Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Ranikhet-Mohan Work Completed
Project: UEAP-RB UID: 5803 Sanction Cost: 150.00  lakh Length: 26.000 KM.
District: Almora Block: Sult Constituency: Ranikhet Circle:
DEA: DEA UEAP Almora DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design & Supervision Type: MDR
Procurement:
Package No.: 1003        Package Name:  UEAP/PWD/C2-B        Tender Date: 05-04-2014        Current Status: Agreement signed        Achieved on Date: 26-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C2-B      Contractor Name: Dwarika Projects Limited
Start Date:  17-12-2014      Intended Completion Date:  05-08-2017      Original End Date:  16-03-2016
Total Bond Cost: 15877150.75 (158.77 lakh)        Variation Cost: 622849.06 (6.23 lakh)    Hence Total Bond Cost is   16499999.81 (165 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 285804 for 36 days        LD Analysis for Milestone2: calculated LD is Rs 1079704 for 136 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence5.00 KM4.3001-01-201525-08-20165.00 KM5.00 KM2.614.30
2.R/Wall, B/ Wall Type Protection works220.00 m43.0901-02-201505-09-2016220.00 m220.00 m26.1243.09
3.GSB/RBI/G-10.05 KM0.3603-03-201530-06-20150.05 KM0.05 KM0.220.36
4.G-20.23 KM3.9903-03-201530-06-20150.23 KM0.23 KM2.423.99
5.G-30.23 KM5.3703-03-201530-06-20150.23 KM0.23 KM3.255.37
6.BM i/c Prime Coat, Tack Coat0.12 KM2.7002-05-201530-06-20150.12 KM0.12 KM1.642.70
7.SDBC i/c Tackcoat0.27 KM45.5803-05-201530-08-20160.27 KM0.27 KM27.6245.58
8.Cause Way2.00 No8.2201-04-201510-06-20162.00 No2.00 No4.988.22
9.longitudinal Drain14852.00 m48.7206-09-201505-08-20164850.00 m4850.00 m29.5348.72
10.Other Allied Works & Finishing Work 1.00 Job2.6701-01-201505-08-20161.00 Job1.00 Job1.622.67
Total Amount: 165 100   165
Remarks:        Work Program Made On: 05-04-2017        Updation of work program on: 20-09-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-March-20157.34  lakh
2.23-June-201524.04  lakh
3.25-July-201539.36  lakh
4.29-February-20168.56  lakh
5.17-December-201653.25  lakh
6.25-April-201731.85  lakh
7.29-September-20170.60  lakh
Total 165  lakh
% Payment 99.99 %
Advance Amount:  15.88  lakh        Recovered Amount:  15.88  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 190   No. of Test Done : 192    No. of Test Passed : 138   No. of Test Failed : 0    No. of Test Result Awaited : 50     Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 85.00
Number of Notice(s) issued: 84

Mobile Pic Upload

Number of Pics Available on Web Repository: 28
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.29-08-20163.700KC Drain work is in progressGaurav BishtJEUEAP R&B Almora See Pic
2.29-08-2016Ch 3.50 near Power houseKC Drain work is in progressGaurav BishtJEUEAP R&B Almora See Pic
3.28-08-2016Ch 0.025KC Drain work is in progressGaurav BishtJEUEAP R&B Almora See Pic
4.28-08-2016Ch 5.200 starting of Tarikhet marketKC Drain work is in progressGaurav BishtJEUEAP R&B Almora See Pic
5.20-05-2016Ch 12.500PCC for KC drainChetan BhattJEUEAP R&B Almora See Pic
6.13-07-2015Ch.65.300Causeway DamageA S BishtEEDEA ADB Almora See Pic
7.13-07-2015Ch.60.600LandslideA S BishtEEDEA ADB Almora See Pic
8.13-07-2015Ch. 22.200LandslideA S BishtEEDEA ADB Almora See Pic
9.23-06-2015KM 57Patch work is in progressGaurav BishtJEUEAP R&B Almora See Pic
10.23-06-2015At Plant near Soni MarketSDBC For patch WorkGaurav BishtJEUEAP R&B Almora See Pic
11.23-06-2015Km13 (Soni Daat)Patch Work is in ProgressGaurav BishtJEUEAP R&B Almora See Pic
12.23-06-2015Km 26 Near Inspection House PWDPatch Work is in ProgressGaurav BishtJEUEAP R&B Almora See Pic
13.23-06-2015Km 26 Near Petrol Pump BhatrojkhanPatch Work is in ProgressGaurav BishtJEUEAP R&B Almora See Pic
14.23-06-2015Km 26 near Bhatrojkhan Filling stationPatch work is in progressGaurav BishtJEUEAP R&B Almora See Pic
15.18-05-2015Ch.63.800Patch repair workA S BishtEEDEA ADB Almora See Pic
16.18-05-2015Ch.62.400R/Wall with toe wall & scupperA S BishtEEDEA ADB Almora See Pic
17.18-05-2015Ch.57.800R/Wall in 1:5A S BishtEEDEA ADB Almora See Pic
18.28-03-2015Ch 0000Forward FriDwarika cons ` ` See Pic
19.28-03-2015Ch 0000For billingRoad-5803 ` ` See Pic
20.23-03-2015Ch.57.500R/wall CompletedGaurav BishtJEUEAP R&B Almora See Pic