Reconstruction of internal road of Nagar Panchayat Ranikhet
Work Completed
|
Project: |
UEAP-RB |
UID: |
5806 |
Sanction Cost: |
285.00 lakh |
Length:
|
6.000 KM. |
District: |
Almora |
Block: |
Tarikhet |
Constituency: |
Ranikhet |
Circle: |
|
DEA: |
DEA UEAP Almora |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design & Supervision |
Type: |
Urban |
|
Procurement: |
Package No.: 1019
Package Name: 
UEAP/PWD/C17-A
Tender Date: 28-03-2014
Current Status: Agreement signed
Achieved on Date: 26-11-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C17-A
Contractor Name: R.G. Buildwell.
|
Start Date: 16-12-2014
Intended Completion Date: 26-10-2016
Original End Date: 15-06-2016 |
Total Bond Cost: 31282100 (312.82 lakh)
Variation Cost: 717899.50 (7.18 lakh) Hence Total Bond Cost is 31999999.5 (320 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 3.67 KM | 6.45 | 16-12-2015 | 26-10-2016 | 3.67 KM | 3.67 KM | 2.03 | 6.45 | 2. | R/Wall, B/ Wall Type Protection works | 200.00 m | 3.91 | 20-03-2015 | 20-10-2016 | 200.00 m | 200.00 m | 1.23 | 3.91 | 3. | GSB/RBI/G-1 | 3.65 KM | 31.49 | 10-01-2015 | 30-09-2016 | 3.65 KM | 3.65 KM | 9.92 | 31.49 | 4. | G-2 | 3.65 KM | 7.46 | 20-01-2015 | 30-09-2016 | 3.65 KM | 3.65 KM | 2.35 | 7.46 | 5. | G-3 | 3.65 KM | 7.83 | 02-02-2015 | 30-09-2016 | 3.65 KM | 3.65 KM | 2.47 | 7.83 | 6. | PC/CC i/c Prime Coat, Tack Coat | 3.67 KM | 60.27 | 10-04-2015 | 30-09-2016 | 3.67 KM | 3.67 KM | 18.98 | 60.27 | 7. | BM i/c Prime Coat, Tack Coat | 0.20 KM | 6.91 | 15-03-2015 | 27-03-2015 | 0.20 KM | 0.20 KM | 2.18 | 6.91 | 8. | SDBC i/c Tackcoat | 2.00 KM | 47.70 | 15-03-2015 | 27-03-2015 | 2.00 KM | 2.00 KM | 15.03 | 47.70 | 9. | Culverts/Scupper | 3.00 No | 3.25 | 20-03-2015 | 10-08-2016 | 3.00 No | 3.00 No | 1.02 | 3.25 | 10. | longitudinal Drain | 3643.75 m | 57.31 | 01-04-2015 | 10-10-2016 | 3643.75 m | 3643.75 m | 18.05 | 57.31 | 11. | Crash Barrier | 950.00 m | 29.45 | 20-06-2015 | 26-10-2016 | 950.00 m | 950.00 m | 9.28 | 29.45 | 12. | Road Furniture | 60.00 No | 53.58 | 20-05-2015 | 26-10-2016 | 60.00 No | 60.00 No | 16.88 | 53.58 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 1.87 | 20-12-2014 | 26-10-2016 | 1.00 Job | 1.00 Job | 0.59 | 1.87 |
Total Amount: |
317.48 |
|
100 |
317.48 |
|
Remarks:
Work Program Made On:
24-06-2015 } ?>
Updation of work program on:
20-09-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-March-2015 | 82.87 lakh | 2. | 25-June-2015 | 25.42 lakh | 3. | 07-November-2015 | 45.19 lakh | 4. | 29-February-2016 | 16.71 lakh | 5. | 31-March-2016 | 12.17 lakh | 6. | 08-September-2016 | 24.40 lakh | 7. | 25-October-2016 | 10.69 lakh | 8. | 25-March-2017 | 28.71 lakh | 9. | 20-June-2017 | 31.78 lakh | 10. | 13-October-2017 | 39.55 lakh |
Total |
317.49 lakh |
% Payment |
99.21 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.31 lakh
Balance to be Recovered -0.31 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 140 No. of Test Done : 135 No. of Test Passed : 122 No. of Test Failed : 0
No. of Test Result Awaited : 10
Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.25 |
Number of Notice(s) issued: 76 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 41 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 08-02-2017 | Ch 30.500 | Interlocking tiling work is completed | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
2. | 08-02-2017 | Ch 30.700 near Vijay chok | Interlocking tiling work is comleted | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
3. | 08-02-2017 | Ch 30.300 near Vijay Chauk | Interlocking tiling work is in progress. | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
4. | 29-08-2016 | Ch 27.200 | KC Drain work is in progress | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
5. | 28-08-2016 | Ch 30.900 | Interlocking pavement work is in progress | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
6. | 28-08-2016 | Ch 28.850 | Interlocking pavement work is in progress near KMOU station | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
7. | 28-08-2016 | Ch 27.800 | KC Drain work completed | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
8. | 28-08-2016 | Ch 27.450 | KC Drain work completed | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
9. | 28-08-2016 | Ch 27.500 | KC Drain work completed | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
10. | 28-08-2016 | Ch 26.600 | Crash barrier work completed | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
11. | 11-05-2016 | Ch 29.250 | Interlocking tile work in progress near taxi stand KMOU station | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
12. | 07-05-2016 | Ch 28.700 | K C drain after completion | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
13. | 07-05-2016 | Ch 28.700 | KC drain in progress | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
14. | 26-04-2016 | Ch 29.400 | Fixing of curve stone for KC Drain in progress | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
15. | 08-04-2016 | Ch 26.500 | OPC cement used at site | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
16. | 01-04-2016 | Ch 26.060 | Delenators fixed at site | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
17. | 14-03-2016 | Ch 29.200 | Staking of interlocking tile | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
18. | 14-03-2016 | Ch 29.200 | Excavation for KC drain | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
19. | 12-03-2016 | Ch 29.500 | Excavation for hume pipe in progress | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
20. | 12-03-2016 | Ch 29.500 | Excavation for hume pipe | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
|
|