Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bhugadi-Develgadh-Chamdhar Motor Road Agreement signed
Project: UEAP-RB UID: 5512 Sanction Cost: 916.00  lakh Length: KM.
District: Pauri Block: Khirsu Constituency: Srinagar Circle:
DEA: DEA UEAP Pauri DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design and Supervision Type: MDR
Procurement:
Package No.: 1069        Package Name:  UEAP/PWD/C65        Tender Date: 28-10-2014        Current Status: Agreement signed        Achieved on Date: 13-02-2015

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C65      Contractor Name: Rajshree company
Start Date:  12-02-2015      Intended Completion Date:  11-08-2016     
Total Bond Cost: 133704695.04 (1337.05 lakh)        Variation Cost: 1963076.25 (19.63 lakh)    Hence Total Bond Cost is   135667771.29 (1356.68 lakh) 
Sub Project Cost: 866.95  lakh       
LD Analysis for Milestone1: calculated LD is Rs 2607228 for 39 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.38 KM3.0615-03-201514-04-20150.38 KM0.38 KM0.353.06
2.R/Wall, B/ Wall Type Protection works1358.00 m200.2301-03-201528-02-20161143.00 m1143.00 m22.86200.23
3.GSB/RBI/G-10.50 KM1.7715-04-201530-11-20150.49 KM0.49 KM0.21.77
4.G-22.24 KM3.1416-04-201530-11-20150.86 KM0.86 KM0.363.14
5.G-32.72 KM8.6920-04-201530-11-20151.41 KM1.41 KM0.998.69
6.BM i/c Prime Coat, Tack Coat13.70 KM291.4225-10-201530-11-201513.55 KM13.55 KM33.28291.42
7.SDBC i/c Tackcoat13.70 KM244.3501-11-201530-11-201513.55 KM13.55 KM27.9244.35
8.Cause Way2.00 No26.2401-08-201531-03-20162.00 No2.00 No326.24
9.Culverts/Scupper 1.00 No0.9810-10-201531-03-20161.00 No1.00 No0.110.98
10.longitudinal Drain12950.00 m9.5520-03-201531-03-201612980.00 m12950.00 m1.099.53
11.Crash Barrier1432.00 m44.3901-12-201531-03-20161445.00 m1432.00 m5.0243.99
12.Road Furniture1337.00 No26.0501-12-201531-03-20161295.00 No1295.00 No2.9826.05
13.Other Allied Works & Finishing Work 1.00 Job15.8801-11-201531-03-20161.00 Job0.00 Job00.00
Total Amount: 875.75 98.14   859.45
Remarks: No Remarks       Work Program Made On: 25-03-2015        Updation of work program on: 24-07-2017       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.30-March-20153.54  lakh
2.23-May-201524.07  lakh
3.17-June-201517.10  lakh
4.04-September-201514.43  lakh
5.03-October-201555.82  lakh
6.17-October-2015197.23  lakh
7.06-November-2015236.78  lakh
8.07-December-201591.06  lakh
9.15-January-201610.53  lakh
10.09-February-201660.10  lakh
11.29-February-201653.63  lakh
12.31-March-201639.66  lakh
13.30-April-201625.47  lakh
14.28-June-201617.20  lakh
15.10-March-201718.34  lakh
Total 864.96  lakh
% Payment99.77 %
Advance Amount:  174.97  lakh        Recovered Amount:  174.97  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 256   No. of Test Done : 510    No. of Test Passed : 510   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 85.33
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 1
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-02-2017Km 12R.Wall damage & stone collection for recontructionAlok JainAEUEAP R&B and CA Pauri See Pic