Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Baijnath-Gwaldam Work Completed
Project: UEAP-RB UID: 5707 Sanction Cost: 14.00  lakh Length: 3.190 KM.
District: Bageshwar Block: Garud Constituency: Bageshwar Circle:
DEA: DEA UEAP Bageshwar DSC: Royal Haskoning DHV DSC Scope: Design & Supervision Type: Not known
Procurement:
Package No.: 1050        Package Name:  UEAP/PWD/C47        Tender Date: 03-05-2014        Current Status: Agreement signed        Achieved on Date: 15-09-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C47      Contractor Name: Zender Engineers Ltd
Start Date:  20-11-2014      Intended Completion Date:  19-11-2015     
Total Bond Cost: 2717115.6 (27.17 lakh)       
Sub Project Cost: 14.00  lakh       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 93771 for 69 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.longitudinal Drain600.00 m14.5601-10-201517-11-2015600.00 m600.00 m10014.56
Total Amount: 14.56 100   14.56
Remarks: No Remarks       Work Program Made On: 29-06-2015        Updation of work program on: 04-01-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.11-August-201613.50  lakh
Total 13.5  lakh
% Payment96.43 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 49   No. of Test Done : 49    No. of Test Passed : 49   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 2
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-03-201685.450-85.500/near bajrikhanDrain construction in almora gualdam M/R.Jagdish Kumar TamtaAAEUEAP R&B Bageshwar See Pic
2.03-09-201586.070-86.100/near gualdamDrain construction work done in almora gualdam M/RJagdish Kumar TamtaAAEUEAP R&B Bageshwar See Pic