Protection/Treatment work on chronic land slide zone on Kapkot-Sama-Tejam MR in Km66(Chainage 66.00 to 66.80)
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5711 |
Sanction Cost: |
780.00 lakh |
Length:
|
0.800 KM. |
District: |
Bageshwar |
Block: |
Kapkot |
Constituency: |
Bageshwar |
Circle: |
|
DEA: |
DEA UEAP Bageshwar |
DSC: |
CCEE Group India Pvt.Ltd |
DSC Scope: |
Design and Supervision |
Type: |
SH |
|
Procurement: |
Package No.: 1104
Package Name: 
UEAP/PWD/C-119
Tender Date: 04-11-2016
Current Status: Agreement signed
Achieved on Date: 30-03-2017 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C-119
Contractor Name: JV of Spar & Hardik
|
Start Date: 20-04-2017
Intended Completion Date: 19-10-2017
|
Total Bond Cost: 71515552.6 (715.16 lakh)
Variation Cost: 10712109.38 (107.12 lakh) Hence Total Bond Cost is 82227661.98 (822.28 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 7258874 for 203 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.80 KM | 9.63 | 20-04-2017 | 25-05-2017 | 0.80 KM | 0.00 KM | 0 | 0.00 | 2. | R/Wall, B/ Wall Type Protection works | 800.00 m | 674.62 | 21-04-2017 | 15-10-2017 | 800.00 m | 300.00 m | 35.37 | 252.98 | 3. | longitudinal Drain | 800.00 m | 15.28 | 01-05-2017 | 30-07-2017 | 800.00 m | 350.00 m | 0.93 | 6.68 | 4. | Other Allied Works & Finishing Work | 1.00 Job | 15.63 | 20-05-2017 | 19-10-2017 | 1.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
715.16 |
|
36.31 |
259.66 |
|
Remarks:
No Remarks
Work Program Made On:
02-06-2017 } ?>
Updation of work program on:
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 06-June-2017 | 37.10 lakh | 2. | 05-August-2017 | 44.40 lakh | 3. | 16-September-2017 | 102.71 lakh | 4. | 29-September-2017 | 76.17 lakh | 5. | 12-October-2017 | 64.43 lakh |
Total |
324.81 lakh |
% Payment |
39.5 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
Staff not deputed yet
Environment & Social Compliances(Sub Project level):
No Pending Issue |
Detailed report of this subproject
|
|
Quality
|
No. of Test Required : 113 No. of Test Done : 124 No. of Test Passed : 113 No. of Test Failed : 11 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
Number of Notice(s) issued: 15 |
Mobile Pic Upload |
No Pics Available on Web Repository |
( last 20 Pics) |
No Pic uploaded. |
|