Khirsu-Musagli-Damdevel Motor Raod
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5511 |
Sanction Cost: |
467.00 lakh |
Length:
|
KM. |
District: |
Pauri |
Block: |
Pabo |
Constituency: |
Srinagar |
Circle: |
|
DEA: |
DEA UEAP Pauri |
DSC: |
|
DSC Scope: |
Design and Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1069
Package Name: 
UEAP/PWD/C65
Tender Date: 28-10-2014
Current Status: Agreement signed
Achieved on Date: 13-02-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C65
Contractor Name: Rajshree company
|
Start Date: 12-02-2015
Intended Completion Date: 11-08-2016
|
Total Bond Cost: 133704695.04 (1337.05 lakh)
Variation Cost: 1963076.25 (19.63 lakh) Hence Total Bond Cost is 135667771.29 (1356.68 lakh)
|
Sub Project Cost: 424.58 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2607228 for 39 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.14 KM | 6.28 | 20-02-2015 | 30-10-2015 | 0.14 KM | 0.14 KM | 1.28 | 6.28 | 2. | R/Wall, B/ Wall Type Protection works | 654.00 m | 52.86 | 20-02-2015 | 31-12-2015 | 542.00 m | 542.00 m | 10.78 | 52.86 | 3. | G-2 | 0.35 KM | 0.98 | 01-04-2015 | 30-10-2015 | 0.17 KM | 0.17 KM | 0.2 | 0.98 | 4. | G-3 | 0.61 KM | 4.46 | 10-04-2015 | 31-03-2016 | 0.97 KM | 0.97 KM | 0.91 | 4.46 | 5. | BM i/c Prime Coat, Tack Coat | 1.42 KM | 38.38 | 01-05-2015 | 31-03-2016 | 1.42 KM | 1.42 KM | 7.83 | 38.38 | 6. | SDBC i/c Tackcoat | 16.27 KM | 270.97 | 05-05-2015 | 31-03-2016 | 16.27 KM | 16.27 KM | 55.26 | 270.97 | 7. | Cause Way | 3.00 No | 4.96 | 15-04-2015 | 31-12-2015 | 3.00 No | 3.00 No | 1.01 | 4.96 | 8. | Culverts/Scupper | 1.00 No | 10.26 | 01-04-2015 | 31-12-2015 | 1.00 No | 1.00 No | 2.09 | 10.26 | 9. | longitudinal Drain | 15130.00 m | 11.24 | 01-03-2015 | 30-01-2016 | 15130.00 m | 15130.00 m | 2.29 | 11.24 | 10. | Crash Barrier | 865.00 m | 30.38 | 16-06-2015 | 31-03-2016 | 865.00 m | 865.00 m | 6.2 | 30.38 | 11. | Parapet | 240.00 No | 9.45 | 16-06-2015 | 31-07-2015 | 240.00 No | 0.00 No | 0 | 0.00 | 12. | Road Furniture | 1110.00 No | 28.18 | 01-06-2015 | 31-03-2016 | 1110.00 No | 996.00 No | 5.16 | 25.29 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 21.95 | 01-11-2015 | 31-03-2016 | 1.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
490.35 |
|
93.01 |
456.06 |
|
Remarks:
No Remarks
Work Program Made On:
25-03-2015 } ?>
Updation of work program on:
28-06-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-March-2015 | 6.08 lakh | 2. | 23-May-2015 | 14.58 lakh | 3. | 17-June-2015 | 17.98 lakh | 4. | 29-June-2015 | 92.89 lakh | 5. | 04-September-2015 | 9.33 lakh | 6. | 03-October-2015 | 61.01 lakh | 7. | 17-October-2015 | 37.91 lakh | 8. | 06-November-2015 | 11.99 lakh | 9. | 07-December-2015 | 35.86 lakh | 10. | 15-January-2016 | 120.55 lakh | 11. | 09-February-2016 | 30.88 lakh | 12. | 29-February-2016 | 4.20 lakh | 13. | 31-March-2016 | 19.57 lakh | 14. | 30-April-2016 | 15.35 lakh | 15. | 10-March-2017 | 13.51 lakh |
Total |
491.69 lakh |
% Payment | 115.81 % |
|
Advance Amount: 174.97 lakh
Recovered Amount: 174.97 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 256 No. of Test Done : 510 No. of Test Passed : 510 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 85.49 |
No Notice issued. |
Mobile Pic Upload |
No Pics Available on Web Repository |
( last 20 Pics) |
No Pic uploaded. |
|