Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Kanda-Sumari-Bugani Agreement signed
Project: UEAP-RB UID: 5503 Sanction Cost: 610.00  lakh Length: 17.500 KM.
District: Pauri Block: Khirsu Constituency: Srinagar Circle:
DEA: DEA UEAP Pauri DSC: Royal Haskoning DHV DSC Scope: Design & Supervision Type: SH
Procurement:
Package No.: 1043        Package Name:  UEAP/PWD/C40        Tender Date: 06-08-2014        Current Status: Agreement signed        Achieved on Date: 22-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C40      Contractor Name: N P Buildwell Pvt. Ltd
Start Date:  01-12-2014      Intended Completion Date:  31-05-2016     
Total Bond Cost: 59489480 (594.89 lakh)        Variation Cost: 709540.00 (7.1 lakh)    Hence Total Bond Cost is   60199020 (601.99 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.06 KM1.1505-12-201404-03-201517.50 KM17.50 KM0.31.15
2.R/Wall, B/ Wall Type Protection works1070.00 m108.8601-01-201510-08-20151070.00 m1070.00 m28.74108.86
3.GSB/RBI/G-10.45 KM2.3225-02-201524-04-20150.45 KM0.45 KM0.612.32
4.G-20.55 KM2.0228-02-201524-04-20150.55 KM0.55 KM0.532.02
5.G-30.85 KM7.0802-03-201524-04-20150.85 KM0.85 KM1.877.08
6.BM i/c Prime Coat, Tack Coat1.13 KM41.6517-03-201516-05-20151.13 KM1.13 KM1141.65
7.SDBC i/c Tackcoat17.50 KM32.2425-03-201530-10-201517.50 KM17.50 KM8.5132.24
8.Cause Way1.00 No4.5015-01-201530-05-20151.00 No1.00 No1.194.50
9.Culverts/Scupper 4.00 No11.4215-01-201530-05-20154.00 No4.00 No3.0211.42
10.longitudinal Drain17500.00 m32.2401-02-201530-10-201517500.00 m17500.00 m8.5132.24
11.Crash Barrier3200.00 m93.2615-05-201530-10-20153200.00 m3200.00 m24.6293.26
12.Parapet104.00 No1.8315-05-201530-10-2015104.00 No0.00 No00.00
13.Road Furniture4463.00 No27.3315-07-201514-10-20154463.00 No4463.00 No7.2227.33
14.Other Allied Works & Finishing Work 1.00 Job12.9115-07-201514-10-20151.00 Job0.00 Job00.00
Total Amount: 378.81 96.11   364.07
Remarks: No Remarks       Work Program Made On: 26-02-2015        Updation of work program on: 24-07-2017       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.03-March-201526.30  lakh
2.28-March-201532.65  lakh
3.23-May-201518.84  lakh
4.04-June-2015112.95  lakh
5.17-June-2015158.18  lakh
6.29-June-201578.46  lakh
7.17-August-201554.06  lakh
8.22-September-201548.60  lakh
9.20-October-201556.33  lakh
10.29-February-20163.56  lakh
11.27-February-20178.99  lakh
12.16-October-20173.06  lakh
Total 601.98  lakh
% Payment 99.99 %
Advance Amount:  76.04  lakh        Recovered Amount:  76.04  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 11   No. of Test Done : 472    No. of Test Passed : 472   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.46
Number of Notice(s) issued: 76

Mobile Pic Upload

Number of Pics Available on Web Repository: 67
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-11-2015C40, Damaged road R/Wall in progress at KM17+450R/Wall in progressCol M S Bisht (Retd)REDSC2 See Pic
2.07-11-2015C35, KM18, Buakhal-Devpryag RdRolling in progressCol M S Bisht (Retd)REDSC2 See Pic
3.26-10-2015C40-KM18, Khanda-Bugani RdR/Wall foundation in progressCol M S Bisht (Retd)REDSC2 See Pic
4.05-10-2015Ch 17.500UEAP project board C 40Alok JainAEUEAP R&B and CA Pauri See Pic
5.25-09-2015C40,KM1+450, Khanda-Sumari-Bugani RdKC drain work in progressCol M S Bisht (Retd)REDSC2 See Pic
6.09-09-2015Km 18Damaged R.WallAlok JainAEUEAP R&B and CA Pauri See Pic
7.23-08-2015C40,KM3+700,Khanda-Sumadi-Bugani RdDigging work in progress for MBCBCol M S Bisht (Retd)REDSC2 See Pic
8.23-08-2015C40,KM17+450,Khanda-Sumadi-Bugani RdSRMD. Damage due to rainCol M S Bisht (Retd)REDSC2 See Pic
9.23-08-2015C40, KM17+600,Khanda-Sumadi-Bugani RdSRMD. Damage due to rainCol M S Bisht (Retd)REDSC2 See Pic
10.17-08-2015C40,KM4+970, Khand-Sumafi-Bugani RdSlip due to Rain. SRMDCol M S Bisht (Retd)REDSC2 See Pic
11.17-08-2015C40,KM2+080,khand-Sumadi-Bugani RdSlip due to rain. SRMDCol M S Bisht (Retd)REDSC2 See Pic
12.17-08-2015C40,KM 1+245 to 270,Khanda-Sumadi-Bugani Rdsrmd:Slip about 30m stretch. Dry wall damaged. SRMDCol M S Bisht (Retd)REDSC2 See Pic
13.17-08-2015C40, KM7+680, Khand-Sumadi-Bugani RdDigging for MBCB work in progressCol M S Bisht (Retd)REDSC2 See Pic
14.11-08-2015C40, KM 13+450,Khanda-Sumari-Bugani RdPost digging for crash barriear in progressCol M S Bisht (Retd)REDSC2 See Pic
15.10-08-2015Km0+210K.C Drain work in progressO P SinghunknownUEAP R&B Pauri See Pic
16.04-08-2015SC40,KM 14+700Crash barrier work in progressCol M S Bisht (Retd)REDSC2 See Pic
17.29-07-2015C40, KM 11+870,khanda-Sumari-Bhugani Road.Slip due to rain & PMGSY Rd above washed away.RR Bended wall damaged.SRMDCol M S Bisht (Retd)REDSC2 See Pic
18.09-07-2015NH-119, Km. 268Pollution Control UnitD P Singh1REDSC ADB Pauri See Pic
19.09-07-201514+750Raniy sesonArivind guptaSite SupervisorDSC2 Pauri See Pic
20.02-07-2015Road mraking in progressKm 6+350 road marking in progressO P SinghunknownUEAP R&B Pauri See Pic