Kanda-Sumari-Bugani
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5503 |
Sanction Cost: |
610.00 lakh |
Length:
|
17.500 KM. |
District: |
Pauri |
Block: |
Khirsu |
Constituency: |
Srinagar |
Circle: |
|
DEA: |
DEA UEAP Pauri |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
Design & Supervision |
Type: |
SH |
|
Procurement: |
Package No.: 1043
Package Name: 
UEAP/PWD/C40
Tender Date: 06-08-2014
Current Status: Agreement signed
Achieved on Date: 22-11-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C40
Contractor Name: N P Buildwell Pvt. Ltd
|
Start Date: 01-12-2014
Intended Completion Date: 31-05-2016
|
Total Bond Cost: 59489480 (594.89 lakh)
Variation Cost: 709540.00 (7.1 lakh) Hence Total Bond Cost is 60199020 (601.99 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.06 KM | 1.15 | 05-12-2014 | 04-03-2015 | 17.50 KM | 17.50 KM | 0.3 | 1.15 | 2. | R/Wall, B/ Wall Type Protection works | 1070.00 m | 108.86 | 01-01-2015 | 10-08-2015 | 1070.00 m | 1070.00 m | 28.74 | 108.86 | 3. | GSB/RBI/G-1 | 0.45 KM | 2.32 | 25-02-2015 | 24-04-2015 | 0.45 KM | 0.45 KM | 0.61 | 2.32 | 4. | G-2 | 0.55 KM | 2.02 | 28-02-2015 | 24-04-2015 | 0.55 KM | 0.55 KM | 0.53 | 2.02 | 5. | G-3 | 0.85 KM | 7.08 | 02-03-2015 | 24-04-2015 | 0.85 KM | 0.85 KM | 1.87 | 7.08 | 6. | BM i/c Prime Coat, Tack Coat | 1.13 KM | 41.65 | 17-03-2015 | 16-05-2015 | 1.13 KM | 1.13 KM | 11 | 41.65 | 7. | SDBC i/c Tackcoat | 17.50 KM | 32.24 | 25-03-2015 | 30-10-2015 | 17.50 KM | 17.50 KM | 8.51 | 32.24 | 8. | Cause Way | 1.00 No | 4.50 | 15-01-2015 | 30-05-2015 | 1.00 No | 1.00 No | 1.19 | 4.50 | 9. | Culverts/Scupper | 4.00 No | 11.42 | 15-01-2015 | 30-05-2015 | 4.00 No | 4.00 No | 3.02 | 11.42 | 10. | longitudinal Drain | 17500.00 m | 32.24 | 01-02-2015 | 30-10-2015 | 17500.00 m | 17500.00 m | 8.51 | 32.24 | 11. | Crash Barrier | 3200.00 m | 93.26 | 15-05-2015 | 30-10-2015 | 3200.00 m | 3200.00 m | 24.62 | 93.26 | 12. | Parapet | 104.00 No | 1.83 | 15-05-2015 | 30-10-2015 | 104.00 No | 0.00 No | 0 | 0.00 | 13. | Road Furniture | 4463.00 No | 27.33 | 15-07-2015 | 14-10-2015 | 4463.00 No | 4463.00 No | 7.22 | 27.33 | 14. | Other Allied Works & Finishing Work | 1.00 Job | 12.91 | 15-07-2015 | 14-10-2015 | 1.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
378.81 |
|
96.11 |
364.07 |
|
Remarks:
No Remarks
Work Program Made On:
26-02-2015 } ?>
Updation of work program on:
24-07-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 03-March-2015 | 26.30 lakh | 2. | 28-March-2015 | 32.65 lakh | 3. | 23-May-2015 | 18.84 lakh | 4. | 04-June-2015 | 112.95 lakh | 5. | 17-June-2015 | 158.18 lakh | 6. | 29-June-2015 | 78.46 lakh | 7. | 17-August-2015 | 54.06 lakh | 8. | 22-September-2015 | 48.60 lakh | 9. | 20-October-2015 | 56.33 lakh | 10. | 29-February-2016 | 3.56 lakh | 11. | 27-February-2017 | 8.99 lakh | 12. | 16-October-2017 | 3.06 lakh |
Total |
601.98 lakh |
% Payment |
99.99 % |
|
Advance Amount: 76.04 lakh
Recovered Amount: 76.04 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 11 No. of Test Done : 472 No. of Test Passed : 472 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.46 |
Number of Notice(s) issued: 76 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 67 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 08-11-2015 | C40, Damaged road R/Wall in progress at KM17+450 | R/Wall in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
2. | 07-11-2015 | C35, KM18, Buakhal-Devpryag Rd | Rolling in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
3. | 26-10-2015 | C40-KM18, Khanda-Bugani Rd | R/Wall foundation in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
4. | 05-10-2015 | Ch 17.500 | UEAP project board C 40 | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
5. | 25-09-2015 | C40,KM1+450, Khanda-Sumari-Bugani Rd | KC drain work in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
6. | 09-09-2015 | Km 18 | Damaged R.Wall | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
7. | 23-08-2015 | C40,KM3+700,Khanda-Sumadi-Bugani Rd | Digging work in progress for MBCB | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
8. | 23-08-2015 | C40,KM17+450,Khanda-Sumadi-Bugani Rd | SRMD. Damage due to rain | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
9. | 23-08-2015 | C40, KM17+600,Khanda-Sumadi-Bugani Rd | SRMD. Damage due to rain | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
10. | 17-08-2015 | C40,KM4+970, Khand-Sumafi-Bugani Rd | Slip due to Rain. SRMD | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
11. | 17-08-2015 | C40,KM2+080,khand-Sumadi-Bugani Rd | Slip due to rain. SRMD | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
12. | 17-08-2015 | C40,KM 1+245 to 270,Khanda-Sumadi-Bugani Rd | srmd:Slip about 30m stretch. Dry wall damaged. SRMD | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
13. | 17-08-2015 | C40, KM7+680, Khand-Sumadi-Bugani Rd | Digging for MBCB work in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
14. | 11-08-2015 | C40, KM 13+450,Khanda-Sumari-Bugani Rd | Post digging for crash barriear in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
15. | 10-08-2015 | Km0+210 | K.C Drain work in progress | O P Singh | unknown | UEAP R&B Pauri | See Pic |
16. | 04-08-2015 | SC40,KM 14+700 | Crash barrier work in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
17. | 29-07-2015 | C40, KM 11+870,khanda-Sumari-Bhugani Road. | Slip due to rain & PMGSY Rd above washed away.RR Bended wall damaged.SRMD | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
18. | 09-07-2015 | NH-119, Km. 268 | Pollution Control Unit | D P Singh1 | RE | DSC ADB Pauri | See Pic |
19. | 09-07-2015 | 14+750 | Raniy seson | Arivind gupta | Site Supervisor | DSC2 Pauri | See Pic |
20. | 02-07-2015 | Road mraking in progress | Km 6+350 road marking in progress | O P Singh | unknown | UEAP R&B Pauri | See Pic |
|
|