Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Seraghat-Udiyaribend Agreement signed
Project: UEAP-RB UID: 5606 Sanction Cost: 113.00  lakh Length: 42.000 KM.
District: Pithoragarh Block: Gangolihat Constituency: Gangolihat Circle:
DEA: DEA UEAP Pithoragarh DSC: Royal Haskoning DHV DSC Scope: Design & Supervision Type: Not known
Procurement:
Package No.: 1049        Package Name:  UEAP/PWD/C46        Tender Date: 03-05-2014        Current Status: Agreement signed        Achieved on Date: 10-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C46      Contractor Name: Zender Engineers Ltd
Start Date:  11-12-2014      Intended Completion Date:  30-11-2015     
Total Bond Cost: 8132474 (81.32 lakh)        Variation Cost: 3027216.61 (30.27 lakh)    Hence Total Bond Cost is   11159690.61 (111.6 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
100200285.5370.5370.5
SNo. Progress Name Target Quantity Achieved Quantity Progress(in %)
1.Cause Way1.00 No1.00 No100.00
2.Culverts/Scupper 2.00 No2.00 No100.00
3.R/Wall, B/ Wall Type Protection works200.00 m171.00 m85.50
4.Hill side Cutting & Slip clearence0.20 KM0.17 KM85.00
5.G-30.35 KM0.00 KM0.00
Total Progress: 74.1  
Remarks: No Remarks       Work Program Made On:        Updation of work program on:       
Work Program Status:Work Program Not Made Yet
Financial Progress
SNo. Date Payment
1.11-February-201546.28  lakh
2.27-June-201530.87  lakh
3.14-October-20173.52  lakh
Total 80.67  lakh
% Payment 72.28 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill should be issued( Work program not made hence analysis may not be realistic).
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): workmen Insurance
Environment & Social Compliances(Sub Project level): No Pending Issue
Detailed report of this subproject
Quality
No. of Test Required : 26   No. of Test Done : 26    No. of Test Passed : 25   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 91.67
Number of Notice(s) issued: 68

Mobile Pic Upload

Number of Pics Available on Web Repository: 4
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.06-11-20154Pkg c-46km75 culvert&R/w constructedCulvert & R /W B/W constructedGulab RamSEADB Circle See Pic
2.06-04-2015B/w constructed in km88hm0-2SeraghatUdyaribend m/rGulab RamSEADB Circle See Pic
3.22-03-2015Ch 70.05 protaction of causeway d/s sideProtection work causewaySatyendra sharmaCE PitharogarhPWD See Pic
4.22-03-2015Ch 88.200Protection work wall of plumb concereteSatyendra sharmaCE PitharogarhPWD See Pic