Ranikhet-Mohan
Work Completed
|
Project: |
UEAP-RB |
UID: |
5803 |
Sanction Cost: |
150.00 lakh |
Length:
|
26.000 KM. |
District: |
Almora |
Block: |
Sult |
Constituency: |
Ranikhet |
Circle: |
|
DEA: |
DEA UEAP Almora |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design & Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1003
Package Name: 
UEAP/PWD/C2-B
Tender Date: 05-04-2014
Current Status: Agreement signed
Achieved on Date: 26-11-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C2-B
Contractor Name: Dwarika Projects Limited
|
Start Date: 17-12-2014
Intended Completion Date: 05-08-2017
Original End Date: 16-03-2016 |
Total Bond Cost: 15877150.75 (158.77 lakh)
Variation Cost: 622849.06 (6.23 lakh) Hence Total Bond Cost is 16499999.81 (165 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 285804 for 36 days
LD Analysis for Milestone2: calculated LD is Rs 1079704 for 136 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 5.00 KM | 4.30 | 01-01-2015 | 25-08-2016 | 5.00 KM | 5.00 KM | 2.61 | 4.30 | 2. | R/Wall, B/ Wall Type Protection works | 220.00 m | 43.09 | 01-02-2015 | 05-09-2016 | 220.00 m | 220.00 m | 26.12 | 43.09 | 3. | GSB/RBI/G-1 | 0.05 KM | 0.36 | 03-03-2015 | 30-06-2015 | 0.05 KM | 0.05 KM | 0.22 | 0.36 | 4. | G-2 | 0.23 KM | 3.99 | 03-03-2015 | 30-06-2015 | 0.23 KM | 0.23 KM | 2.42 | 3.99 | 5. | G-3 | 0.23 KM | 5.37 | 03-03-2015 | 30-06-2015 | 0.23 KM | 0.23 KM | 3.25 | 5.37 | 6. | BM i/c Prime Coat, Tack Coat | 0.12 KM | 2.70 | 02-05-2015 | 30-06-2015 | 0.12 KM | 0.12 KM | 1.64 | 2.70 | 7. | SDBC i/c Tackcoat | 0.27 KM | 45.58 | 03-05-2015 | 30-08-2016 | 0.27 KM | 0.27 KM | 27.62 | 45.58 | 8. | Cause Way | 2.00 No | 8.22 | 01-04-2015 | 10-06-2016 | 2.00 No | 2.00 No | 4.98 | 8.22 | 9. | longitudinal Drain | 14852.00 m | 48.72 | 06-09-2015 | 05-08-2016 | 4850.00 m | 4850.00 m | 29.53 | 48.72 | 10. | Other Allied Works & Finishing Work | 1.00 Job | 2.67 | 01-01-2015 | 05-08-2016 | 1.00 Job | 1.00 Job | 1.62 | 2.67 |
Total Amount: |
165 |
|
100 |
165 |
|
Remarks:
Work Program Made On:
05-04-2017 } ?>
Updation of work program on:
20-09-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-March-2015 | 7.34 lakh | 2. | 23-June-2015 | 24.04 lakh | 3. | 25-July-2015 | 39.36 lakh | 4. | 29-February-2016 | 8.56 lakh | 5. | 17-December-2016 | 53.25 lakh | 6. | 25-April-2017 | 31.85 lakh | 7. | 29-September-2017 | 0.60 lakh |
Total |
165 lakh |
% Payment |
99.99 % |
|
Advance Amount: 15.88 lakh
Recovered Amount: 15.88 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 190 No. of Test Done : 192 No. of Test Passed : 138 No. of Test Failed : 0
No. of Test Result Awaited : 50
Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 85.00 |
Number of Notice(s) issued: 84 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 28 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 29-08-2016 | 3.700 | KC Drain work is in progress | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
2. | 29-08-2016 | Ch 3.50 near Power house | KC Drain work is in progress | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
3. | 28-08-2016 | Ch 0.025 | KC Drain work is in progress | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
4. | 28-08-2016 | Ch 5.200 starting of Tarikhet market | KC Drain work is in progress | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
5. | 20-05-2016 | Ch 12.500 | PCC for KC drain | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
6. | 13-07-2015 | Ch.65.300 | Causeway Damage | A S Bisht | EE | DEA ADB Almora | See Pic |
7. | 13-07-2015 | Ch.60.600 | Landslide | A S Bisht | EE | DEA ADB Almora | See Pic |
8. | 13-07-2015 | Ch. 22.200 | Landslide | A S Bisht | EE | DEA ADB Almora | See Pic |
9. | 23-06-2015 | KM 57 | Patch work is in progress | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
10. | 23-06-2015 | At Plant near Soni Market | SDBC For patch Work | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
11. | 23-06-2015 | Km13 (Soni Daat) | Patch Work is in Progress | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
12. | 23-06-2015 | Km 26 Near Inspection House PWD | Patch Work is in Progress | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
13. | 23-06-2015 | Km 26 Near Petrol Pump Bhatrojkhan | Patch Work is in Progress | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
14. | 23-06-2015 | Km 26 near Bhatrojkhan Filling station | Patch work is in progress | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
15. | 18-05-2015 | Ch.63.800 | Patch repair work | A S Bisht | EE | DEA ADB Almora | See Pic |
16. | 18-05-2015 | Ch.62.400 | R/Wall with toe wall & scupper | A S Bisht | EE | DEA ADB Almora | See Pic |
17. | 18-05-2015 | Ch.57.800 | R/Wall in 1:5 | A S Bisht | EE | DEA ADB Almora | See Pic |
18. | 28-03-2015 | Ch 0000 | Forward Fri | Dwarika cons | ` | ` | See Pic |
19. | 28-03-2015 | Ch 0000 | For billing | Road-5803 | ` | ` | See Pic |
20. | 23-03-2015 | Ch.57.500 | R/wall Completed | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
|
|