Kosi-Daulaghat Motor Raod
Work Completed
|
Project: |
UEAP-RB |
UID: |
5817 |
Sanction Cost: |
2528.00 lakh |
Length:
|
0.000 KM. |
District: |
Almora |
Block: |
Hawal Bagh |
Constituency: |
Someshwar |
Circle: |
|
DEA: |
DEA UEAP Almora |
DSC: |
CCEE Group India Pvt.Ltd |
DSC Scope: |
Design and Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1064
Package Name: 
UEAP/PWD/C60
Tender Date: 28-10-2014
Current Status: Agreement signed
Achieved on Date: 19-02-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C60
Contractor Name: Shiva Buildtech
|
Start Date: 13-03-2015
Intended Completion Date: 12-09-2016
|
Total Bond Cost: 204735793.42 (2047.36 lakh)
Variation Cost: 61088958.28 (610.89 lakh) Hence Total Bond Cost is 265824751.7 (2658.25 lakh)
|
Sub Project Cost: 2672.96 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 9315488 for 91 days
LD Analysis for Milestone2: calculated LD is Rs 5732608 for 56 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 6.00 KM | 8.18 | 15-03-2015 | 30-07-2016 | 6.00 KM | 6.00 KM | 0.45 | 8.18 | 2. | R/Wall, B/ Wall Type Protection works | 2700.00 m | 209.71 | 15-04-2015 | 10-09-2016 | 2700.00 m | 2700.00 m | 11.4 | 209.71 | 3. | GSB/RBI/G-1 | 0.05 KM | 0.13 | 01-08-2015 | 20-08-2016 | 0.05 KM | 0.05 KM | 0.01 | 0.13 | 4. | G-2 | 3.80 KM | 5.08 | 01-08-2015 | 20-08-2016 | 3.80 KM | 3.80 KM | 0.28 | 5.08 | 5. | G-3 | 13.10 KM | 21.97 | 15-08-2015 | 20-08-2016 | 13.10 KM | 13.10 KM | 1.19 | 21.97 | 6. | PC/CC i/c Prime Coat, Tack Coat | 11.90 KM | 8.91 | 01-05-2015 | 30-09-2016 | 11.90 KM | 11.90 KM | 0.48 | 8.91 | 7. | BM i/c Prime Coat, Tack Coat | 33.65 KM | 516.13 | 01-10-2015 | 05-09-2016 | 33.65 KM | 33.65 KM | 28.05 | 516.13 | 8. | SDBC i/c Tackcoat | 35.15 KM | 589.56 | 15-02-2016 | 10-09-2016 | 35.15 KM | 35.15 KM | 32.04 | 589.56 | 9. | Cause Way | 10.00 No | 26.44 | 01-05-2015 | 15-08-2016 | 10.00 No | 10.00 No | 1.44 | 26.44 | 10. | Culverts/Scupper | 32.00 No | 59.66 | 01-04-2015 | 30-08-2016 | 32.00 No | 32.00 No | 3.24 | 59.66 | 11. | longitudinal Drain | 33238.83 m | 97.80 | 01-04-2016 | 12-09-2016 | 36660.00 m | 36660.00 m | 5.32 | 97.80 | 12. | Crash Barrier | 4329.40 m | 147.08 | 01-04-2016 | 12-09-2016 | 3440.00 m | 3440.00 m | 7.99 | 147.08 | 13. | Parapet | 2563.00 No | 103.29 | 01-06-2015 | 12-09-2016 | 2000.00 No | 2000.00 No | 5.61 | 103.29 | 14. | Road Furniture | 246.00 No | 40.52 | 01-04-2016 | 12-09-2016 | 70.00 No | 70.00 No | 2.2 | 40.52 | 15. | Other Allied Works & Finishing Work | 1.00 Job | 5.58 | 15-03-2015 | 12-09-2016 | 1.00 Job | 1.00 Job | 0.3 | 5.58 |
Total Amount: |
1840.04 |
|
100 |
1840.04 |
|
Remarks:
Work Program Made On:
23-07-2015 } ?>
Updation of work program on:
20-09-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 04-July-2015 | 46.56 lakh | 2. | 30-September-2015 | 33.23 lakh | 3. | 07-November-2015 | 134.01 lakh | 4. | 30-November-2015 | 135.45 lakh | 5. | 30-December-2015 | 99.80 lakh | 6. | 28-February-2016 | 16.16 lakh | 7. | 29-February-2016 | 37.61 lakh | 8. | 26-March-2016 | 216.24 lakh | 9. | 30-April-2016 | 205.39 lakh | 10. | 18-May-2016 | 150.48 lakh | 11. | 30-May-2016 | 66.71 lakh | 12. | 31-May-2016 | 40.56 lakh | 13. | 22-June-2016 | 20.78 lakh | 14. | 14-July-2016 | 97.32 lakh | 15. | 11-August-2016 | 192.53 lakh | 16. | 30-September-2016 | 66.71 lakh | 17. | 26-October-2016 | 77.46 lakh | 18. | 05-December-2016 | 25.99 lakh | 19. | 23-February-2017 | 27.63 lakh | 20. | 28-February-2017 | 90.49 lakh | 21. | 31-May-2017 | 49.77 lakh | 22. | 20-June-2017 | 11.09 lakh |
Total |
1841.97 lakh |
% Payment | 68.91 % |
|
Advance Amount: 211.14 lakh
Recovered Amount: 211.14 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1757 No. of Test Done : 1789 No. of Test Passed : 1689 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.33 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 137 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 08-02-2017 | | Parapets ,edge line,BC work completed. | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
2. | 08-02-2017 | | Parapets edge line bc work completed | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
3. | 08-02-2017 | | Parapets work | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
4. | 08-02-2017 | | Crash barrier,edge line ,bc work completed | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
5. | 08-02-2017 | | Bc work completed | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
6. | 08-02-2017 | | Parapets ,edge line ,BC work completed | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
7. | 08-02-2017 | | Egde line ,BC work,signage board 5th km stone work completed | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
8. | 08-02-2017 | | Edge line, BC work, signage board work completed | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
9. | 08-02-2017 | | Edge line BC work parapets signage | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
10. | 08-02-2017 | | Parapets work completed | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
11. | 08-02-2017 | | Parapets edge line BC work.. | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
12. | 08-02-2017 | | Parapets edge line sign board and BC work | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
13. | 08-02-2017 | Starting point | Starting point kosi daulahat road at junction of NH 87E | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
14. | 09-10-2016 | Ch 13.070 | Core cutting for BM/SDBC work | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
15. | 09-10-2016 | Ch 13.220 | Core cutting for BM/SDBC | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
16. | 09-10-2016 | Ch 12.800 | B/wall work is in progress | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
17. | 09-10-2016 | Ch 13.950 | Kc Drain and shoulder Protection work is completed | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
18. | 09-10-2016 | 13.850 | Shoulder protection and KC Drain work completed | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
19. | 09-10-2016 | Ch 14.600 | K.c.drain & soulder protection work is completed | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
20. | 09-10-2016 | Ch 14.700 | B/Wall work is in progress | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
|
|