Internal Motor Road of Nagar Palika Tanakpur
Work Completed
|
Project: |
UEAP-RB |
UID: |
5611 |
Sanction Cost: |
380.00 lakh |
Length:
|
9.060 KM. |
District: |
Champawat |
Block: |
Champawat |
Constituency: |
Champawat |
Circle: |
|
DEA: |
DEA UEAP Nainital |
DSC: |
CCEE Group India Pvt.Ltd |
DSC Scope: |
Design and Supervision |
Type: |
Urban |
|
Procurement: |
Package No.: 1081
Package Name: 
UEAP/PWD/C-77
Tender Date: 14-08-2015
Current Status: Agreement signed
Achieved on Date: 25-02-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C-77
Contractor Name: Kumar Infratech
|
Start Date: 16-03-2016
Intended Completion Date: 15-12-2016
|
Total Bond Cost: 32320115 (323.2 lakh)
Variation Cost: 5679810.25 (56.8 lakh) Hence Total Bond Cost is 37999925.25 (380 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 339360 for 21 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | GSB/RBI/G-1 | 3.90 KM | 0.59 | 08-09-2016 | 15-09-2016 | 3.90 KM | 3.90 KM | 0.23 | 0.59 | 2. | G-2 | 3.90 KM | 4.68 | 16-09-2016 | 20-09-2016 | 3.90 KM | 3.90 KM | 1.83 | 4.68 | 3. | G-3 | 3.90 KM | 6.70 | 21-09-2016 | 26-09-2016 | 3.90 KM | 3.90 KM | 2.61 | 6.70 | 4. | BM i/c Prime Coat, Tack Coat | 4.06 KM | 56.92 | 01-04-2016 | 20-10-2016 | 4.06 KM | 4.06 KM | 22.2 | 56.92 | 5. | SDBC i/c Tackcoat | 9.11 KM | 187.47 | 10-04-2016 | 20-10-2016 | 9.11 KM | 9.11 KM | 73.13 | 187.47 |
Total Amount: |
256.36 |
|
100 |
256.36 |
|
Remarks:
No Remarks
Work Program Made On:
25-07-2016 } ?>
Updation of work program on:
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-May-2016 | 69.15 lakh | 2. | 30-September-2016 | 76.30 lakh | 3. | 28-November-2016 | 162.41 lakh | 4. | 24-March-2017 | 46.06 lakh | 5. | 19-June-2017 | 18.64 lakh | 6. | 26-September-2017 | 2.47 lakh |
Total |
375.03 lakh |
% Payment |
98.7 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 376 No. of Test Done : 379 No. of Test Passed : 372 No. of Test Failed : 4 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.89 |
Number of Notice(s) issued: 33 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 12 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 07-02-2017 | Chainage 2.050 | chore cutting checking by NH Chief Engineer Haldwani Kumaon zone in Tanakpur Verma lene to Shailanigot motor road | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
2. | 07-02-2017 | Internal road inside rest house | Inside rest house | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
3. | 02-11-2016 | Sharda chungi | SDBC surface | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
4. | 02-11-2016 | Near Bus Station Tanakpur | Joint Inspection of Site with SDM Tanakpur | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
5. | 02-11-2016 | Near Bus station | Cleaning of Existing Surface before laying of SDBC , SE sir visit | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
6. | 02-11-2016 | Internal Road of Tanakpur | SDBC work | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
7. | 02-11-2016 | At Plant | SDBC production | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
8. | 19-05-2016 | Bus Station Tanakpur | Resolving site issues with local residents along with SDM Tanakpur | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
9. | 19-05-2016 | Internal road of Tanakpur Nagar palika near Bush Station after removing encroachment by Administration | Internal roads of Tanakpur construction is on near Bus Station | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
10. | 04-03-2016 | K.M. 58 of New NH- 09 | HMP established for internal road Tankpur nagarpalika | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
11. | 04-03-2016 | HMP site at New N H 09 Km 58 | HMP ready will start from 12th March | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
12. | 04-03-2016 | Plant Site for C 77 | HMP is ready for C 77 package likely to start from 12th march | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
|
|