PCTTBD Motor Road (Thalisain-Bungidhar-Deghat Motor Road)
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5510 |
Sanction Cost: |
2275.00 lakh |
Length:
|
43.000 KM. |
District: |
Pauri |
Block: |
Thalisain |
Constituency: |
Srinagar |
Circle: |
|
DEA: |
DEA UEAP Pauri |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design & Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1076
Package Name: 
UEAP/PWD/C-72
Tender Date: 06-01-2015
Current Status: Agreement signed
Achieved on Date: 15-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C-72
Contractor Name: ISP Construction Pvt. Ltd.
|
Start Date: 07-07-2015
Intended Completion Date: 31-05-2017
Original End Date: 06-02-2017 |
Total Bond Cost: 194499283.4 (1944.99 lakh)
Variation Cost: 19364502.68 (193.65 lakh) Hence Total Bond Cost is 213863786.08 (2138.64 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 13712250 for 141 days
LD Analysis for Milestone2: calculated LD is Rs 8849750 for 91 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.09 KM | 1.60 | 15-07-2015 | 31-10-2016 | 1.51 KM | 0.69 KM | 0.03 | 0.46 | 2. | R/Wall, B/ Wall Type Protection works | 1389.75 m | 188.49 | 01-09-2015 | 28-02-2017 | 2265.00 m | 1215.00 m | 4.73 | 88.40 | 3. | GSB/RBI/G-1 | 0.58 KM | 4.86 | 16-03-2016 | 30-11-2016 | 0.58 KM | 0.50 KM | 0.2 | 4.19 | 4. | G-2 | 7.05 KM | 40.57 | 01-04-2016 | 15-02-2017 | 5.73 KM | 5.73 KM | 1.9 | 40.57 | 5. | G-3 | 17.76 KM | 106.31 | 15-04-2016 | 28-02-2017 | 9.16 KM | 9.16 KM | 4.97 | 106.31 | 6. | PC/CC i/c Prime Coat, Tack Coat | 0.50 KM | 1.00 | 15-04-2016 | 07-03-2017 | 0.50 KM | 0.00 KM | 0 | 0.00 | 7. | BM i/c Prime Coat, Tack Coat | 43.00 KM | 705.63 | 16-04-2016 | 31-03-2017 | 43.00 KM | 33.60 KM | 25.78 | 551.37 | 8. | SDBC i/c Tackcoat | 43.00 KM | 605.24 | 01-05-2016 | 07-04-2017 | 43.00 KM | 33.00 KM | 21.71 | 464.49 | 9. | Cause Way | 29.00 No | 186.65 | 01-10-2015 | 28-02-2017 | 35.00 No | 22.00 No | 5.49 | 89.00 | 10. | Culverts/Scupper | 18.00 No | 62.92 | 01-01-2016 | 28-02-2017 | 10.00 No | 5.00 No | 1.47 | 31.46 | 11. | longitudinal Drain | 9585.00 m | 54.13 | 01-04-2016 | 15-03-2017 | 9585.00 m | 9585.00 m | 2.53 | 54.13 | 12. | Crash Barrier | 1894.00 m | 57.01 | 01-11-2016 | 15-03-2017 | 1894.00 m | 0.00 m | 0 | 0.00 | 13. | Parapet | 430.00 No | 8.01 | 01-11-2016 | 15-03-2017 | 430.00 No | 0.00 No | 0 | 0.00 | 14. | Road Furniture | 2066.00 No | 100.07 | 01-12-2016 | 15-04-2017 | 2066.00 No | 0.00 No | 0 | 0.00 | 15. | Other Allied Works & Finishing Work | 1.00 Job | 16.46 | 01-12-2016 | 30-04-2017 | 1.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
2138.95 |
|
68.8 |
1430.38 |
|
Remarks:
No Remarks
Work Program Made On:
14-09-2016 } ?>
Updation of work program on:
28-06-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-October-2015 | 38.79 lakh | 2. | 15-January-2016 | 46.43 lakh | 3. | 29-February-2016 | 51.85 lakh | 4. | 21-March-2016 | 52.02 lakh | 5. | 30-April-2016 | 95.17 lakh | 6. | 04-June-2016 | 98.75 lakh | 7. | 17-June-2016 | 142.37 lakh | 8. | 27-June-2016 | 69.82 lakh | 9. | 27-July-2016 | 66.20 lakh | 10. | 25-October-2016 | 145.93 lakh | 11. | 27-October-2016 | 163.15 lakh | 12. | 29-November-2016 | 181.13 lakh | 13. | 07-February-2017 | 112.52 lakh | 14. | 20-April-2017 | 217.62 lakh | 15. | 30-May-2017 | 191.11 lakh | 16. | 07-June-2017 | 99.70 lakh |
Total |
1772.56 lakh |
% Payment |
82.88 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 85.96 lakh
Balance to be Recovered -85.96 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
workmen Insurance
Environment & Social Compliances(Sub Project level):
Land Owner Consent |
Detailed report of this subproject
|
|
Quality
|
No. of Test Required : 23 No. of Test Done : 44 No. of Test Passed : 42 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.66 |
Number of Notice(s) issued: 74 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 51 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 06-07-2017 | 0.950 | Site visit CE level 1 Pauri Density checking | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
2. | 03-04-2017 | Ch 25.105 | WBM work in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
3. | 08-03-2017 | Ch 32.450 | WBM G3 in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
4. | 08-03-2017 | Ch 32.350 | WBM G3 in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
5. | 08-03-2017 | Ch 25.700 | Site inspection with DSC & Contrator | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
6. | 08-03-2017 | Ch 9.700 | Brest wall & drain | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
7. | 08-03-2017 | Ch 0.030 | Joint visit with DSC | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
8. | 08-03-2017 | Ch 25.700 Plant site | Material collection at plant | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
9. | 08-03-2017 | Ch 27.800 | Brest wall in wire crate | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
10. | 08-03-2017 | Ch 28.400 | Causeway wall | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
11. | 14-11-2016 | C72-Thalisen- Bungidhar Rd Ch-17+500 | Thrmoplastic paint work in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
12. | 08-11-2016 | Ch 42.160 | Hot mix work(BM) in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
13. | 08-11-2016 | Ch 25.700 Plant Site | BM Production | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
14. | 18-10-2016 | Ch 20.310 | SDBC in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
15. | 18-10-2016 | Km 26 Plant site | SDBC production in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
16. | 18-10-2016 | Ch 20.200 | SDBC in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
17. | 30-09-2016 | C-72-Thailisen-Bungidhar Rd, Ch 12+020 | CC road Work in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
18. | 30-09-2016 | Ch-15+900-Thailisen-Bungidhar rd | WBM
rolling in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
19. | 29-09-2016 | Ch 21.100 | Cleaning of road for hot mix | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
20. | 29-09-2016 | Ch 0.350 | C.C.Road in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
|
|