Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Haripur-Ichari-Kwanu-Meenus MR (Chainage-33 Km from Haripur) Agreement signed
Project: UEAP-RB UID: 5414 Sanction Cost: 925.00  lakh Length: 0.575 KM.
District: Dehradun Block: 0028 Constituency: 15 Circle:
DEA: DEA UEAP Tehri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: SH
Procurement:
Package No.: 1099        Package Name:  UEAP/PWD/C-104        Tender Date: 08-06-2016        Current Status: Agreement signed        Achieved on Date: 31-01-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C-104      Contractor Name: Bharat Construction
Start Date:  20-02-2017      Intended Completion Date:  19-09-2017     
Total Bond Cost: 90204464.5 (902.04 lakh)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 10418562 for 231 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.90 KM15.9520-02-201731-07-20170.90 KM0.50 KM0.988.86
2.R/Wall, B/ Wall Type Protection works900.00 m621.0920-02-201713-09-2017900.00 m300.00 m22.95207.03
3.Other Allied Works & Finishing Work 12.00 Job265.0121-07-201718-09-201712.00 Job5.00 Job12.24110.42
Total Amount: 902.05 36.17   326.31
Remarks: No Remarks       Work Program Made On: 21-07-2017        Updation of work program on: 09-08-2017       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.13-June-20175.58  lakh
2.29-June-201757.79  lakh
3.22-July-201725.40  lakh
4.31-August-2017124.07  lakh
5.23-September-2017202.71  lakh
Total 415.55  lakh
% Payment 46.07 %
Advance Amount:  123.37  lakh        Recovered Amount:  95.50  lakh        Balance to be Recovered  27.87  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): No Pending Issue
Environment & Social Compliances(Sub Project level): debris disposal, Query
Detailed report of this subproject
Quality
Test Information not Available.
Quality Ranking in %: 95.00
Number of Notice(s) issued: 26

Mobile Pic Upload

Number of Pics Available on Web Repository: 2
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-07-20170+800Site visit THGC Eng.Vikas VermaJEUEAP R&B Tehri See Pic
2.27-07-20170+575Thdc site visitVikas VermaJEUEAP R&B Tehri See Pic