Project:  District: Package: Sub Project: 

Sub Project Profile Report

Buwakhal-Pauri-Devprayag-Gaja-Jajal Agreement signed
Project: UEAP-RB UID: 5502 Sanction Cost: 1386.00  lakh Length: 45.000 KM.
District: Pauri Block: Pauri Constituency: Pauri Circle:
DEA: DEA UEAP Pauri DSC: DSC Scope: Design & Supervision Type: MDR
Procurement:
Package No.: 1038        Package Name:  UEAP/PWD/C35        Tender Date: 08-04-2014        Current Status: Agreement signed        Achieved on Date: 13-10-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C35      Contractor Name: Bharat Construction
Start Date:  20-10-2014      Intended Completion Date:  19-04-2016     
Total Bond Cost: 134093812 (1340.94 lakh)        Variation Cost: 3365211.98 (33.65 lakh)    Hence Total Bond Cost is   137459023.98 (1374.59 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 5028525 for 75 days        LD Analysis for Milestone2: calculated LD is Rs 10392285 for 155 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence8.56 KM19.6120-10-201415-03-20168.56 KM8.56 KM1.4219.61
2.R/Wall, B/ Wall Type Protection works1970.00 m56.4701-11-201401-04-20161970.00 m1970.00 m4.0856.47
3.GSB/RBI/G-10.10 KM0.2801-04-201525-02-20160.10 KM0.10 KM0.020.28
4.G-20.10 KM0.1305-04-201526-02-20160.05 KM0.05 KM0.010.13
5.G-30.19 KM0.9108-04-201528-02-20160.25 KM0.25 KM0.070.91
6.BM i/c Prime Coat, Tack Coat1.93 KM57.5701-04-201512-04-20161.93 KM1.93 KM4.1657.57
7.SDBC i/c Tackcoat41.45 KM930.4805-04-201515-04-201634.00 KM34.00 KM67.3930.48
8.Cause Way3.00 No6.3330-03-201515-03-20163.00 No3.00 No0.466.33
9.Culverts/Scupper 2.00 No7.9901-04-201530-05-20152.00 No0.00 No00.00
10.longitudinal Drain91750.00 m87.7320-10-201430-03-201683450.00 m83450.00 m6.3587.73
11.Crash Barrier2830.00 m99.0215-04-201515-04-20162830.00 m2830.00 m7.1699.02
12.Road Furniture2800.00 No79.1615-05-201515-04-20163000.00 No2800.00 No5.3473.89
13.Other Allied Works & Finishing Work 1.00 Job36.9301-01-201615-04-20161.00 Job0.00 Job00.00
Total Amount: 1382.61 96.37   1332.42
Remarks: No Remarks       Work Program Made On: 28-03-2015        Updation of work program on: 28-06-2017       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.21-January-201527.35  lakh
2.17-March-201510.41  lakh
3.30-March-201514.49  lakh
4.23-May-2015113.01  lakh
5.08-June-201559.38  lakh
6.20-October-2015225.51  lakh
7.09-November-201574.83  lakh
8.15-January-201684.21  lakh
9.22-March-201640.55  lakh
10.30-March-2016214.85  lakh
11.30-April-2016291.25  lakh
12.15-May-2016174.03  lakh
13.07-February-201744.71  lakh
Total 1374.58  lakh
% Payment 100 %
Advance Amount:  260.20  lakh        Recovered Amount:  260.20  lakh        Balance to be Recovered  -0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): No Pending Issue
Environment & Social Compliances(Sub Project level): project information board, DG set
Detailed report of this subproject
Quality
No. of Test Required : 337   No. of Test Done : 438    No. of Test Passed : 437   No. of Test Failed : 1   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 85.60
Number of Notice(s) issued: 76

Mobile Pic Upload

Number of Pics Available on Web Repository: 119
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-03-2017Km 35Site visitAlok JainAEUEAP R&B and CA Pauri See Pic
2.16-03-2016Ch 47.925Sdbc in progressAlok JainAEUEAP R&B and CA Pauri See Pic
3.16-03-2016Km 48SDBC in progressAlok JainAEUEAP R&B and CA Pauri See Pic
4.16-03-2016Km 46Pucca drain in progressAlok JainAEUEAP R&B and CA Pauri See Pic
5.16-03-201627.532Core sample takenAlok JainAEUEAP R&B and CA Pauri See Pic
6.16-02-2016Km 44Const of R.WallAlok JainAEUEAP R&B and CA Pauri See Pic
7.25-11-2015Plant site km44Sdbc in progressAlok JainAEUEAP R&B and CA Pauri See Pic
8.09-11-2015C35, Buakhal-Devpryag RdLaying & rolling in progressCol M S Bisht (Retd)REDSC2 See Pic
9.07-11-2015C35,Buakhal-Devpryag, KM18Laying & Rolling in progressCol M S Bisht (Retd)REDSC2 See Pic
10.07-11-2015C35, Buakhal-Devpryag Rd, KM18SDBC rolling in progressCol M S Bisht (Retd)REDSC2 See Pic
11.07-11-2015C35, Buakhal-Devpryag Rd,Km 18,Rolling in progressCol M S Bisht (Retd)REDSC2 See Pic
12.07-11-2015C35, Buakhal-Devpryag, KM18Laying & Rolling in progressCol M S Bisht (Retd)REDSC2 See Pic
13.07-11-2015C35,17+210,Buakhal-Devpryag RdRoad surface cleaning before layingCol M S Bisht (Retd)REDSC2 See Pic
14.05-11-2015Ch 32.755Causeway in progressAlok JainAEUEAP R&B and CA Pauri See Pic
15.28-10-201517.770Sdbc work in progressAlok JainAEUEAP R&B and CA Pauri See Pic
16.28-10-2015Ch 17.830Sdbc work in progressAlok JainAEUEAP R&B and CA Pauri See Pic
17.16-10-2015C35 KM22, Buakhal Devpryag RdLaying & rolling SDBCCol M S Bisht (Retd)REDSC2 See Pic
18.15-10-2015Km 22SDBC work in progressAlok JainAEUEAP R&B and CA Pauri See Pic
19.15-10-2015Km 22SDBC in progressAlok JainAEUEAP R&B and CA Pauri See Pic
20.12-10-2015C35,KM 22+950,Buakhal-Drvpryag RdRolling work SDBC in progressCol M S Bisht (Retd)REDSC2 See Pic