Seraghat-Udiyaribend
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5606 |
Sanction Cost: |
113.00 lakh |
Length:
|
42.000 KM. |
District: |
Pithoragarh |
Block: |
Gangolihat |
Constituency: |
Gangolihat |
Circle: |
|
DEA: |
DEA UEAP Pithoragarh |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
Design & Supervision |
Type: |
Not known |
|
Procurement: |
Package No.: 1049
Package Name: 
UEAP/PWD/C46
Tender Date: 03-05-2014
Current Status: Agreement signed
Achieved on Date: 10-11-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C46
Contractor Name: Zender Engineers Ltd
|
Start Date: 11-12-2014
Intended Completion Date: 30-11-2015
|
Total Bond Cost: 8132474 (81.32 lakh)
Variation Cost: 3027216.61 (30.27 lakh) Hence Total Bond Cost is 11159690.61 (111.6 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
Target Quantity |
Achieved Quantity |
Progress(in %) |
1001. | Cause Way | 1.00 No | 1.00 No | 100.00 | 2002. | Culverts/Scupper | 2.00 No | 2.00 No | 100.00 | 285.53. | R/Wall, B/ Wall Type Protection works | 200.00 m | 171.00 m | 85.50 | 370.54. | Hill side Cutting & Slip clearence | 0.20 KM | 0.17 KM | 85.00 | 370.55. | G-3 | 0.35 KM | 0.00 KM | 0.00 |
Total Progress: |
74.1 |
|
Remarks:
No Remarks
Work Program Made On:
} ?>
Updation of work program on:
|
|
Work Program Status:Work Program Not Made Yet |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 11-February-2015 | 46.28 lakh | 2. | 27-June-2015 | 30.87 lakh | 3. | 14-October-2017 | 3.52 lakh |
Total |
80.67 lakh |
% Payment |
72.28 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill should be issued( Work program not made hence analysis may not be realistic). | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
workmen Insurance
Environment & Social Compliances(Sub Project level):
No Pending Issue |
Detailed report of this subproject
|
|
Quality
|
No. of Test Required : 26 No. of Test Done : 26 No. of Test Passed : 25 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 91.67 |
Number of Notice(s) issued: 68 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 4 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 06-11-2015 | 4Pkg c-46km75 culvert&R/w constructed | Culvert & R /W B/W constructed | Gulab Ram | SE | ADB Circle | See Pic |
2. | 06-04-2015 | B/w constructed in km88hm0-2 | SeraghatUdyaribend m/r | Gulab Ram | SE | ADB Circle | See Pic |
3. | 22-03-2015 | Ch 70.05 protaction of causeway d/s side | Protection work causeway | Satyendra sharma | CE Pitharogarh | PWD | See Pic |
4. | 22-03-2015 | Ch 88.200 | Protection work wall of plumb concerete | Satyendra sharma | CE Pitharogarh | PWD | See Pic |
|
|