Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Internal Motor Road of Nagar Palika Parishad Srinagar Agreement signed
Project: UEAP-RB UID: 5514 Sanction Cost: 740.00  lakh Length: 12.000 KM.
District: Pauri Block: Khirsu Constituency: Srinagar Circle:
DEA: DEA UEAP Pauri DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design and Supervision Type: Urban
Procurement:
Package No.: 1085        Package Name:  UEAP/PWD/C-81        Tender Date: 14-08-2015        Current Status: Agreement signed        Achieved on Date: 17-12-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C-81      Contractor Name: N P Buildwell Pvt. Ltd
Start Date:  30-12-2015      Intended Completion Date:  08-08-2017      Original End Date:  29-03-2017
Total Bond Cost: 66277367.5 (662.77 lakh)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 1391838 for 42 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence2.10 KM9.2231-12-201522-01-20172.10 KM0.00 KM00.00
2.R/Wall, B/ Wall Type Protection works426.00 m78.8025-01-201623-03-2017482.00 m417.00 m10.2766.73
3.GSB/RBI/G-11.06 KM7.3915-01-201615-06-20160.90 KM0.76 KM0.946.24
4.G-21.03 KM5.4115-01-201625-06-20160.90 KM0.76 KM0.694.57
5.G-31.44 KM7.7908-05-201630-06-20161.30 KM0.96 KM0.875.76
6.PC/CC i/c Prime Coat, Tack Coat1.73 KM22.6001-06-201623-03-20171.73 KM0.00 KM00.00
7.BM i/c Prime Coat, Tack Coat2.80 KM50.1001-04-201623-03-20175.53 KM2.01 KM2.7413.07
8.SDBC i/c Tackcoat7.35 KM162.1203-04-201623-03-20177.35 KM4.34 KM14.4395.73
9.Cause Way1.00 No7.6501-07-201615-03-20171.00 No0.00 No00.00
10.Culverts/Scupper 4.00 No286.5101-03-201630-11-20164.00 No0.00 No00.00
11.longitudinal Drain3800.00 m10.9410-03-201623-03-20171000.00 m790.00 m1.38.64
12.Crash Barrier200.00 m5.4010-09-201623-03-2017200.00 m0.00 m00.00
13.Road Furniture229.00 No4.8301-06-201623-03-2017234.00 No103.00 No0.320.96
14.Other Allied Works & Finishing Work 1.00 Job4.8301-09-201620-03-20171.00 Job0.00 Job00.00
Total Amount: 663.59 31.56   201.7
Remarks: No Remarks       Work Program Made On: 12-09-2016        Updation of work program on: 28-06-2017       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.12-December-2016334.51  lakh
2.28-February-201725.49  lakh
3.18-April-201713.67  lakh
4.31-May-201730.46  lakh
5.19-June-201732.40  lakh
6.11-August-201714.66  lakh
7.16-October-201710.93  lakh
Total 462.12  lakh
% Payment 69.73 %
Advance Amount:  11.70  lakh        Recovered Amount:  23.40  lakh        Balance to be Recovered  -11.70  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): Staff not deputed yet
Environment & Social Compliances(Sub Project level): No Pending Issue
Detailed report of this subproject
Quality
Test Information not Available.
Quality Ranking in %: 85.11
Number of Notice(s) issued: 55

Mobile Pic Upload

Number of Pics Available on Web Repository: 12
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.18-04-2017Gola bazar to Dr. Nethani resi Ch 0.430Core thickness checkingAlok JainAEUEAP R&B and CA Pauri See Pic
2.15-03-2017Gola bazar to Dr. Nethani resi roadCore cutting testAlok JainAEUEAP R&B and CA Pauri See Pic
3.15-03-2017Grudwara road ch 0.350Core thickness checkingAlok JainAEUEAP R&B and CA Pauri See Pic
4.15-03-2017At Grudwara Road Ch 0.350Cure cutting testAlok JainAEUEAP R&B and CA Pauri See Pic
5.08-03-2017Ch 0.740Road inspection by E.E. sirAlok JainAEUEAP R&B and CA Pauri See Pic
6.08-03-2017Km 1Hec 0-2Site Inspection by C.E. sir at Dang Dhobighat M/RAlok JainAEUEAP R&B and CA Pauri See Pic
7.19-11-2016Ch 0.390Hot mix work BC in progressAlok JainAEUEAP R&B and CA Pauri See Pic
8.19-11-2016Ch 0.460 Gola bazar to Dr.Nethani Resi RoadHot mix work BC in progressAlok JainAEUEAP R&B and CA Pauri See Pic
9.06-10-2016Ch 0.480Reinforcement in progress for C.C.roadAlok JainAEUEAP R&B and CA Pauri See Pic
10.30-09-2016Ch 1.460Brest wall in plum concreteAlok JainAEUEAP R&B and CA Pauri See Pic
11.21-09-2016Ch 1.190Dang road visitAlok JainAEUEAP R&B and CA Pauri See Pic
12.06-09-2016Internal rd Srinagar, 1+350CC road under constructionCol M S Bisht (Retd)REDSC2 See Pic