Pauri-Khirsu-Srinagar Road
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5501 |
Sanction Cost: |
404.00 lakh |
Length:
|
39.000 KM. |
District: |
Pauri |
Block: |
Khirsu |
Constituency: |
Srinagar |
Circle: |
|
DEA: |
DEA UEAP Pauri |
DSC: |
CCEE Group India Pvt.Ltd |
DSC Scope: |
Design & Supervision |
Type: |
SH |
|
Procurement: |
Package No.: 1007
Package Name: 
UEAP/PWD/C5
Tender Date: 13-01-2014
Current Status: Agreement signed
Achieved on Date: 21-04-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C5
Contractor Name: R.G. Buildwell.
|
Start Date: 17-06-2014
Intended Completion Date: 16-09-2015
|
Total Bond Cost: 38469172.15 (384.69 lakh)
Variation Cost: 743715.00 (7.44 lakh) Hence Total Bond Cost is 39212887.15 (392.13 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 3308420 for 172 days
LD Analysis for Milestone2: calculated LD is Rs 884810 for 46 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.58 KM | 0.73 | 01-07-2014 | 15-09-2014 | 0.58 KM | 0.58 KM | 0.19 | 0.73 | 2. | R/Wall, B/ Wall Type Protection works | 1013.00 m | 49.99 | 01-07-2014 | 25-07-2015 | 1013.00 m | 1013.00 m | 12.61 | 49.99 | 3. | GSB/RBI/G-1 | 0.22 KM | 1.79 | 15-10-2014 | 28-02-2015 | 0.22 KM | 0.22 KM | 0.45 | 1.79 | 4. | G-2 | 0.33 KM | 1.41 | 15-10-2014 | 28-02-2015 | 0.33 KM | 0.33 KM | 0.36 | 1.41 | 5. | G-3 | 1.81 KM | 8.35 | 15-10-2014 | 05-03-2015 | 1.81 KM | 1.81 KM | 2.11 | 8.35 | 6. | PC/CC i/c Prime Coat, Tack Coat | 7.00 KM | 69.21 | 15-10-2014 | 15-05-2015 | 7.00 KM | 7.00 KM | 17.46 | 69.21 | 7. | BM i/c Prime Coat, Tack Coat | 3.50 KM | 29.33 | 15-10-2014 | 15-05-2015 | 3.50 KM | 3.50 KM | 7.4 | 29.33 | 8. | SDBC i/c Tackcoat | 14.00 KM | 164.15 | 15-10-2014 | 15-05-2015 | 14.00 KM | 14.00 KM | 41.41 | 164.15 | 9. | Cause Way | 4.00 No | 9.72 | 01-12-2014 | 15-08-2015 | 4.00 No | 4.00 No | 2.45 | 9.72 | 10. | Culverts/Scupper | 4.00 No | 6.15 | 01-12-2014 | 15-08-2015 | 4.00 No | 4.00 No | 1.55 | 6.15 | 11. | longitudinal Drain | 17200.00 m | 17.57 | 01-12-2014 | 15-08-2015 | 27550.00 m | 27550.00 m | 4.43 | 17.57 | 12. | Crash Barrier | 696.00 m | 23.37 | 01-03-2015 | 30-07-2015 | 700.00 m | 700.00 m | 5.9 | 23.37 | 13. | Parapet | 16.00 No | 0.93 | 01-05-2015 | 30-07-2015 | 16.00 No | 0.00 No | 0 | 0.00 | 14. | Road Furniture | 457.00 No | 6.47 | 01-05-2015 | 30-08-2015 | 457.00 No | 457.00 No | 1.63 | 6.47 | 15. | Other Allied Works & Finishing Work | 1.00 Job | 7.25 | 01-05-2015 | 30-08-2015 | 1.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
396.42 |
|
97.94 |
388.24 |
|
Remarks:
No Remarks
Work Program Made On:
17-03-2015 } ?>
Updation of work program on:
24-07-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 10-February-2015 | 17.64 lakh | 2. | 30-March-2015 | 12.59 lakh | 3. | 25-May-2015 | 68.40 lakh | 4. | 09-June-2015 | 177.31 lakh | 5. | 11-August-2015 | 45.31 lakh | 6. | 06-November-2015 | 47.14 lakh | 7. | 30-June-2016 | 25.01 lakh |
Total |
393.4 lakh |
% Payment |
100.32 % |
|
Advance Amount: 85.19 lakh
Recovered Amount: 85.19 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1 No. of Test Done : 195 No. of Test Passed : 195 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.82 |
Number of Notice(s) issued: 68 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 55 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 28-09-2015 | C5, KM19+300, Pauri-Khirsu-Srinagar Rd | Breast wall foundation work in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
2. | 22-09-2015 | C65,KM6+650,Khirsu-Musagali-Damdeval Rd | R/Wall in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
3. | 30-08-2015 | C5, KM28+160, Pauri-Khirsu-Srinagar Rd | R/Wall in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
4. | 28-08-2015 | C5,KM 28+170,Pauri-Khirsu-Srinagar Rd | R/Wall foundation in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
5. | 11-08-2015 | C5,KM33+400, Pauri-Khirsu-Drinagat Rd | Old dry wall damaged. SRMD | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
6. | 11-08-2015 | C5,KM23+400,Pauri-Khirsu-Srinagar Rd | Breast wall in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
7. | 11-08-2015 | C5,KM 24+650,Pauri-Khirsu-Srinagar Rd | Breast wall in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
8. | 11-08-2015 | C5,KM23+250,Pauri-Khirsu-Srinagar Rd | Old dry breast wall damaged in rain. SRMD | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
9. | 11-08-2015 | C5-KM19+450,Pauri-Khirsu-Srinagar Rd | Road side damaged due to heavy rain. SRMD | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
10. | 11-08-2015 | C5, KM-19+250,Pauri-Khirsu-Srinagar Rd | Breast Wall in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
11. | 04-08-2015 | C5, KM 28+400,Pauri-Khirsu-Srinagar Rd | Breast Wall in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
12. | 04-08-2015 | C5,KM-43+240,Pauri-Khirsu-Srinagar Rd | Road damaged. SRMD | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
13. | 29-07-2015 | C5,km 28+390,khrsu-Srinagar Rd | Breast wall foundation in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
14. | 24-07-2015 | C5, KM24+690, Pauri-Khirsu-Srinagar Rd | Breast wall damaged due to heavy rain. SRMD | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
15. | 24-07-2015 | C5, KM 30+370, Pauri-Khirsu-Srinagar Rd | R/Wall in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
16. | 24-07-2015 | C5, KM33+960,Pauri-Khirsu-Srinagar | Road 20m length sinking, C5,Rd width left 2.5m | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
17. | 24-07-2015 | C5, KM33+960,Pauri-Khirsu-Srinagar | Road damaged due to heavy rain.SRMD | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
18. | 13-07-2015 | Km 31 | Damaged R.wall due to rain | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
19. | 11-07-2015 | Ch 21.350 | Road closed due to slip | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
20. | 09-07-2015 | Patch work | Km 11.400 | D P Singh1 | RE | DSC ADB Pauri | See Pic |
|
|