NTD Kafarkhan- Dhaulchinna
Work Completed
|
Project: |
UEAP-RB |
UID: |
5801 |
Sanction Cost: |
436.00 lakh |
Length:
|
8.000 KM. |
District: |
Almora |
Block: |
Hawal Bagh |
Constituency: |
Almora |
Circle: |
|
DEA: |
DEA UEAP Almora |
DSC: |
CCEE Group India Pvt.Ltd |
DSC Scope: |
Design & Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1008
Package Name: 
UEAP/PWD/C6
Tender Date: 13-01-2014
Current Status: Agreement signed
Achieved on Date: 21-04-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C6
Contractor Name: R.G. Buildwell.
|
Start Date: 17-06-2014
Intended Completion Date: 15-06-2017
Original End Date: 16-09-2015 |
Total Bond Cost: 41547651.25 (415.48 lakh)
Variation Cost: 11452505.13 (114.53 lakh) Hence Total Bond Cost is 53000156.38 (530 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 4404088 for 212 days
LD Analysis for Milestone2: calculated LD is Rs 1724242 for 83 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 8.00 KM | 2.77 | 17-06-2014 | 16-09-2015 | 8.00 KM | 8.00 KM | 0.52 | 2.77 | 2. | R/Wall, B/ Wall Type Protection works | 460.00 m | 13.52 | 20-06-2014 | 31-03-2015 | 460.00 m | 460.00 m | 2.55 | 13.52 | 3. | GSB/RBI/G-1 | 0.20 KM | 0.03 | 15-08-2014 | 30-04-2015 | 0.20 KM | 0.20 KM | 0.01 | 0.03 | 4. | G-2 | 1.60 KM | 2.20 | 15-08-2014 | 15-05-2015 | 1.60 KM | 1.60 KM | 0.42 | 2.20 | 5. | G-3 | 6.00 KM | 3.21 | 15-08-2014 | 31-05-2015 | 6.00 KM | 6.00 KM | 0.61 | 3.21 | 6. | PC/CC i/c Prime Coat, Tack Coat | 0.67 KM | 4.33 | 01-04-2016 | 31-10-2016 | 0.67 KM | 0.67 KM | 0.82 | 4.33 | 7. | BM i/c Prime Coat, Tack Coat | 10.37 KM | 162.17 | 20-04-2015 | 30-05-2016 | 10.37 KM | 10.37 KM | 30.6 | 162.17 | 8. | SDBC i/c Tackcoat | 10.37 KM | 120.03 | 01-05-2015 | 05-06-2016 | 10.37 KM | 10.37 KM | 22.65 | 120.03 | 9. | Cause Way | 7.00 No | 5.36 | 17-06-2014 | 31-12-2014 | 7.00 No | 7.00 No | 1.01 | 5.36 | 10. | Culverts/Scupper | 8.00 No | 9.36 | 20-07-2014 | 31-03-2015 | 8.00 No | 8.00 No | 1.77 | 9.36 | 11. | longitudinal Drain | 9100.00 m | 31.40 | 20-05-2015 | 10-06-2016 | 9100.00 m | 9100.00 m | 5.93 | 31.40 | 12. | Crash Barrier | 2820.00 m | 86.26 | 10-12-2014 | 31-05-2016 | 2820.00 m | 2820.00 m | 16.28 | 86.26 | 13. | Parapet | 150.00 No | 4.93 | 25-06-2015 | 31-05-2016 | 150.00 No | 150.00 No | 0.93 | 4.93 | 14. | Road Furniture | 46.00 No | 80.43 | 25-06-2015 | 10-06-2016 | 46.00 No | 46.00 No | 15.18 | 80.43 | 15. | Other Allied Works & Finishing Work | 1.00 Job | 4.01 | 17-06-2014 | 15-06-2016 | 1.00 Job | 1.00 Job | 0.76 | 4.01 |
Total Amount: |
530.01 |
|
100 |
530.01 |
|
Remarks:
Work Program Made On:
24-06-2015 } ?>
Updation of work program on:
20-09-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 10-February-2015 | 7.65 lakh | 2. | 31-March-2015 | 27.36 lakh | 3. | 23-June-2015 | 52.14 lakh | 4. | 26-June-2015 | 105.95 lakh | 5. | 30-September-2015 | 105.45 lakh | 6. | 06-November-2015 | 59.22 lakh | 7. | 30-April-2016 | 27.92 lakh | 8. | 01-June-2016 | 68.74 lakh | 9. | 14-July-2016 | 50.52 lakh | 10. | 17-October-2016 | 8.65 lakh | 11. | 20-June-2017 | 16.39 lakh |
Total |
529.99 lakh |
% Payment |
99.99 % |
|
Advance Amount: 41.55 lakh
Recovered Amount: 41.55 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 403 No. of Test Done : 409 No. of Test Passed : 395 No. of Test Failed : 0
No. of Test Result Awaited : 1
Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 91.59 |
Number of Notice(s) issued: 71 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 46 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 08-02-2017 | Ch0.350 | After completion of work | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
2. | 08-02-2017 | Ch0.050 | After completion of work | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
3. | 01-09-2016 | Ch0.080 | Core Cutting of B M /SDBC | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
4. | 28-08-2016 | CH.7.600 | Crash Barrier work is in progress | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
5. | 28-08-2016 | Ch 2+900 | After completion of crash barrier, thermoplas paint work | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
6. | 28-08-2016 | Ch0+225 | After completion ofThermplastic paint&Road marker | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
7. | 04-06-2016 | Ch9+650 | Laying &Rolling of SDBC&is in progress | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
8. | 13-09-2015 | Km 6 | Laying of SDBC work is in progress | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
9. | 12-09-2015 | KM 7 | SDBC work is in prpgress | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
10. | 10-09-2015 | Ch7.400 | SDBC Work is in progress | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
11. | 10-09-2015 | Plant Site | Making and loading sdbc in tippers at plant | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
12. | 10-09-2015 | Plant site for NTD Kafarkhan M Road at kwarab Mona M Road | SDBC Material loading in Tippers | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
13. | 03-09-2015 | Ch 7.750 | B M work is in progress | A S Bisht | EE | DEA ADB Almora | See Pic |
14. | 28-08-2015 | Ch3.210 | Drain work is in progress | Ravi Shankar Joshi | AE | UEAB R&B Almora | See Pic |
15. | 06-08-2015 | LGCh4.080 near Kasardevi | Excavation for Hume pipe culvert | Ravi Shankar Joshi | AE | UEAB R&B Almora | See Pic |
16. | 07-07-2015 | Ch.7.060 | BM work is in progress | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
17. | 07-07-2015 | Ch.5.775 | BM Work is in Progress | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
18. | 25-06-2015 | Ch 5.900 | Cleaning of existing Surface for BM work | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
19. | 23-06-2015 | 5.600 | BM Work is in Progress Inspection by Cheif Engineer UEAP | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
20. | 09-05-2015 | Ch2.900 | BM &CrushBarier work | Gulab Ram | SE | ADB Circle | See Pic |
|
|