Bhatrojkhan Bhikiyasain Chokhutiya Motor road
Work Completed
|
Project: |
UEAP-RB |
UID: |
5819 |
Sanction Cost: |
1132.00 lakh |
Length:
|
KM. |
District: |
Almora |
Block: |
Bhikiyasain |
Constituency: |
Dwarahat |
Circle: |
|
DEA: |
DEA UEAP Almora |
DSC: |
CCEE Group India Pvt.Ltd |
DSC Scope: |
Design and Supervision |
Type: |
SH |
|
Procurement: |
Package No.: 1065
Package Name: 
UEAP/PWD/C61
Tender Date: 28-10-2014
Current Status: Agreement signed
Achieved on Date: 12-02-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C61
Contractor Name: Jagdish Saran
|
Start Date: 07-03-2015
Intended Completion Date: 21-12-2016
Original End Date: 06-09-2016 |
Total Bond Cost: 119197725.82 (1191.98 lakh)
Variation Cost: 23156147.76 (231.56 lakh) Hence Total Bond Cost is 142353873.58 (1423.54 lakh)
|
Sub Project Cost: 1423.54 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 6377093 for 107 days
LD Analysis for Milestone2: calculated LD is Rs 5542707 for 93 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 4.00 KM | 13.41 | 14-06-2015 | 15-08-2016 | 4.00 KM | 4.00 KM | 1.24 | 13.41 | 2. | R/Wall, B/ Wall Type Protection works | 2100.00 m | 217.57 | 14-06-2015 | 20-08-2016 | 2100.00 m | 2100.00 m | 20.05 | 217.57 | 3. | G-2 | 4.00 KM | 14.69 | 10-02-2016 | 20-06-2016 | 4.00 KM | 4.00 KM | 1.35 | 14.69 | 4. | G-3 | 5.50 KM | 23.23 | 10-02-2016 | 20-06-2016 | 5.50 KM | 5.50 KM | 2.14 | 23.23 | 5. | PC/CC i/c Prime Coat, Tack Coat | 0.93 KM | 7.21 | 15-03-2016 | 20-08-2016 | 0.93 KM | 0.93 KM | 0.67 | 7.21 | 6. | BM i/c Prime Coat, Tack Coat | 20.00 KM | 266.39 | 20-03-2016 | 20-08-2016 | 20.00 KM | 20.00 KM | 24.54 | 266.39 | 7. | SDBC i/c Tackcoat | 20.00 KM | 281.56 | 20-04-2016 | 20-08-2016 | 20.00 KM | 20.00 KM | 25.94 | 281.56 | 8. | Cause Way | 2.00 No | 5.14 | 01-10-2015 | 14-06-2016 | 2.00 No | 2.00 No | 0.47 | 5.14 | 9. | Culverts/Scupper | 20.00 No | 44.07 | 01-10-2015 | 14-06-2016 | 20.00 No | 20.00 No | 4.06 | 44.07 | 10. | longitudinal Drain | 20000.00 m | 59.31 | 25-06-2015 | 20-08-2016 | 20000.00 m | 20000.00 m | 5.46 | 59.31 | 11. | Crash Barrier | 3257.00 m | 71.07 | 01-03-2016 | 20-08-2016 | 3520.00 m | 3520.00 m | 6.55 | 71.07 | 12. | Parapet | 1020.00 No | 31.78 | 25-01-2016 | 20-08-2016 | 1020.00 No | 1020.00 No | 2.93 | 31.78 | 13. | Road Furniture | 167.00 No | 28.12 | 20-03-2016 | 20-11-2016 | 86.00 No | 86.00 No | 2.59 | 28.12 | 14. | Other Allied Works & Finishing Work | 1.00 Job | 21.83 | 14-06-2015 | 20-11-2016 | 1.00 Job | 1.00 Job | 2.01 | 21.83 |
Total Amount: |
1085.38 |
|
100 |
1085.38 |
|
Remarks:
Work Program Made On:
24-08-2015 } ?>
Updation of work program on:
25-09-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-August-2015 | 30.46 lakh | 2. | 26-October-2015 | 49.54 lakh | 3. | 30-December-2015 | 47.11 lakh | 4. | 29-February-2016 | 96.57 lakh | 5. | 13-April-2016 | 66.43 lakh | 6. | 30-April-2016 | 20.80 lakh | 7. | 01-June-2016 | 41.58 lakh | 8. | 25-June-2016 | 133.47 lakh | 9. | 04-August-2016 | 60.83 lakh | 10. | 05-October-2016 | 177.99 lakh | 11. | 10-October-2016 | 96.82 lakh | 12. | 25-October-2016 | 112.36 lakh | 13. | 25-November-2016 | 56.59 lakh | 14. | 28-February-2017 | 66.03 lakh | 15. | 25-April-2017 | 8.58 lakh | 16. | 31-May-2017 | 20.22 lakh | 17. | 20-June-2017 | 20.52 lakh |
Total |
1105.9 lakh |
% Payment | 77.69 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1079 No. of Test Done : 1105 No. of Test Passed : 1079 No. of Test Failed : 1 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.12 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 68 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 29-11-2016 | Chainage-31+400 | Shoulder protection work | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
2. | 12-11-2016 | Hot mix plant | Bitumen extraction test for BC | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
3. | 20-10-2016 | 42.800 | Bm laying work in progress at pacakge c61 | Pooja Garg | JE | UEAP R&B Almora | See Pic |
4. | 20-10-2016 | Package C61 | Traffic sign board fixing | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
5. | 20-10-2016 | Chainage-42.800 | BM rolling in progress | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
6. | 18-10-2016 | 35.740 | Bm laying work in progress at c61 bhikiyashain masi motor road | Pooja Garg | JE | UEAP R&B Almora | See Pic |
7. | 18-10-2016 | 35.750 | Bm laying work in progress at c61 bhikiyashain masi motor road | Pooja Garg | JE | UEAP R&B Almora | See Pic |
8. | 18-10-2016 | 34.350 | BC work laying in progress at c61 bhikiyashain masi motor road | Pooja Garg | JE | UEAP R&B Almora | See Pic |
9. | 18-10-2016 | 34.350 | BC laying work in progress at c61 bhikiyashain masi motor road | Pooja Garg | JE | UEAP R&B Almora | See Pic |
10. | 18-10-2016 | 33.800 | BC laying work in progress at c61 bhikiyashain masi motor road | Pooja Garg | JE | UEAP R&B Almora | See Pic |
11. | 11-10-2016 | Chainage-39.650 | BC rolling in progress | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
12. | 11-10-2016 | Chainage-39.300 | BC work in progress | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
13. | 11-10-2016 | Chainage-39.200 | BM work in progress | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
14. | 11-10-2016 | Chainage-38+250 | BC rolling in progress | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
15. | 02-10-2016 | Chainage-37.550 | BM work in progress | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
16. | 02-10-2016 | Chainage-35.200 package C61 | BC surface after compaction | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
17. | 25-09-2016 | Chainage-35.410 | BC work in progress | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
18. | 25-09-2016 | Chainage-35.380 | BC laying in progress | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
19. | 25-09-2016 | Chainage-35.360 | BC rolling in progress | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
20. | 25-09-2016 | Hot mix plant | Aggragate grading test for BM | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
|
|