Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Reconstruction of Internal Roads of Nagarpanchayat Berinag Work Completed
Project: UEAP-RB UID: 5605 Sanction Cost: 325.00  lakh Length: 7.820 KM.
District: Pithoragarh Block: Berinag Constituency: Gangolihat Circle:
DEA: DEA UEAP Pithoragarh DSC: DSC Scope: Design & Supervision Type: Urban
Procurement:
Package No.: 1031        Package Name:  UEAP/PWD/C28        Tender Date: 28-03-2014        Current Status: Agreement signed        Achieved on Date: 15-08-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C28      Contractor Name: Rami Construction
Start Date:  17-09-2014      Intended Completion Date:  16-12-2015     
Total Bond Cost: 30780038.5 (307.8 lakh)        Variation Cost: -2900892.46 (-29.01 lakh)    Hence Total Bond Cost is   27879146.04 (278.79 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 2323890 for +151 days        LD Analysis for Milestone2: calculated LD is Rs 2339280 for +152 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.10 KM0.2625-05-201620-06-20160.10 KM0.10 KM0.080.26
2.G-30.56 KM2.4410-04-201631-05-20160.56 KM0.56 KM0.772.44
3.PC/CC i/c Prime Coat, Tack Coat7.82 KM12.5501-05-201630-06-20167.82 KM7.82 KM3.9712.55
4.BM i/c Prime Coat, Tack Coat2.82 KM92.9101-05-201625-06-20162.77 KM2.77 KM29.4192.91
5.SDBC i/c Tackcoat7.82 KM133.4715-05-201630-06-20167.77 KM7.77 KM42.25133.47
6.longitudinal Drain5180.00 m37.2312-10-201530-10-20165180.00 m5180.00 m11.7937.23
7.Crash Barrier780.00 m19.5001-05-201625-06-2016780.00 m780.00 m6.1719.50
8.Parapet100.00 No2.2005-02-201630-06-2016100.00 No100.00 No0.72.20
9.Road Furniture55.00 No15.3501-09-201630-10-201655.00 No55.00 No4.8615.35
10.Other Allied Works & Finishing Work 0.00 Job0.0001-09-201601-09-20161.00 Job1.00 Job00.00
Total Amount: 315.91 100   315.91
Remarks: No Remarks       Work Program Made On: 12-09-2016        Updation of work program on: 17-10-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.26-May-201511.83  lakh
2.28-November-201513.76  lakh
3.26-December-201519.30  lakh
4.25-January-20166.93  lakh
5.19-March-20160.76  lakh
6.24-May-201666.41  lakh
7.22-June-2016133.40  lakh
8.27-October-20166.30  lakh
9.12-October-201719.44  lakh
Total 278.13  lakh
% Payment 99.76 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 249   No. of Test Done : 249    No. of Test Passed : 226   No. of Test Failed : 0    No. of Test Result Awaited : 13     Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 88.27
Number of Notice(s) issued: 68

Mobile Pic Upload

Number of Pics Available on Web Repository: 28
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-11-2016Gic roadSdbc temperature in paver hoper... 125 cShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
2.07-11-2016Didihaat plantBitumin content test in plantShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
3.01-09-2016Ch 800 to 900Pg collage road ... thermoplast bandShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
4.20-06-20162890Sdbc rollingShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
5.14-06-20160+4950Sdbc rolling continue in berinag ti askot roadShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
6.02-06-2016170 to 190Sdbc rolling in vbpm road.Shankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
7.01-06-2016450 to 480Sdbc work in progressShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
8.26-05-2016BVPM roadCREDA camp for labour of berinagShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
9.26-05-2016970 to 990Sdbc rolling continue in BVPM roadShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
10.17-05-2016Hospital road Ch 50BM work in progressShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
11.15-05-2016Berinag plantPlant at sakunkande village.. Sdbc materialShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
12.15-05-20160 to 80Sdbc rolling continueShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
13.14-05-2016720Sdbc work in progressShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
14.12-05-2016Ch 370 PG collageBm work continueShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
15.12-05-2016Ch 370 PG collageRolling work in bmShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
16.12-05-2016PG collage road Ch 0-270Road clearing for bmShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
17.04-05-2016PG collage roadRoad clearing for BMShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
18.01-04-2016Berinag to thal marg 300 meter ahead from petrol pumpParapet workShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
19.01-04-2016Berinag to askot margParapet work in progressShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
20.16-03-2016Near petrol pump .. Berinag to thal roadDrain work in progressShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic