Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Internal Motor Road of Nagar Palika Tanakpur Work Completed
Project: UEAP-RB UID: 5611 Sanction Cost: 380.00  lakh Length: 9.060 KM.
District: Champawat Block: Champawat Constituency: Champawat Circle:
DEA: DEA UEAP Nainital DSC: CCEE Group India Pvt.Ltd DSC Scope: Design and Supervision Type: Urban
Procurement:
Package No.: 1081        Package Name:  UEAP/PWD/C-77        Tender Date: 14-08-2015        Current Status: Agreement signed        Achieved on Date: 25-02-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C-77      Contractor Name: Kumar Infratech
Start Date:  16-03-2016      Intended Completion Date:  15-12-2016     
Total Bond Cost: 32320115 (323.2 lakh)        Variation Cost: 5679810.25 (56.8 lakh)    Hence Total Bond Cost is   37999925.25 (380 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 339360 for 21 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.GSB/RBI/G-13.90 KM0.5908-09-201615-09-20163.90 KM3.90 KM0.230.59
2.G-23.90 KM4.6816-09-201620-09-20163.90 KM3.90 KM1.834.68
3.G-33.90 KM6.7021-09-201626-09-20163.90 KM3.90 KM2.616.70
4.BM i/c Prime Coat, Tack Coat4.06 KM56.9201-04-201620-10-20164.06 KM4.06 KM22.256.92
5.SDBC i/c Tackcoat9.11 KM187.4710-04-201620-10-20169.11 KM9.11 KM73.13187.47
Total Amount: 256.36 100   256.36
Remarks: No Remarks       Work Program Made On: 25-07-2016        Updation of work program on:       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-May-201669.15  lakh
2.30-September-201676.30  lakh
3.28-November-2016162.41  lakh
4.24-March-201746.06  lakh
5.19-June-201718.64  lakh
6.26-September-20172.47  lakh
Total 375.03  lakh
% Payment 98.7 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 376   No. of Test Done : 379    No. of Test Passed : 372   No. of Test Failed : 4   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.89
Number of Notice(s) issued: 33

Mobile Pic Upload

Number of Pics Available on Web Repository: 12
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.07-02-2017Chainage 2.050chore cutting checking by NH Chief Engineer Haldwani Kumaon zone in Tanakpur Verma lene to Shailanigot motor roadRajiv GururaniEEUEAP R&B Nainital See Pic
2.07-02-2017Internal road inside rest houseInside rest houseRajiv GururaniEEUEAP R&B Nainital See Pic
3.02-11-2016Sharda chungiSDBC surfaceLalit TiwariAEDEA ADB Nainital See Pic
4.02-11-2016Near Bus Station TanakpurJoint Inspection of Site with SDM TanakpurLalit TiwariAEDEA ADB Nainital See Pic
5.02-11-2016Near Bus stationCleaning of Existing Surface before laying of SDBC , SE sir visitLalit TiwariAEDEA ADB Nainital See Pic
6.02-11-2016Internal Road of TanakpurSDBC workLalit TiwariAEDEA ADB Nainital See Pic
7.02-11-2016At PlantSDBC productionLalit TiwariAEDEA ADB Nainital See Pic
8.19-05-2016Bus Station TanakpurResolving site issues with local residents along with SDM TanakpurRajiv GururaniEEUEAP R&B Nainital See Pic
9.19-05-2016Internal road of Tanakpur Nagar palika near Bush Station after removing encroachment by AdministrationInternal roads of Tanakpur construction is on near Bus StationRajiv GururaniEEUEAP R&B Nainital See Pic
10.04-03-2016K.M. 58 of New NH- 09HMP established for internal road Tankpur nagarpalikaLalit TiwariAEDEA ADB Nainital See Pic
11.04-03-2016HMP site at New N H 09 Km 58HMP ready will start from 12th MarchRajiv GururaniEEUEAP R&B Nainital See Pic
12.04-03-2016Plant Site for C 77HMP is ready for C 77 package likely to start from 12th marchRajiv GururaniEEUEAP R&B Nainital See Pic