Bageshwar-Kapkot-Sama-Tejam
Work Completed
|
Project: |
UEAP-RB |
UID: |
5704 |
Sanction Cost: |
1172.00 lakh |
Length:
|
35.000 KM. |
District: |
Bageshwar |
Block: |
Kapkot |
Constituency: |
Kapkote |
Circle: |
|
DEA: |
DEA UEAP Bageshwar |
DSC: |
|
DSC Scope: |
Design & Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1029
Package Name: 
UEAP/PWD/C26
Tender Date: 31-03-2014
Current Status: Agreement signed
Achieved on Date: 29-09-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C26
Contractor Name: Bharat Construction
|
Start Date: 08-10-2014
Intended Completion Date: 07-04-2016
|
Total Bond Cost: 71283437.6 (712.83 lakh)
Variation Cost: 16203407.47 (162.03 lakh) Hence Total Bond Cost is 87486845.07 (874.87 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 6593770 for 185 days
LD Analysis for Milestone2: calculated LD is Rs 6486844 for +182 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 17.00 KM | 36.12 | 01-12-2015 | 30-01-2016 | 17.00 KM | 17.00 KM | 4.13 | 36.12 | 2. | R/Wall, B/ Wall Type Protection works | 15000.00 m | 306.72 | 01-04-2015 | 14-09-2016 | 15000.00 m | 15000.00 m | 35.06 | 306.72 | 3. | GSB/RBI/G-1 | 2.00 KM | 14.25 | 15-05-2015 | 16-05-2016 | 2.00 KM | 2.00 KM | 1.63 | 14.25 | 4. | G-2 | 2.00 KM | 11.01 | 30-05-2015 | 28-06-2016 | 2.00 KM | 2.00 KM | 1.26 | 11.01 | 5. | G-3 | 5.00 KM | 28.34 | 15-07-2015 | 28-06-2016 | 5.00 KM | 5.00 KM | 3.24 | 28.34 | 6. | PC/CC i/c Prime Coat, Tack Coat | 1.50 KM | 14.99 | 01-03-2016 | 14-04-2016 | 1.50 KM | 1.50 KM | 1.71 | 14.99 | 7. | BM i/c Prime Coat, Tack Coat | 5.00 KM | 123.75 | 05-10-2015 | 28-06-2016 | 5.00 KM | 5.00 KM | 14.15 | 123.75 | 8. | SDBC i/c Tackcoat | 15.00 KM | 219.38 | 25-02-2016 | 12-10-2016 | 15.00 KM | 15.00 KM | 25.08 | 219.38 | 9. | Cause Way | 7.00 No | 28.03 | 10-10-2014 | 05-05-2016 | 7.00 No | 7.00 No | 3.2 | 28.03 | 10. | longitudinal Drain | 11900.00 m | 17.92 | 05-06-2015 | 12-10-2016 | 11900.00 m | 11900.00 m | 2.05 | 17.92 | 11. | Crash Barrier | 500.00 m | 10.82 | 01-04-2016 | 10-10-2016 | 500.00 m | 500.00 m | 1.24 | 10.82 | 12. | Road Furniture | 106.00 No | 8.53 | 01-09-2016 | 30-11-2016 | 106.00 No | 106.00 No | 0.98 | 8.53 | 13. | Other Allied Works & Finishing Work | 4.00 Job | 54.99 | 10-12-2016 | 27-12-2016 | 4.00 Job | 4.00 Job | 6.29 | 54.99 |
Total Amount: |
874.85 |
|
100 |
874.85 |
|
Remarks:
No Remarks
Work Program Made On:
26-06-2015 } ?>
Updation of work program on:
13-09-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 23-January-2015 | 6.67 lakh | 2. | 29-June-2015 | 16.87 lakh | 3. | 01-October-2015 | 102.66 lakh | 4. | 30-October-2015 | 55.68 lakh | 5. | 31-October-2015 | 0.00 lakh | 6. | 03-February-2016 | 57.87 lakh | 7. | 29-February-2016 | 14.84 lakh | 8. | 22-March-2016 | 13.27 lakh | 9. | 23-April-2016 | 74.71 lakh | 10. | 31-May-2016 | 168.03 lakh | 11. | 20-July-2016 | 32.22 lakh | 12. | 03-October-2016 | 167.07 lakh | 13. | 27-October-2016 | 65.21 lakh | 14. | 17-December-2016 | 25.57 lakh |
Total |
800.67 lakh |
% Payment |
91.51 % |
|
Advance Amount: 71.28 lakh
Recovered Amount: 71.28 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 949 No. of Test Done : 950 No. of Test Passed : 949 No. of Test Failed : 1 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.33 |
Number of Notice(s) issued: 76 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 6 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 25-02-2017 | Down side of ramadi vill./62.000 to 62.030 | Road studse, tharmoplast paint lining, deilenetor work done in kapkot shama tejam M/R pkg.C-26 | Jagdish Kumar Tamta | AAE | UEAP R&B Bageshwar | See Pic |
2. | 25-02-2017 | Near ramari/55.750 to 55.770 | Road studes, white washing and tharmoplast lining work done in Kapkot shama tejam M/R pkg.C-26 | Jagdish Kumar Tamta | AAE | UEAP R&B Bageshwar | See Pic |
3. | 05-09-2016 | 65.300-65.350near HP bend | Slip to night rain. | Jagdish Kumar Tamta | AAE | UEAP R&B Bageshwar | See Pic |
4. | 31-10-2015 | Vill. Ramadi/62.720-62.740 | Laying of top concrete in couseway in shama Tejam M./R pak. 26 | Jagdish Kumar Tamta | AAE | UEAP R&B Bageshwar | See Pic |
5. | 13-08-2015 | Ch 66.750 | Plum concrete near ramganga bridge | R C Pandey | AE | DEA WB Bageshwar | See Pic |
6. | 07-08-2015 | 66.00-66.100near ramana bridge | Foundation 0f R/W | Jagdish Kumar Tamta | AAE | UEAP R&B Bageshwar | See Pic |
|
|