Reconstruction of internal road of Nagar Panchayat Didihaat
Work Completed
|
Project: |
UEAP-RB |
UID: |
5604 |
Sanction Cost: |
752.00 lakh |
Length:
|
8.360 KM. |
District: |
Pithoragarh |
Block: |
Didihat |
Constituency: |
Didihat |
Circle: |
|
DEA: |
DEA UEAP Pithoragarh |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design & Supervision |
Type: |
Urban |
|
Procurement: |
Package No.: 1017
Package Name: 
UEAP/PWD/C15
Tender Date: 03-03-2014
Current Status: Agreement signed
Achieved on Date: 10-07-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C15
Contractor Name: Rami Construction
|
Start Date: 04-08-2014
Intended Completion Date: 03-02-2016
|
Total Bond Cost: 63124966.55 (631.25 lakh)
Variation Cost: -14834438.78 (-148.34 lakh) Hence Total Bond Cost is 48290527.77 (482.91 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 6438648 for 204 days
LD Analysis for Milestone2: calculated LD is Rs 2745894 for 87 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | GSB/RBI/G-1 | 1.00 KM | 6.41 | 01-09-2016 | 04-10-2016 | 1.00 KM | 1.00 KM | 0.98 | 6.41 | 2. | G-2 | 1.48 KM | 8.05 | 01-09-2016 | 14-10-2016 | 1.48 KM | 1.48 KM | 1.23 | 8.05 | 3. | G-3 | 8.36 KM | 43.97 | 01-09-2016 | 21-10-2016 | 8.36 KM | 8.36 KM | 6.7 | 43.97 | 4. | PC/CC i/c Prime Coat, Tack Coat | 8.36 KM | 32.76 | 01-09-2016 | 30-10-2016 | 8.36 KM | 8.36 KM | 4.99 | 32.76 | 5. | BM i/c Prime Coat, Tack Coat | 8.36 KM | 257.70 | 01-09-2016 | 28-11-2016 | 8.36 KM | 8.36 KM | 39.25 | 257.70 | 6. | SDBC i/c Tackcoat | 8.36 KM | 174.15 | 01-09-2016 | 03-12-2016 | 8.36 KM | 8.36 KM | 26.53 | 174.15 | 7. | Culverts/Scupper | 20.00 No | 3.39 | 04-05-2015 | 15-12-2016 | 1.00 No | 1.00 No | 0.52 | 3.39 | 8. | longitudinal Drain | 5340.00 m | 5.18 | 20-09-2016 | 25-11-2016 | 5340.00 m | 5340.00 m | 0.79 | 5.18 | 9. | Crash Barrier | 3700.00 m | 107.30 | 01-09-2016 | 05-12-2016 | 3200.00 m | 3200.00 m | 16.35 | 107.30 | 10. | Parapet | 61.00 No | 1.40 | 04-05-2015 | 30-05-2015 | 61.00 No | 61.00 No | 0.21 | 1.40 | 11. | Road Furniture | 60.00 No | 1.64 | 01-09-2016 | 18-12-2016 | 60.00 No | 60.00 No | 0.25 | 1.64 | 12. | Other Allied Works & Finishing Work | 2.00 Job | 14.53 | 15-11-2016 | 18-12-2016 | 2.00 Job | 2.00 Job | 2.21 | 14.53 |
Total Amount: |
656.48 |
|
100 |
656.48 |
|
Remarks:
subproject completed on 31 dec 2016
Work Program Made On:
12-09-2016 } ?>
Updation of work program on:
22-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-May-2015 | 6.99 lakh | 2. | 20-June-2015 | 32.74 lakh | 3. | 29-June-2015 | 36.07 lakh | 4. | 26-August-2015 | 50.54 lakh | 5. | 20-October-2015 | 123.24 lakh | 6. | 31-October-2015 | 71.34 lakh | 7. | 28-November-2015 | 40.63 lakh | 8. | 18-March-2016 | 2.91 lakh | 9. | 25-April-2016 | 31.62 lakh | 10. | 28-February-2017 | 42.47 lakh | 11. | 12-October-2017 | 41.84 lakh |
Total |
480.39 lakh |
% Payment |
99.47 % |
|
Advance Amount: 81.13 lakh
Recovered Amount: 81.13 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 104 No. of Test Done : 104 No. of Test Passed : 96 No. of Test Failed : 0
No. of Test Result Awaited : 3
Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 86.51 |
Number of Notice(s) issued: 68 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 45 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 28-03-2017 | Munsiyari helipad | Cube casting for DLC work in progress | Ankit Nakoti | AE | UEAP- CA | See Pic |
2. | 28-03-2017 | Munisiyari helipad | Cross Checking of level given for Dlc work in presence of dsc fe and by JE FPIU | Ankit Nakoti | AE | UEAP- CA | See Pic |
3. | 11-01-2017 | Jal sasthan road | Sdbc rolling | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
4. | 11-01-2017 | Jal sansthan road | Sdbc laying | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
5. | 27-11-2016 | Jalsasthan road | GM laying | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
6. | 15-11-2016 | Gic road ch820 | Sdbc rolling | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
7. | 08-11-2016 | Gic road sdbc | Sdbc rolling | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
8. | 07-11-2016 | Gic road... | Sdbc rolling continue | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
9. | 07-11-2016 | Police station | Sdbc rolling | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
10. | 07-11-2016 | Police station sdbc | Sdbc rolling | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
11. | 07-11-2016 | Dunakot road ch 1540 | Sdbc rolling | Uday Ram | AE | UEAP R&B Pithoragarh | See Pic |
12. | 07-11-2016 | Plant | Bitumin content test | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
13. | 06-11-2016 | Dunakot road | Sdbc rolling continue | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
14. | 06-11-2016 | Dunakot road | Sdbc rolling | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
15. | 05-11-2016 | Gic road | Be surface not leveled due to labour hand laying | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
16. | 27-10-2016 | Dunakot road ch1900 | Measurement of Bm with AE sir | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
17. | 27-10-2016 | Dunakot Bm ch 990- 1000 | Bm work | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
18. | 27-10-2016 | Dunakot road ch 1010 to1020 | Bm work in progress | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
19. | 27-10-2016 | Dunakot road ch 1000 to 1100 | Bm rolling | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
20. | 24-10-2016 | Gic road ch 820 | Bm work in progress... less amount of dry material laying on 1 square meter area | Shankar Trivedi | JE | UEAP R&B and CA Pithoragarh | See Pic |
|
|