Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Reconstruction of internal road of Nagar Panchayat Didihaat Work Completed
Project: UEAP-RB UID: 5604 Sanction Cost: 752.00  lakh Length: 8.360 KM.
District: Pithoragarh Block: Didihat Constituency: Didihat Circle:
DEA: DEA UEAP Pithoragarh DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design & Supervision Type: Urban
Procurement:
Package No.: 1017        Package Name:  UEAP/PWD/C15        Tender Date: 03-03-2014        Current Status: Agreement signed        Achieved on Date: 10-07-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C15      Contractor Name: Rami Construction
Start Date:  04-08-2014      Intended Completion Date:  03-02-2016     
Total Bond Cost: 63124966.55 (631.25 lakh)        Variation Cost: -14834438.78 (-148.34 lakh)    Hence Total Bond Cost is   48290527.77 (482.91 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 6438648 for 204 days        LD Analysis for Milestone2: calculated LD is Rs 2745894 for 87 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.GSB/RBI/G-11.00 KM6.4101-09-201604-10-20161.00 KM1.00 KM0.986.41
2.G-21.48 KM8.0501-09-201614-10-20161.48 KM1.48 KM1.238.05
3.G-38.36 KM43.9701-09-201621-10-20168.36 KM8.36 KM6.743.97
4.PC/CC i/c Prime Coat, Tack Coat8.36 KM32.7601-09-201630-10-20168.36 KM8.36 KM4.9932.76
5.BM i/c Prime Coat, Tack Coat8.36 KM257.7001-09-201628-11-20168.36 KM8.36 KM39.25257.70
6.SDBC i/c Tackcoat8.36 KM174.1501-09-201603-12-20168.36 KM8.36 KM26.53174.15
7.Culverts/Scupper 20.00 No3.3904-05-201515-12-20161.00 No1.00 No0.523.39
8.longitudinal Drain5340.00 m5.1820-09-201625-11-20165340.00 m5340.00 m0.795.18
9.Crash Barrier3700.00 m107.3001-09-201605-12-20163200.00 m3200.00 m16.35107.30
10.Parapet61.00 No1.4004-05-201530-05-201561.00 No61.00 No0.211.40
11.Road Furniture60.00 No1.6401-09-201618-12-201660.00 No60.00 No0.251.64
12.Other Allied Works & Finishing Work 2.00 Job14.5315-11-201618-12-20162.00 Job2.00 Job2.2114.53
Total Amount: 656.48 100   656.48
Remarks: subproject completed on 31 dec 2016       Work Program Made On: 12-09-2016        Updation of work program on: 22-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.26-May-20156.99  lakh
2.20-June-201532.74  lakh
3.29-June-201536.07  lakh
4.26-August-201550.54  lakh
5.20-October-2015123.24  lakh
6.31-October-201571.34  lakh
7.28-November-201540.63  lakh
8.18-March-20162.91  lakh
9.25-April-201631.62  lakh
10.28-February-201742.47  lakh
11.12-October-201741.84  lakh
Total 480.39  lakh
% Payment 99.47 %
Advance Amount:  81.13  lakh        Recovered Amount:  81.13  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 104   No. of Test Done : 104    No. of Test Passed : 96   No. of Test Failed : 0    No. of Test Result Awaited : 3     Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 86.51
Number of Notice(s) issued: 68

Mobile Pic Upload

Number of Pics Available on Web Repository: 45
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.28-03-2017Munsiyari helipadCube casting for DLC work in progressAnkit NakotiAEUEAP- CA See Pic
2.28-03-2017Munisiyari helipadCross Checking of level given for Dlc work in presence of dsc fe and by JE FPIUAnkit NakotiAEUEAP- CA See Pic
3.11-01-2017Jal sasthan roadSdbc rollingShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
4.11-01-2017Jal sansthan roadSdbc layingShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
5.27-11-2016Jalsasthan roadGM layingShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
6.15-11-2016Gic road ch820Sdbc rollingShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
7.08-11-2016Gic road sdbcSdbc rollingShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
8.07-11-2016Gic road...Sdbc rolling continueShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
9.07-11-2016Police stationSdbc rollingShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
10.07-11-2016Police station sdbcSdbc rollingShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
11.07-11-2016Dunakot road ch 1540Sdbc rollingUday RamAEUEAP R&B Pithoragarh See Pic
12.07-11-2016PlantBitumin content testShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
13.06-11-2016Dunakot roadSdbc rolling continueShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
14.06-11-2016Dunakot roadSdbc rollingShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
15.05-11-2016Gic roadBe surface not leveled due to labour hand layingShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
16.27-10-2016Dunakot road ch1900Measurement of Bm with AE sirShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
17.27-10-2016Dunakot Bm ch 990- 1000Bm workShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
18.27-10-2016Dunakot road ch 1010 to1020Bm work in progressShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
19.27-10-2016Dunakot road ch 1000 to 1100Bm rollingShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
20.24-10-2016Gic road ch 820Bm work in progress... less amount of dry material laying on 1 square meter areaShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic