Haripur-Ichari-Kwanu-Meenus MR (Chainage-33 Km from Haripur)
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5414 |
Sanction Cost: |
925.00 lakh |
Length:
|
0.575 KM. |
District: |
Dehradun |
Block: |
0028 |
Constituency: |
15 |
Circle: |
|
DEA: |
DEA UEAP Tehri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
SH |
|
Procurement: |
Package No.: 1099
Package Name: 
UEAP/PWD/C-104
Tender Date: 08-06-2016
Current Status: Agreement signed
Achieved on Date: 31-01-2017 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C-104
Contractor Name: Bharat Construction
|
Start Date: 20-02-2017
Intended Completion Date: 19-09-2017
|
Total Bond Cost: 90204464.5 (902.04 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 10418562 for 231 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.90 KM | 15.95 | 20-02-2017 | 31-07-2017 | 0.90 KM | 0.50 KM | 0.98 | 8.86 | 2. | R/Wall, B/ Wall Type Protection works | 900.00 m | 621.09 | 20-02-2017 | 13-09-2017 | 900.00 m | 300.00 m | 22.95 | 207.03 | 3. | Other Allied Works & Finishing Work | 12.00 Job | 265.01 | 21-07-2017 | 18-09-2017 | 12.00 Job | 5.00 Job | 12.24 | 110.42 |
Total Amount: |
902.05 |
|
36.17 |
326.31 |
|
Remarks:
No Remarks
Work Program Made On:
21-07-2017 } ?>
Updation of work program on:
09-08-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 13-June-2017 | 5.58 lakh | 2. | 29-June-2017 | 57.79 lakh | 3. | 22-July-2017 | 25.40 lakh | 4. | 31-August-2017 | 124.07 lakh | 5. | 23-September-2017 | 202.71 lakh |
Total |
415.55 lakh |
% Payment |
46.07 % |
|
Advance Amount: 123.37 lakh
Recovered Amount: 95.50 lakh
Balance to be Recovered 27.87 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
No Pending Issue
Environment & Social Compliances(Sub Project level):
debris disposal, Query |
Detailed report of this subproject
|
|
Quality
|
Test Information not Available. |
Quality Ranking in %: 95.00 |
Number of Notice(s) issued: 26 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 2 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 27-07-2017 | 0+800 | Site visit THGC Eng. | Vikas Verma | JE | UEAP R&B Tehri | See Pic |
2. | 27-07-2017 | 0+575 | Thdc site visit | Vikas Verma | JE | UEAP R&B Tehri | See Pic |
|
|