Bhikiyasain Deghat Bungidhar Bachuwaban Mehalchori Chaukhutiya Motor Road
Work Completed
|
Project: |
UEAP-RB |
UID: |
5820 |
Sanction Cost: |
337.00 lakh |
Length:
|
KM. |
District: |
Almora |
Block: |
Syaldey |
Constituency: |
Salt |
Circle: |
|
DEA: |
DEA UEAP Almora |
DSC: |
CCEE Group India Pvt.Ltd |
DSC Scope: |
Design and Supervision |
Type: |
SH |
|
Procurement: |
Package No.: 1065
Package Name: 
UEAP/PWD/C61
Tender Date: 28-10-2014
Current Status: Agreement signed
Achieved on Date: 12-02-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C61
Contractor Name: Jagdish Saran
|
Start Date: 07-03-2015
Intended Completion Date: 21-12-2016
Original End Date: 06-09-2016 |
Total Bond Cost: 119197725.82 (1191.98 lakh)
Variation Cost: 23156147.76 (231.56 lakh) Hence Total Bond Cost is 142353873.58 (1423.54 lakh)
|
Sub Project Cost: 1423.54 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 6377093 for 107 days
LD Analysis for Milestone2: calculated LD is Rs 5542707 for 93 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 6.00 KM | 4.50 | 01-07-2015 | 02-08-2016 | 6.00 KM | 6.00 KM | 1.42 | 4.50 | 2. | R/Wall, B/ Wall Type Protection works | 500.00 m | 122.06 | 01-07-2015 | 02-08-2016 | 500.00 m | 500.00 m | 38.43 | 122.06 | 3. | G-2 | 0.00 KM | 0.00 | 10-02-2016 | 10-02-2016 | 0.00 KM | 0.00 KM | 0 | 0.00 | 4. | G-3 | 5.50 KM | 9.11 | 01-02-2016 | 02-08-2016 | 5.50 KM | 5.50 KM | 2.87 | 9.11 | 5. | PC/CC i/c Prime Coat, Tack Coat | 6.90 KM | 117.32 | 01-04-2016 | 02-08-2016 | 6.30 KM | 6.30 KM | 36.93 | 117.32 | 6. | BM i/c Prime Coat, Tack Coat | 0.00 KM | 0.00 | 20-03-2016 | 20-03-2016 | 0.00 KM | 0.00 KM | 0 | 0.00 | 7. | SDBC i/c Tackcoat | 0.00 KM | 0.00 | 20-04-2016 | 20-04-2016 | 0.00 KM | 0.00 KM | 0 | 0.00 | 8. | Cause Way | 4.00 No | 6.96 | 01-09-2015 | 02-06-2016 | 4.00 No | 4.00 No | 2.19 | 6.96 | 9. | Culverts/Scupper | 2.00 No | 6.00 | 01-12-2015 | 12-08-2016 | 2.00 No | 2.00 No | 1.89 | 6.00 | 10. | longitudinal Drain | 7700.00 m | 17.00 | 01-07-2015 | 15-06-2016 | 7700.00 m | 7700.00 m | 5.35 | 17.00 | 11. | Crash Barrier | 514.00 m | 11.23 | 01-03-2016 | 15-06-2016 | 1200.00 m | 1200.00 m | 3.54 | 11.23 | 12. | Parapet | 120.00 No | 3.75 | 01-03-2016 | 12-05-2016 | 120.00 No | 120.00 No | 1.18 | 3.75 | 13. | Road Furniture | 55.00 No | 5.19 | 01-03-2016 | 10-10-2016 | 55.00 No | 55.00 No | 1.63 | 5.19 | 14. | Other Allied Works & Finishing Work | 1.00 Job | 14.52 | 01-07-2015 | 10-10-2016 | 1.00 Job | 1.00 Job | 4.57 | 14.52 |
Total Amount: |
317.64 |
|
100 |
317.64 |
|
Remarks:
Work Program Made On:
24-08-2015 } ?>
Updation of work program on:
25-09-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-August-2015 | 6.90 lakh | 2. | 30-September-2015 | 16.45 lakh | 3. | 28-October-2015 | 45.44 lakh | 4. | 30-December-2015 | 55.83 lakh | 5. | 29-February-2016 | 61.53 lakh | 6. | 13-April-2016 | 11.38 lakh | 7. | 30-April-2016 | 4.69 lakh | 8. | 25-June-2016 | 10.85 lakh | 9. | 04-August-2016 | 15.37 lakh | 10. | 05-October-2016 | 17.89 lakh | 11. | 25-October-2016 | 21.06 lakh | 12. | 28-February-2017 | 42.71 lakh | 13. | 25-April-2017 | 1.95 lakh | 14. | 31-May-2017 | 0.97 lakh | 15. | 20-June-2017 | 4.61 lakh |
Total |
317.63 lakh |
% Payment | 22.31 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1079 No. of Test Done : 1105 No. of Test Passed : 1079 No. of Test Failed : 1 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.01 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 16 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 12-11-2016 | Chainage- 40+700 | PC work at deghat bungidhar road | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
2. | 12-11-2016 | Chainage-40+700 | PC work in progress | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
3. | 12-11-2016 | Chainage-41.640 | PC work package C-61deghat bungidhar road | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
4. | 20-10-2016 | Chainage-39.500 | PC work deghat bungidhar road package-C61 | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
5. | 20-10-2016 | Chainage-39.650 | PC work in progress pacakge C-61 deghat bungidhar road | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
6. | 02-10-2016 | Chainage-37.800 | Seal coat over pc | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
7. | 02-10-2016 | Chainage-38.00 | PC work | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
8. | 25-09-2016 | Chainage-37.900 | PC work package C61 deghat bungidhar | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
9. | 20-09-2016 | Chainage-37.400 deghat bungidhar road | Cleaning of road surface for pc and EE Sir visit | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
10. | 07-09-2016 | 35.090 | Crash barrier work done at c61 deghay bungidhar motor road | Pooja Garg | JE | UEAP R&B Almora | See Pic |
11. | 07-09-2016 | 35.070 | Crus barrier at c 61 deghat bungidhar motor road | Pooja Garg | JE | UEAP R&B Almora | See Pic |
12. | 07-09-2016 | 36.830 | Pc work done c61 at deghat bungidhar motor road | Pooja Garg | JE | UEAP R&B Almora | See Pic |
13. | 07-09-2016 | 36.500 | Pc work done at c 61 deghat bungidhar | Pooja Garg | JE | UEAP R&B Almora | See Pic |
14. | 07-09-2016 | 36.950 | Pc work done c61 deghat bungidhar motor road | Pooja Garg | JE | UEAP R&B Almora | See Pic |
15. | 07-09-2016 | 1.450 | Pc work done c 61 deghat bungidhar | Pooja Garg | JE | UEAP R&B Almora | See Pic |
16. | 04-05-2016 | 35.050 | Profile levelling for cc shoulher protection work | Pooja Garg | JE | UEAP R&B Almora | See Pic |
|
|