Baijnath-Gwaldam
Work Completed
|
Project: |
UEAP-RB |
UID: |
5707 |
Sanction Cost: |
14.00 lakh |
Length:
|
3.190 KM. |
District: |
Bageshwar |
Block: |
Garud |
Constituency: |
Bageshwar |
Circle: |
|
DEA: |
DEA UEAP Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
Design & Supervision |
Type: |
Not known |
|
Procurement: |
Package No.: 1050
Package Name: 
UEAP/PWD/C47
Tender Date: 03-05-2014
Current Status: Agreement signed
Achieved on Date: 15-09-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C47
Contractor Name: Zender Engineers Ltd
|
Start Date: 20-11-2014
Intended Completion Date: 19-11-2015
|
Total Bond Cost: 2717115.6 (27.17 lakh)
|
Sub Project Cost: 14.00 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 93771 for 69 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | longitudinal Drain | 600.00 m | 14.56 | 01-10-2015 | 17-11-2015 | 600.00 m | 600.00 m | 100 | 14.56 |
Total Amount: |
14.56 |
|
100 |
14.56 |
|
Remarks:
No Remarks
Work Program Made On:
29-06-2015 } ?>
Updation of work program on:
04-01-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 11-August-2016 | 13.50 lakh |
Total |
13.5 lakh |
% Payment | 96.43 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 49 No. of Test Done : 49 No. of Test Passed : 49 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 2 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 27-03-2016 | 85.450-85.500/near bajrikhan | Drain construction in almora gualdam M/R. | Jagdish Kumar Tamta | AAE | UEAP R&B Bageshwar | See Pic |
2. | 03-09-2015 | 86.070-86.100/near gualdam | Drain construction work done in almora gualdam M/R | Jagdish Kumar Tamta | AAE | UEAP R&B Bageshwar | See Pic |
|
|