Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Reconstruction of internal road of Nagar Panchayat Ranikhet Work Completed
Project: UEAP-RB UID: 5806 Sanction Cost: 285.00  lakh Length: 6.000 KM.
District: Almora Block: Tarikhet Constituency: Ranikhet Circle:
DEA: DEA UEAP Almora DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design & Supervision Type: Urban
Procurement:
Package No.: 1019        Package Name:  UEAP/PWD/C17-A        Tender Date: 28-03-2014        Current Status: Agreement signed        Achieved on Date: 26-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C17-A      Contractor Name: R.G. Buildwell.
Start Date:  16-12-2014      Intended Completion Date:  26-10-2016      Original End Date:  15-06-2016
Total Bond Cost: 31282100 (312.82 lakh)        Variation Cost: 717899.50 (7.18 lakh)    Hence Total Bond Cost is   31999999.5 (320 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence3.67 KM6.4516-12-201526-10-20163.67 KM3.67 KM2.036.45
2.R/Wall, B/ Wall Type Protection works200.00 m3.9120-03-201520-10-2016200.00 m200.00 m1.233.91
3.GSB/RBI/G-13.65 KM31.4910-01-201530-09-20163.65 KM3.65 KM9.9231.49
4.G-23.65 KM7.4620-01-201530-09-20163.65 KM3.65 KM2.357.46
5.G-33.65 KM7.8302-02-201530-09-20163.65 KM3.65 KM2.477.83
6.PC/CC i/c Prime Coat, Tack Coat3.67 KM60.2710-04-201530-09-20163.67 KM3.67 KM18.9860.27
7.BM i/c Prime Coat, Tack Coat0.20 KM6.9115-03-201527-03-20150.20 KM0.20 KM2.186.91
8.SDBC i/c Tackcoat2.00 KM47.7015-03-201527-03-20152.00 KM2.00 KM15.0347.70
9.Culverts/Scupper 3.00 No3.2520-03-201510-08-20163.00 No3.00 No1.023.25
10.longitudinal Drain3643.75 m57.3101-04-201510-10-20163643.75 m3643.75 m18.0557.31
11.Crash Barrier950.00 m29.4520-06-201526-10-2016950.00 m950.00 m9.2829.45
12.Road Furniture60.00 No53.5820-05-201526-10-201660.00 No60.00 No16.8853.58
13.Other Allied Works & Finishing Work 1.00 Job1.8720-12-201426-10-20161.00 Job1.00 Job0.591.87
Total Amount: 317.48 100   317.48
Remarks:        Work Program Made On: 24-06-2015        Updation of work program on: 20-09-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-March-201582.87  lakh
2.25-June-201525.42  lakh
3.07-November-201545.19  lakh
4.29-February-201616.71  lakh
5.31-March-201612.17  lakh
6.08-September-201624.40  lakh
7.25-October-201610.69  lakh
8.25-March-201728.71  lakh
9.20-June-201731.78  lakh
10.13-October-201739.55  lakh
Total 317.49  lakh
% Payment 99.21 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.31  lakh        Balance to be Recovered  -0.31  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 140   No. of Test Done : 135    No. of Test Passed : 122   No. of Test Failed : 0    No. of Test Result Awaited : 10     Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.25
Number of Notice(s) issued: 76

Mobile Pic Upload

Number of Pics Available on Web Repository: 41
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-02-2017Ch 30.500Interlocking tiling work is completedGaurav BishtJEUEAP R&B Almora See Pic
2.08-02-2017Ch 30.700 near Vijay chokInterlocking tiling work is comletedGaurav BishtJEUEAP R&B Almora See Pic
3.08-02-2017Ch 30.300 near Vijay ChaukInterlocking tiling work is in progress.Gaurav BishtJEUEAP R&B Almora See Pic
4.29-08-2016Ch 27.200KC Drain work is in progressGaurav BishtJEUEAP R&B Almora See Pic
5.28-08-2016Ch 30.900Interlocking pavement work is in progressGaurav BishtJEUEAP R&B Almora See Pic
6.28-08-2016Ch 28.850Interlocking pavement work is in progress near KMOU stationGaurav BishtJEUEAP R&B Almora See Pic
7.28-08-2016Ch 27.800KC Drain work completedGaurav BishtJEUEAP R&B Almora See Pic
8.28-08-2016Ch 27.450KC Drain work completedGaurav BishtJEUEAP R&B Almora See Pic
9.28-08-2016Ch 27.500KC Drain work completedGaurav BishtJEUEAP R&B Almora See Pic
10.28-08-2016Ch 26.600Crash barrier work completedGaurav BishtJEUEAP R&B Almora See Pic
11.11-05-2016Ch 29.250Interlocking tile work in progress near taxi stand KMOU stationChetan BhattJEUEAP R&B Almora See Pic
12.07-05-2016Ch 28.700K C drain after completionChetan BhattJEUEAP R&B Almora See Pic
13.07-05-2016Ch 28.700KC drain in progressChetan BhattJEUEAP R&B Almora See Pic
14.26-04-2016Ch 29.400Fixing of curve stone for KC Drain in progressChetan BhattJEUEAP R&B Almora See Pic
15.08-04-2016Ch 26.500OPC cement used at siteChetan BhattJEUEAP R&B Almora See Pic
16.01-04-2016Ch 26.060Delenators fixed at siteChetan BhattJEUEAP R&B Almora See Pic
17.14-03-2016Ch 29.200Staking of interlocking tileChetan BhattJEUEAP R&B Almora See Pic
18.14-03-2016Ch 29.200Excavation for KC drainChetan BhattJEUEAP R&B Almora See Pic
19.12-03-2016Ch 29.500Excavation for hume pipe in progressChetan BhattJEUEAP R&B Almora See Pic
20.12-03-2016Ch 29.500Excavation for hume pipeChetan BhattJEUEAP R&B Almora See Pic