Bhugadi-Develgadh-Chamdhar Motor Road
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5512 |
Sanction Cost: |
916.00 lakh |
Length:
|
KM. |
District: |
Pauri |
Block: |
Khirsu |
Constituency: |
Srinagar |
Circle: |
|
DEA: |
DEA UEAP Pauri |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design and Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1069
Package Name: 
UEAP/PWD/C65
Tender Date: 28-10-2014
Current Status: Agreement signed
Achieved on Date: 13-02-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C65
Contractor Name: Rajshree company
|
Start Date: 12-02-2015
Intended Completion Date: 11-08-2016
|
Total Bond Cost: 133704695.04 (1337.05 lakh)
Variation Cost: 1963076.25 (19.63 lakh) Hence Total Bond Cost is 135667771.29 (1356.68 lakh)
|
Sub Project Cost: 866.95 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2607228 for 39 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.38 KM | 3.06 | 15-03-2015 | 14-04-2015 | 0.38 KM | 0.38 KM | 0.35 | 3.06 | 2. | R/Wall, B/ Wall Type Protection works | 1358.00 m | 200.23 | 01-03-2015 | 28-02-2016 | 1143.00 m | 1143.00 m | 22.86 | 200.23 | 3. | GSB/RBI/G-1 | 0.50 KM | 1.77 | 15-04-2015 | 30-11-2015 | 0.49 KM | 0.49 KM | 0.2 | 1.77 | 4. | G-2 | 2.24 KM | 3.14 | 16-04-2015 | 30-11-2015 | 0.86 KM | 0.86 KM | 0.36 | 3.14 | 5. | G-3 | 2.72 KM | 8.69 | 20-04-2015 | 30-11-2015 | 1.41 KM | 1.41 KM | 0.99 | 8.69 | 6. | BM i/c Prime Coat, Tack Coat | 13.70 KM | 291.42 | 25-10-2015 | 30-11-2015 | 13.55 KM | 13.55 KM | 33.28 | 291.42 | 7. | SDBC i/c Tackcoat | 13.70 KM | 244.35 | 01-11-2015 | 30-11-2015 | 13.55 KM | 13.55 KM | 27.9 | 244.35 | 8. | Cause Way | 2.00 No | 26.24 | 01-08-2015 | 31-03-2016 | 2.00 No | 2.00 No | 3 | 26.24 | 9. | Culverts/Scupper | 1.00 No | 0.98 | 10-10-2015 | 31-03-2016 | 1.00 No | 1.00 No | 0.11 | 0.98 | 10. | longitudinal Drain | 12950.00 m | 9.55 | 20-03-2015 | 31-03-2016 | 12980.00 m | 12950.00 m | 1.09 | 9.53 | 11. | Crash Barrier | 1432.00 m | 44.39 | 01-12-2015 | 31-03-2016 | 1445.00 m | 1432.00 m | 5.02 | 43.99 | 12. | Road Furniture | 1337.00 No | 26.05 | 01-12-2015 | 31-03-2016 | 1295.00 No | 1295.00 No | 2.98 | 26.05 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 15.88 | 01-11-2015 | 31-03-2016 | 1.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
875.75 |
|
98.14 |
859.45 |
|
Remarks:
No Remarks
Work Program Made On:
25-03-2015 } ?>
Updation of work program on:
24-07-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-March-2015 | 3.54 lakh | 2. | 23-May-2015 | 24.07 lakh | 3. | 17-June-2015 | 17.10 lakh | 4. | 04-September-2015 | 14.43 lakh | 5. | 03-October-2015 | 55.82 lakh | 6. | 17-October-2015 | 197.23 lakh | 7. | 06-November-2015 | 236.78 lakh | 8. | 07-December-2015 | 91.06 lakh | 9. | 15-January-2016 | 10.53 lakh | 10. | 09-February-2016 | 60.10 lakh | 11. | 29-February-2016 | 53.63 lakh | 12. | 31-March-2016 | 39.66 lakh | 13. | 30-April-2016 | 25.47 lakh | 14. | 28-June-2016 | 17.20 lakh | 15. | 10-March-2017 | 18.34 lakh |
Total |
864.96 lakh |
% Payment | 99.77 % |
|
Advance Amount: 174.97 lakh
Recovered Amount: 174.97 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 256 No. of Test Done : 510 No. of Test Passed : 510 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 85.33 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 1 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 08-02-2017 | Km 12 | R.Wall damage & stone collection for recontruction | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
|
|