Lakshman jhoola Rathuwadhaab Dhumakot Motor road
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5505 |
Sanction Cost: |
3636.00 lakh |
Length:
|
80.000 KM. |
District: |
Pauri |
Block: |
Dogadda |
Constituency: |
Yamkeshwar |
Circle: |
|
DEA: |
DEA UEAP Pauri |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design & Supervision |
Type: |
SH |
|
Procurement: |
Package No.: 1075
Package Name: 
UEAP/PWD/C-71
Tender Date: 06-01-2015
Current Status: Agreement signed
Achieved on Date: 25-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C-71
Contractor Name: Woodhill Infrastructure Ltd
|
Start Date: 01-07-2015
Intended Completion Date: 31-03-2017
|
Total Bond Cost: 296910950 (2969.11 lakh)
Variation Cost: 29646131.00 (296.46 lakh) Hence Total Bond Cost is 326557081 (3265.57 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 17517690 for 118 days
LD Analysis for Milestone2: calculated LD is Rs 9352665 for 63 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 4.22 KM | 31.28 | 01-07-2015 | 25-03-2017 | 1.89 KM | 1.20 KM | 0.33 | 19.86 | 2. | R/Wall, B/ Wall Type Protection works | 3004.00 m | 291.74 | 15-07-2015 | 25-05-2017 | 2341.00 m | 1360.00 m | 2.82 | 169.49 | 3. | GSB/RBI/G-1 | 0.59 KM | 4.13 | 15-09-2016 | 20-04-2017 | 0.59 KM | 0.00 KM | 0 | 0.00 | 4. | G-2 | 1.59 KM | 19.36 | 15-10-2015 | 20-04-2017 | 1.25 KM | 0.70 KM | 0.18 | 10.84 | 5. | G-3 | 9.31 KM | 72.38 | 01-11-2015 | 20-04-2017 | 7.83 KM | 3.02 KM | 0.47 | 27.92 | 6. | PC/CC i/c Prime Coat, Tack Coat | 0.53 KM | 5.50 | 01-04-2016 | 20-04-2017 | 0.53 KM | 0.00 KM | 0 | 0.00 | 7. | BM i/c Prime Coat, Tack Coat | 78.64 KM | 1057.78 | 01-10-2015 | 24-04-2017 | 25.34 KM | 25.34 KM | 17.63 | 1000.00 | 8. | SDBC i/c Tackcoat | 80.00 KM | 862.95 | 08-10-2015 | 30-04-2017 | 80.00 KM | 73.00 KM | 13.13 | 787.44 | 9. | Cause Way | 40.00 No | 3031.34 | 15-10-2015 | 20-05-2017 | 42.00 No | 15.00 No | 18.04 | 357.14 | 10. | Culverts/Scupper | 41.00 No | 211.56 | 01-01-2016 | 30-05-2017 | 40.00 No | 8.00 No | 0.71 | 42.31 | 11. | longitudinal Drain | 71785.00 m | 70.78 | 01-10-2015 | 25-05-2017 | 67655.00 m | 45050.00 m | 0.79 | 47.13 | 12. | Crash Barrier | 3867.00 m | 112.14 | 15-05-2016 | 30-05-2017 | 3867.00 m | 1354.00 m | 0.65 | 39.27 | 13. | Parapet | 1560.00 No | 39.34 | 01-10-2016 | 30-05-2017 | 160.00 No | 50.00 No | 0.21 | 12.29 | 14. | Road Furniture | 4561.00 No | 150.31 | 01-01-2017 | 30-05-2017 | 4571.00 No | 662.00 No | 0.36 | 3.16 | 15. | Other Allied Works & Finishing Work | 1.00 Job | 38.68 | 01-01-2017 | 30-05-2017 | 1.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
5999.27 |
|
55.32 |
2516.85 |
|
Remarks:
No Remarks
Work Program Made On:
14-09-2016 } ?>
Updation of work program on:
28-06-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 17-October-2015 | 41.73 lakh | 2. | 09-November-2015 | 17.73 lakh | 3. | 04-January-2016 | 54.75 lakh | 4. | 01-February-2016 | 86.52 lakh | 5. | 19-March-2016 | 66.13 lakh | 6. | 30-April-2016 | 143.04 lakh | 7. | 22-May-2016 | 100.86 lakh | 8. | 30-May-2016 | 146.91 lakh | 9. | 24-June-2016 | 91.04 lakh | 10. | 28-June-2016 | 65.04 lakh | 11. | 29-June-2016 | 33.20 lakh | 12. | 25-July-2016 | 74.33 lakh | 13. | 30-July-2016 | 95.07 lakh | 14. | 31-August-2016 | 40.84 lakh | 15. | 15-September-2016 | 14.30 lakh | 16. | 25-October-2016 | 242.22 lakh | 17. | 26-October-2016 | 139.15 lakh | 18. | 30-November-2016 | 184.11 lakh | 19. | 06-January-2017 | 180.65 lakh | 20. | 12-January-2017 | 116.66 lakh | 21. | 28-February-2017 | 106.93 lakh | 22. | 09-March-2017 | 46.21 lakh | 23. | 20-April-2017 | 103.92 lakh | 24. | 03-May-2017 | 86.88 lakh | 25. | 17-May-2017 | 55.13 lakh | 26. | 30-May-2017 | 26.44 lakh | 27. | 07-June-2017 | 95.85 lakh | 28. | 19-June-2017 | 117.73 lakh | 29. | 31-August-2017 | 48.23 lakh | 30. | 16-October-2017 | 177.35 lakh |
Total |
2798.95 lakh |
% Payment |
85.74 % |
|
Advance Amount: 421.58 lakh
Recovered Amount: 265.90 lakh
Balance to be Recovered 155.68 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
workmen Insurance
Environment & Social Compliances(Sub Project level):
Land Owner Consent |
Detailed report of this subproject
|
|
Quality
|
No. of Test Required : 1551 No. of Test Done : 1600 No. of Test Passed : 1600 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 86.88 |
Number of Notice(s) issued: 79 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 84 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 19-07-2017 | Ch 106.450 | Tree plantation work in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
2. | 03-05-2017 | Ch 110.100 | Box culvert bridge in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
3. | 18-04-2017 | Ch 110.100 | Box culvert bridge in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
4. | 30-03-2017 | Km 98 | Sdbc work checking by CE sir | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
5. | 29-03-2017 | Km 103 | Sdbc checking by CE 1 Pauri sir | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
6. | 29-03-2017 | Ch 110.100 | Box culvert bridge site visit by CE 1 Pauri | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
7. | 29-03-2017 | Ch 110.100 | Box culvert bridge in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
8. | 17-03-2017 | Ch 110.100 | Box culvert bridge in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
9. | 17-03-2017 | Ch 110.100 | Box culvert bridge in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
10. | 08-03-2017 | Ch 110.100 | Site inspection by SE sir at bridge | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
11. | 08-03-2017 | Ch 62.500 | SE sir site inspection | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
12. | 08-03-2017 | Ch 51.600 | SE sir site visit | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
13. | 08-03-2017 | Ch 41.995 | Thickness checking by SE Sir | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
14. | 08-03-2017 | Ch 25.750 | Thickness checking by SE sir | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
15. | 08-03-2017 | Ch 25.750 | SDBC & BM work checking by SE Sir | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
16. | 08-03-2017 | Ch 19.050 | SDBC Thickness checking by SE sir | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
17. | 08-03-2017 | Ch 18.005 | SDBC thickness by SE Sir | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
18. | 08-03-2017 | Ch 18.005 | SDBC checking by SE Sir | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
19. | 08-03-2017 | Ch 110.100 box culvert bridge near Hanumanti village | Joint Inspection for Reinforcement checking | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
20. | 08-03-2017 | Ch 110.100 box culvert bridge near Hanumanti | Reinforcement work in bridge checking | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
|
|