161.00 Job1.00 Job1.5318.74
Total Amount: 1225.86 100   1225.86
Remarks:        Work Program Made On: 24-08-2015        Updation of work program on: 25-09-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.27-August-201529.04  lakh
2.29-September-201532.06  lakh
3.29-October-201530.55  lakh
4.30-November-2015105.47  lakh
5.30-January-2016107.63  lakh
6.29-February-201670.92  lakh
7.26-March-201645.61  lakh
8.30-April-2016264.00  lakh
9.01-June-2016169.88  lakh
10.10-June-2016190.47  lakh
11.09-August-201664.71  lakh
12.25-October-201625.35  lakh
13.25-November-201611.24  lakh
14.20-June-201778.93  lakh
Total 1225.86  lakh
% Payment 100.02 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 804   No. of Test Done : 847    No. of Test Passed : 802   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
Number of Notice(s) issued: 63

Mobile Pic Upload

Number of Pics Available on Web Repository: 92
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.01-06-2016Chainage- 0+200BM work in progressKuldeep GiriAEUEAP R&B Almora See Pic
2.29-05-2016Chainage 4.550BM workKuldeep GiriAEUEAP R&B Almora See Pic
3.22-05-2016Chainage-12.720BC WorkKuldeep GiriAEUEAP R&B Almora See Pic
4.22-05-2016Chainage-12.895BC surface after compactionKuldeep GiriAEUEAP R&B Almora See Pic
5.22-05-2016Chainage12.850Rolling of BC surfaceKuldeep GiriAEUEAP R&B Almora See Pic
6.22-05-2016Chainage-12.850BC work is in progressKuldeep GiriAEUEAP R&B Almora See Pic
7.20-05-2016Chainage-12.00Rolling of BM workKuldeep GiriAEUEAP R&B Almora See Pic
8.19-05-201612.860BM laying in progressChetan BhattJEUEAP R&B Almora See Pic
9.19-05-2016Ch 12.800B M laying in progressChetan BhattJEUEAP R&B Almora See Pic
10.16-05-2016Ch 14.425E E sir visitChetan BhattJEUEAP R&B Almora See Pic
11.16-05-2016Ch 14.300E.E sir visit at B C laying siteChetan BhattJEUEAP R&B Almora See Pic
12.16-05-2016Ch 14.400Ch 14.400Chetan BhattJEUEAP R&B Almora See Pic
13.16-05-2016Ch 14.450BC laying in progressChetan BhattJEUEAP R&B Almora See Pic
14.16-05-2016Ch 4.550Plum massonary in progressChetan BhattJEUEAP R&B Almora See Pic
15.16-05-2016At plantAggregates grading testChetan BhattJEUEAP R&B Almora See Pic
16.16-05-2016At plantBitumin extraction testChetan BhattJEUEAP R&B Almora See Pic
17.16-05-2016At plantB C PRODUCTION IN PROGRESSChetan BhattJEUEAP R&B Almora See Pic
18.09-05-2016Ch 16.400E.E. sir visitChetan BhattJEUEAP R&B Almora See Pic
19.09-05-2016Ch 16.500B C laying in progressChetan BhattJEUEAP R&B Almora See Pic
20.09-05-2016Ch 16.600B C LAYING IN PROGRESSChetan BhattJEUEAP R&B Almora See Pic