Buwakhal-Pauri-Devprayag-Gaja-Jajal
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5502 |
Sanction Cost: |
1386.00 lakh |
Length:
|
45.000 KM. |
District: |
Pauri |
Block: |
Pauri |
Constituency: |
Pauri |
Circle: |
|
DEA: |
DEA UEAP Pauri |
DSC: |
|
DSC Scope: |
Design & Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1038
Package Name: 
UEAP/PWD/C35
Tender Date: 08-04-2014
Current Status: Agreement signed
Achieved on Date: 13-10-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C35
Contractor Name: Bharat Construction
|
Start Date: 20-10-2014
Intended Completion Date: 19-04-2016
|
Total Bond Cost: 134093812 (1340.94 lakh)
Variation Cost: 3365211.98 (33.65 lakh) Hence Total Bond Cost is 137459023.98 (1374.59 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 5028525 for 75 days
LD Analysis for Milestone2: calculated LD is Rs 10392285 for 155 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 8.56 KM | 19.61 | 20-10-2014 | 15-03-2016 | 8.56 KM | 8.56 KM | 1.42 | 19.61 | 2. | R/Wall, B/ Wall Type Protection works | 1970.00 m | 56.47 | 01-11-2014 | 01-04-2016 | 1970.00 m | 1970.00 m | 4.08 | 56.47 | 3. | GSB/RBI/G-1 | 0.10 KM | 0.28 | 01-04-2015 | 25-02-2016 | 0.10 KM | 0.10 KM | 0.02 | 0.28 | 4. | G-2 | 0.10 KM | 0.13 | 05-04-2015 | 26-02-2016 | 0.05 KM | 0.05 KM | 0.01 | 0.13 | 5. | G-3 | 0.19 KM | 0.91 | 08-04-2015 | 28-02-2016 | 0.25 KM | 0.25 KM | 0.07 | 0.91 | 6. | BM i/c Prime Coat, Tack Coat | 1.93 KM | 57.57 | 01-04-2015 | 12-04-2016 | 1.93 KM | 1.93 KM | 4.16 | 57.57 | 7. | SDBC i/c Tackcoat | 41.45 KM | 930.48 | 05-04-2015 | 15-04-2016 | 34.00 KM | 34.00 KM | 67.3 | 930.48 | 8. | Cause Way | 3.00 No | 6.33 | 30-03-2015 | 15-03-2016 | 3.00 No | 3.00 No | 0.46 | 6.33 | 9. | Culverts/Scupper | 2.00 No | 7.99 | 01-04-2015 | 30-05-2015 | 2.00 No | 0.00 No | 0 | 0.00 | 10. | longitudinal Drain | 91750.00 m | 87.73 | 20-10-2014 | 30-03-2016 | 83450.00 m | 83450.00 m | 6.35 | 87.73 | 11. | Crash Barrier | 2830.00 m | 99.02 | 15-04-2015 | 15-04-2016 | 2830.00 m | 2830.00 m | 7.16 | 99.02 | 12. | Road Furniture | 2800.00 No | 79.16 | 15-05-2015 | 15-04-2016 | 3000.00 No | 2800.00 No | 5.34 | 73.89 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 36.93 | 01-01-2016 | 15-04-2016 | 1.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
1382.61 |
|
96.37 |
1332.42 |
|
Remarks:
No Remarks
Work Program Made On:
28-03-2015 } ?>
Updation of work program on:
28-06-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 21-January-2015 | 27.35 lakh | 2. | 17-March-2015 | 10.41 lakh | 3. | 30-March-2015 | 14.49 lakh | 4. | 23-May-2015 | 113.01 lakh | 5. | 08-June-2015 | 59.38 lakh | 6. | 20-October-2015 | 225.51 lakh | 7. | 09-November-2015 | 74.83 lakh | 8. | 15-January-2016 | 84.21 lakh | 9. | 22-March-2016 | 40.55 lakh | 10. | 30-March-2016 | 214.85 lakh | 11. | 30-April-2016 | 291.25 lakh | 12. | 15-May-2016 | 174.03 lakh | 13. | 07-February-2017 | 44.71 lakh |
Total |
1374.58 lakh |
% Payment |
100 % |
|
Advance Amount: 260.20 lakh
Recovered Amount: 260.20 lakh
Balance to be Recovered -0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
No Pending Issue
Environment & Social Compliances(Sub Project level):
project information board, DG set |
Detailed report of this subproject
|
|
Quality
|
No. of Test Required : 337 No. of Test Done : 438 No. of Test Passed : 437 No. of Test Failed : 1 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 85.60 |
Number of Notice(s) issued: 76 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 119 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 08-03-2017 | Km 35 | Site visit | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
2. | 16-03-2016 | Ch 47.925 | Sdbc in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
3. | 16-03-2016 | Km 48 | SDBC in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
4. | 16-03-2016 | Km 46 | Pucca drain in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
5. | 16-03-2016 | 27.532 | Core sample taken | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
6. | 16-02-2016 | Km 44 | Const of R.Wall | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
7. | 25-11-2015 | Plant site km44 | Sdbc in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
8. | 09-11-2015 | C35, Buakhal-Devpryag Rd | Laying & rolling in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
9. | 07-11-2015 | C35,Buakhal-Devpryag, KM18 | Laying & Rolling in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
10. | 07-11-2015 | C35, Buakhal-Devpryag Rd, KM18 | SDBC rolling in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
11. | 07-11-2015 | C35, Buakhal-Devpryag Rd,Km 18, | Rolling in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
12. | 07-11-2015 | C35, Buakhal-Devpryag, KM18 | Laying & Rolling in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
13. | 07-11-2015 | C35,17+210,Buakhal-Devpryag Rd | Road surface cleaning before laying | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
14. | 05-11-2015 | Ch 32.755 | Causeway in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
15. | 28-10-2015 | 17.770 | Sdbc work in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
16. | 28-10-2015 | Ch 17.830 | Sdbc work in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
17. | 16-10-2015 | C35 KM22, Buakhal Devpryag Rd | Laying & rolling SDBC | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
18. | 15-10-2015 | Km 22 | SDBC work in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
19. | 15-10-2015 | Km 22 | SDBC in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
20. | 12-10-2015 | C35,KM 22+950,Buakhal-Drvpryag Rd | Rolling work SDBC in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
|
|