Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Pauri-Khirsu-Srinagar Road Agreement signed
Project: UEAP-RB UID: 5501 Sanction Cost: 404.00  lakh Length: 39.000 KM.
District: Pauri Block: Khirsu Constituency: Srinagar Circle:
DEA: DEA UEAP Pauri DSC: CCEE Group India Pvt.Ltd DSC Scope: Design & Supervision Type: SH
Procurement:
Package No.: 1007        Package Name:  UEAP/PWD/C5        Tender Date: 13-01-2014        Current Status: Agreement signed        Achieved on Date: 21-04-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C5      Contractor Name: R.G. Buildwell.
Start Date:  17-06-2014      Intended Completion Date:  16-09-2015     
Total Bond Cost: 38469172.15 (384.69 lakh)        Variation Cost: 743715.00 (7.44 lakh)    Hence Total Bond Cost is   39212887.15 (392.13 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 3308420 for 172 days        LD Analysis for Milestone2: calculated LD is Rs 884810 for 46 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.58 KM0.7301-07-201415-09-20140.58 KM0.58 KM0.190.73
2.R/Wall, B/ Wall Type Protection works1013.00 m49.9901-07-201425-07-20151013.00 m1013.00 m12.6149.99
3.GSB/RBI/G-10.22 KM1.7915-10-201428-02-20150.22 KM0.22 KM0.451.79
4.G-20.33 KM1.4115-10-201428-02-20150.33 KM0.33 KM0.361.41
5.G-31.81 KM8.3515-10-201405-03-20151.81 KM1.81 KM2.118.35
6.PC/CC i/c Prime Coat, Tack Coat7.00 KM69.2115-10-201415-05-20157.00 KM7.00 KM17.4669.21
7.BM i/c Prime Coat, Tack Coat3.50 KM29.3315-10-201415-05-20153.50 KM3.50 KM7.429.33
8.SDBC i/c Tackcoat14.00 KM164.1515-10-201415-05-201514.00 KM14.00 KM41.41164.15
9.Cause Way4.00 No9.7201-12-201415-08-20154.00 No4.00 No2.459.72
10.Culverts/Scupper 4.00 No6.1501-12-201415-08-20154.00 No4.00 No1.556.15
11.longitudinal Drain17200.00 m17.5701-12-201415-08-201527550.00 m27550.00 m4.4317.57
12.Crash Barrier696.00 m23.3701-03-201530-07-2015700.00 m700.00 m5.923.37
13.Parapet16.00 No0.9301-05-201530-07-201516.00 No0.00 No00.00
14.Road Furniture457.00 No6.4701-05-201530-08-2015457.00 No457.00 No1.636.47
15.Other Allied Works & Finishing Work 1.00 Job7.2501-05-201530-08-20151.00 Job0.00 Job00.00
Total Amount: 396.42 97.94   388.24
Remarks: No Remarks       Work Program Made On: 17-03-2015        Updation of work program on: 24-07-2017       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.10-February-201517.64  lakh
2.30-March-201512.59  lakh
3.25-May-201568.40  lakh
4.09-June-2015177.31  lakh
5.11-August-201545.31  lakh
6.06-November-201547.14  lakh
7.30-June-201625.01  lakh
Total 393.4  lakh
% Payment 100.32 %
Advance Amount:  85.19  lakh        Recovered Amount:  85.19  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): No Pending Issue
Environment & Social Compliances(Sub Project level): Borrow pits
Detailed report of this subproject
Quality
No. of Test Required : 1   No. of Test Done : 195    No. of Test Passed : 195   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 88.82
Number of Notice(s) issued: 68

Mobile Pic Upload

Number of Pics Available on Web Repository: 55
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.28-09-2015C5, KM19+300, Pauri-Khirsu-Srinagar RdBreast wall foundation work in progressCol M S Bisht (Retd)REDSC2 See Pic
2.22-09-2015C65,KM6+650,Khirsu-Musagali-Damdeval RdR/Wall in progressCol M S Bisht (Retd)REDSC2 See Pic
3.30-08-2015C5, KM28+160, Pauri-Khirsu-Srinagar RdR/Wall in progressCol M S Bisht (Retd)REDSC2 See Pic
4.28-08-2015C5,KM 28+170,Pauri-Khirsu-Srinagar RdR/Wall foundation in progressCol M S Bisht (Retd)REDSC2 See Pic
5.11-08-2015C5,KM33+400, Pauri-Khirsu-Drinagat RdOld dry wall damaged. SRMDCol M S Bisht (Retd)REDSC2 See Pic
6.11-08-2015C5,KM23+400,Pauri-Khirsu-Srinagar RdBreast wall in progressCol M S Bisht (Retd)REDSC2 See Pic
7.11-08-2015C5,KM 24+650,Pauri-Khirsu-Srinagar RdBreast wall in progressCol M S Bisht (Retd)REDSC2 See Pic
8.11-08-2015C5,KM23+250,Pauri-Khirsu-Srinagar RdOld dry breast wall damaged in rain. SRMDCol M S Bisht (Retd)REDSC2 See Pic
9.11-08-2015C5-KM19+450,Pauri-Khirsu-Srinagar RdRoad side damaged due to heavy rain. SRMDCol M S Bisht (Retd)REDSC2 See Pic
10.11-08-2015C5, KM-19+250,Pauri-Khirsu-Srinagar RdBreast Wall in progressCol M S Bisht (Retd)REDSC2 See Pic
11.04-08-2015C5, KM 28+400,Pauri-Khirsu-Srinagar RdBreast Wall in progressCol M S Bisht (Retd)REDSC2 See Pic
12.04-08-2015C5,KM-43+240,Pauri-Khirsu-Srinagar RdRoad damaged. SRMDCol M S Bisht (Retd)REDSC2 See Pic
13.29-07-2015C5,km 28+390,khrsu-Srinagar RdBreast wall foundation in progressCol M S Bisht (Retd)REDSC2 See Pic
14.24-07-2015C5, KM24+690, Pauri-Khirsu-Srinagar RdBreast wall damaged due to heavy rain. SRMDCol M S Bisht (Retd)REDSC2 See Pic
15.24-07-2015C5, KM 30+370, Pauri-Khirsu-Srinagar RdR/Wall in progressCol M S Bisht (Retd)REDSC2 See Pic
16.24-07-2015C5, KM33+960,Pauri-Khirsu-SrinagarRoad 20m length sinking, C5,Rd width left 2.5mCol M S Bisht (Retd)REDSC2 See Pic
17.24-07-2015C5, KM33+960,Pauri-Khirsu-SrinagarRoad damaged due to heavy rain.SRMDCol M S Bisht (Retd)REDSC2 See Pic
18.13-07-2015Km 31Damaged R.wall due to rainAlok JainAEUEAP R&B and CA Pauri See Pic
19.11-07-2015Ch 21.350Road closed due to slipAlok JainAEUEAP R&B and CA Pauri See Pic
20.09-07-2015Patch workKm 11.400D P Singh1REDSC ADB Pauri See Pic