Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bageshwar-Kapkot-Sama-Tejam Work Completed
Project: UEAP-RB UID: 5704 Sanction Cost: 1172.00  lakh Length: 35.000 KM.
District: Bageshwar Block: Kapkot Constituency: Kapkote Circle:
DEA: DEA UEAP Bageshwar DSC: DSC Scope: Design & Supervision Type: MDR
Procurement:
Package No.: 1029        Package Name:  UEAP/PWD/C26        Tender Date: 31-03-2014        Current Status: Agreement signed        Achieved on Date: 29-09-2014

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C26      Contractor Name: Bharat Construction
Start Date:  08-10-2014      Intended Completion Date:  07-04-2016     
Total Bond Cost: 71283437.6 (712.83 lakh)        Variation Cost: 16203407.47 (162.03 lakh)    Hence Total Bond Cost is   87486845.07 (874.87 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 6593770 for 185 days        LD Analysis for Milestone2: calculated LD is Rs 6486844 for +182 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence17.00 KM36.1201-12-201530-01-201617.00 KM17.00 KM4.1336.12
2.R/Wall, B/ Wall Type Protection works15000.00 m306.7201-04-201514-09-201615000.00 m15000.00 m35.06306.72
3.GSB/RBI/G-12.00 KM14.2515-05-201516-05-20162.00 KM2.00 KM1.6314.25
4.G-22.00 KM11.0130-05-201528-06-20162.00 KM2.00 KM1.2611.01
5.G-35.00 KM28.3415-07-201528-06-20165.00 KM5.00 KM3.2428.34
6.PC/CC i/c Prime Coat, Tack Coat1.50 KM14.9901-03-201614-04-20161.50 KM1.50 KM1.7114.99
7.BM i/c Prime Coat, Tack Coat5.00 KM123.7505-10-201528-06-20165.00 KM5.00 KM14.15123.75
8.SDBC i/c Tackcoat15.00 KM219.3825-02-201612-10-201615.00 KM15.00 KM25.08219.38
9.Cause Way7.00 No28.0310-10-201405-05-20167.00 No7.00 No3.228.03
10.longitudinal Drain11900.00 m17.9205-06-201512-10-201611900.00 m11900.00 m2.0517.92
11.Crash Barrier500.00 m10.8201-04-201610-10-2016500.00 m500.00 m1.2410.82
12.Road Furniture106.00 No8.5301-09-201630-11-2016106.00 No106.00 No0.988.53
13.Other Allied Works & Finishing Work 4.00 Job54.9910-12-201627-12-20164.00 Job4.00 Job6.2954.99
Total Amount: 874.85 100   874.85
Remarks: No Remarks       Work Program Made On: 26-06-2015        Updation of work program on: 13-09-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.23-January-20156.67  lakh
2.29-June-201516.87  lakh
3.01-October-2015102.66  lakh
4.30-October-201555.68  lakh
5.31-October-20150.00  lakh
6.03-February-201657.87  lakh
7.29-February-201614.84  lakh
8.22-March-201613.27  lakh
9.23-April-201674.71  lakh
10.31-May-2016168.03  lakh
11.20-July-201632.22  lakh
12.03-October-2016167.07  lakh
13.27-October-201665.21  lakh
14.17-December-201625.57  lakh
Total 800.67  lakh
% Payment 91.51 %
Advance Amount:  71.28  lakh        Recovered Amount:  71.28  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 949   No. of Test Done : 950    No. of Test Passed : 949   No. of Test Failed : 1   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.33
Number of Notice(s) issued: 76

Mobile Pic Upload

Number of Pics Available on Web Repository: 6
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.25-02-2017Down side of ramadi vill./62.000 to 62.030Road studse, tharmoplast paint lining, deilenetor work done in kapkot shama tejam M/R pkg.C-26Jagdish Kumar TamtaAAEUEAP R&B Bageshwar See Pic
2.25-02-2017Near ramari/55.750 to 55.770Road studes, white washing and tharmoplast lining work done in Kapkot shama tejam M/R pkg.C-26Jagdish Kumar TamtaAAEUEAP R&B Bageshwar See Pic
3.05-09-201665.300-65.350near HP bendSlip to night rain.Jagdish Kumar TamtaAAEUEAP R&B Bageshwar See Pic
4.31-10-2015Vill. Ramadi/62.720-62.740Laying of top concrete in couseway in shama Tejam M./R pak. 26Jagdish Kumar TamtaAAEUEAP R&B Bageshwar See Pic
5.13-08-2015Ch 66.750Plum concrete near ramganga bridgeR C PandeyAEDEA WB Bageshwar See Pic
6.07-08-201566.00-66.100near ramana bridgeFoundation 0f R/WJagdish Kumar TamtaAAEUEAP R&B Bageshwar See Pic