Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Kosi-Daulaghat Motor Raod Work Completed
Project: UEAP-RB UID: 5817 Sanction Cost: 2528.00  lakh Length: 0.000 KM.
District: Almora Block: Hawal Bagh Constituency: Someshwar Circle:
DEA: DEA UEAP Almora DSC: CCEE Group India Pvt.Ltd DSC Scope: Design and Supervision Type: MDR
Procurement:
Package No.: 1064        Package Name:  UEAP/PWD/C60        Tender Date: 28-10-2014        Current Status: Agreement signed        Achieved on Date: 19-02-2015

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C60      Contractor Name: Shiva Buildtech
Start Date:  13-03-2015      Intended Completion Date:  12-09-2016     
Total Bond Cost: 204735793.42 (2047.36 lakh)        Variation Cost: 61088958.28 (610.89 lakh)    Hence Total Bond Cost is   265824751.7 (2658.25 lakh) 
Sub Project Cost: 2672.96  lakh       
LD Analysis for Milestone1: calculated LD is Rs 9315488 for 91 days        LD Analysis for Milestone2: calculated LD is Rs 5732608 for 56 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence6.00 KM8.1815-03-201530-07-20166.00 KM6.00 KM0.458.18
2.R/Wall, B/ Wall Type Protection works2700.00 m209.7115-04-201510-09-20162700.00 m2700.00 m11.4209.71
3.GSB/RBI/G-10.05 KM0.1301-08-201520-08-20160.05 KM0.05 KM0.010.13
4.G-23.80 KM5.0801-08-201520-08-20163.80 KM3.80 KM0.285.08
5.G-313.10 KM21.9715-08-201520-08-201613.10 KM13.10 KM1.1921.97
6.PC/CC i/c Prime Coat, Tack Coat11.90 KM8.9101-05-201530-09-201611.90 KM11.90 KM0.488.91
7.BM i/c Prime Coat, Tack Coat33.65 KM516.1301-10-201505-09-201633.65 KM33.65 KM28.05516.13
8.SDBC i/c Tackcoat35.15 KM589.5615-02-201610-09-201635.15 KM35.15 KM32.04589.56
9.Cause Way10.00 No26.4401-05-201515-08-201610.00 No10.00 No1.4426.44
10.Culverts/Scupper 32.00 No59.6601-04-201530-08-201632.00 No32.00 No3.2459.66
11.longitudinal Drain33238.83 m97.8001-04-201612-09-201636660.00 m36660.00 m5.3297.80
12.Crash Barrier4329.40 m147.0801-04-201612-09-20163440.00 m3440.00 m7.99147.08
13.Parapet2563.00 No103.2901-06-201512-09-20162000.00 No2000.00 No5.61103.29
14.Road Furniture246.00 No40.5201-04-201612-09-201670.00 No70.00 No2.240.52
15.Other Allied Works & Finishing Work 1.00 Job5.5815-03-201512-09-20161.00 Job1.00 Job0.35.58
Total Amount: 1840.04 100   1840.04
Remarks:        Work Program Made On: 23-07-2015        Updation of work program on: 20-09-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.04-July-201546.56  lakh
2.30-September-201533.23  lakh
3.07-November-2015134.01  lakh
4.30-November-2015135.45  lakh
5.30-December-201599.80  lakh
6.28-February-201616.16  lakh
7.29-February-201637.61  lakh
8.26-March-2016216.24  lakh
9.30-April-2016205.39  lakh
10.18-May-2016150.48  lakh
11.30-May-201666.71  lakh
12.31-May-201640.56  lakh
13.22-June-201620.78  lakh
14.14-July-201697.32  lakh
15.11-August-2016192.53  lakh
16.30-September-201666.71  lakh
17.26-October-201677.46  lakh
18.05-December-201625.99  lakh
19.23-February-201727.63  lakh
20.28-February-201790.49  lakh
21.31-May-201749.77  lakh
22.20-June-201711.09  lakh
Total 1841.97  lakh
% Payment68.91 %
Advance Amount:  211.14  lakh        Recovered Amount:  211.14  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1757   No. of Test Done : 1789    No. of Test Passed : 1689   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 88.33
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 137
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-02-2017Parapets ,edge line,BC work completed.Vibhor GuptaAEUEAP R&B Almora See Pic
2.08-02-2017Parapets edge line bc work completedVibhor GuptaAEUEAP R&B Almora See Pic
3.08-02-2017Parapets workVibhor GuptaAEUEAP R&B Almora See Pic
4.08-02-2017Crash barrier,edge line ,bc work completedVibhor GuptaAEUEAP R&B Almora See Pic
5.08-02-2017Bc work completedVibhor GuptaAEUEAP R&B Almora See Pic
6.08-02-2017Parapets ,edge line ,BC work completedVibhor GuptaAEUEAP R&B Almora See Pic
7.08-02-2017Egde line ,BC work,signage board 5th km stone work completedVibhor GuptaAEUEAP R&B Almora See Pic
8.08-02-2017Edge line, BC work, signage board work completedVibhor GuptaAEUEAP R&B Almora See Pic
9.08-02-2017Edge line BC work parapets signageVibhor GuptaAEUEAP R&B Almora See Pic
10.08-02-2017Parapets work completedVibhor GuptaAEUEAP R&B Almora See Pic
11.08-02-2017Parapets edge line BC work..Vibhor GuptaAEUEAP R&B Almora See Pic
12.08-02-2017Parapets edge line sign board and BC workVibhor GuptaAEUEAP R&B Almora See Pic
13.08-02-2017Starting pointStarting point kosi daulahat road at junction of NH 87EVibhor GuptaAEUEAP R&B Almora See Pic
14.09-10-2016Ch 13.070Core cutting for BM/SDBC workGaurav BishtJEUEAP R&B Almora See Pic
15.09-10-2016Ch 13.220Core cutting for BM/SDBCGaurav BishtJEUEAP R&B Almora See Pic
16.09-10-2016Ch 12.800B/wall work is in progressGaurav BishtJEUEAP R&B Almora See Pic
17.09-10-2016Ch 13.950Kc Drain and shoulder Protection work is completedGaurav BishtJEUEAP R&B Almora See Pic
18.09-10-201613.850Shoulder protection and KC Drain work completedGaurav BishtJEUEAP R&B Almora See Pic
19.09-10-2016Ch 14.600K.c.drain & soulder protection work is completedGaurav BishtJEUEAP R&B Almora See Pic
20.09-10-2016Ch 14.700B/Wall work is in progressGaurav BishtJEUEAP R&B Almora See Pic