Reconstruction of Internal Roads of Nagarpanchayat Berinag
Work Completed
|
Project: |
UEAP-RB |
UID: |
5605 |
Sanction Cost: |
325.00 lakh |
Length:
|
7.820 KM. |
District: |
Pithoragarh |
Block: |
Berinag |
Constituency: |
Gangolihat |
Circle: |
|
DEA: |
DEA UEAP Pithoragarh |
DSC: |
|
DSC Scope: |
Design & Supervision |
Type: |
Urban |
|
Procurement: |
Package No.: 1031
Package Name: 
UEAP/PWD/C28
Tender Date: 28-03-2014
Current Status: Agreement signed
Achieved on Date: 15-08-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C28
Contractor Name: Rami Construction
|
Start Date: 17-09-2014
Intended Completion Date: 16-12-2015
|
Total Bond Cost: 30780038.5 (307.8 lakh)
Variation Cost: -2900892.46 (-29.01 lakh) Hence Total Bond Cost is 27879146.04 (278.79 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 2323890 for +151 days
LD Analysis for Milestone2: calculated LD is Rs 2339280 for +152 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.10 KM | 0.26 | 25-05-2016 | 20-06-2016 | 0.10 KM | 0.10 KM | 0.08 | 0.26 | 2. | G-3 | 0.56 KM | 2.44 | 10-04-2016 | 31-05-2016 | 0.56 KM | 0.56 KM | 0.77 | 2.44 | 3. | PC/CC i/c Prime Coat, Tack Coat | 7.82 KM | 12.55 | 01-05-2016 | 30-06-2016 | 7.82 KM | 7.82 KM | 3.97 | 12.55 | 4. | BM i/c Prime Coat, Tack Coat | 2.82 KM | 92.91 | 01-05-2016 | 25-06-2016 | 2.77 KM | 2.77 KM | 29.41 | 92.91 | 5. | SDBC i/c Tackcoat | 7.82 KM | 133.47 | 15-05-2016 | 30-06-2016 | 7.77 KM | 7.77 KM | 42.25 | 133.47 | 6. | longitudinal Drain | 5180.00 m | 37.23 | 12-10-2015 | 30-10-2016 | 5180.00 m | 5180.00 m | 11.79 | 37.23 | 7. | Crash Barrier | 780.00 m | 19.50 | 01-05-2016 | 25-06-2016 | 780.00 m | 780.00 m | 6.17 | 19.50 | 8. | Parapet | 100.00 No | 2.20 | 05-02-2016 | 30-06-2016 | 100.00 No | 100.00 No | 0.7 | 2.20 | 9. | Road Furniture | 55.00 No | 15.35 | 01-09-2016 | 30-10-2016 | 55.00 No | 55.00 No | 4.86 | 15.35 | 10. | Other Allied Works & Finishing Work | 0.00 Job | 0.00 | 01-09-2016 | 01-09-2016 | 1.00 Job | 1.00 Job | 0 | 0.00 |
Total Amount: |
315.91 |
|
100 |
315.91 |
|
Remarks:
No Remarks
Work Program Made On:
12-09-2016 } ?>
Updation of work program on:
17-10-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-May-2015 | 11.83 lakh | 2. | 28-November-2015 | 13.76 lakh | 3. | 26-December-2015 | 19.30 lakh | 4. | 25-January-2016 | 6.93 lakh | 5. | 19-March-2016 | 0.76 lakh | 6. | 24-May-2016 | 66.41 lakh | 7. | 22-June-2016 | 133.40 lakh | 8. | 27-October-2016 | 6.30 lakh | 9. | 12-October-2017 | 19.44 lakh |
Total |
278.13 lakh |
% Payment |
99.76 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 249 No. of Test Done : 249 No. of Test Passed : 226 No. of Test Failed : 0
No. of Test Result Awaited : 13
Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.27 |
Number of Notice(s) issued: 68 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 28 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 08-11-2016 | Gic road | Sdbc temperature in paver hoper... 125 c | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
2. | 07-11-2016 | Didihaat plant | Bitumin content test in plant | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
3. | 01-09-2016 | Ch 800 to 900 | Pg collage road ... thermoplast band | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
4. | 20-06-2016 | 2890 | Sdbc rolling | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
5. | 14-06-2016 | 0+4950 | Sdbc rolling continue in berinag ti askot road | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
6. | 02-06-2016 | 170 to 190 | Sdbc rolling in vbpm road. | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
7. | 01-06-2016 | 450 to 480 | Sdbc work in progress | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
8. | 26-05-2016 | BVPM road | CREDA camp for labour of berinag | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
9. | 26-05-2016 | 970 to 990 | Sdbc rolling continue in BVPM road | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
10. | 17-05-2016 | Hospital road Ch 50 | BM work in progress | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
11. | 15-05-2016 | Berinag plant | Plant at sakunkande village.. Sdbc material | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
12. | 15-05-2016 | 0 to 80 | Sdbc rolling continue | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
13. | 14-05-2016 | 720 | Sdbc work in progress | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
14. | 12-05-2016 | Ch 370 PG collage | Bm work continue | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
15. | 12-05-2016 | Ch 370 PG collage | Rolling work in bm | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
16. | 12-05-2016 | PG collage road Ch 0-270 | Road clearing for bm | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
17. | 04-05-2016 | PG collage road | Road clearing for BM | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
18. | 01-04-2016 | Berinag to thal marg 300 meter ahead from petrol pump | Parapet work | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
19. | 01-04-2016 | Berinag to askot marg | Parapet work in progress | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
20. | 16-03-2016 | Near petrol pump .. Berinag to thal road | Drain work in progress | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
|
|