Kalsi-Bairatkhai
Work Completed
|
Project: |
UEAP-RB |
UID: |
5403 |
Sanction Cost: |
930.00 lakh |
Length:
|
23.500 KM. |
District: |
Dehradun |
Block: |
Vikas Nagar |
Constituency: |
Chakrata |
Circle: |
|
DEA: |
DEA UEAP Uttarkashi |
DSC: |
|
DSC Scope: |
Design & Supervision |
Type: |
SH |
|
Procurement: |
Package No.: 1027
Package Name: 
UEAP/PWD/C24
Tender Date: 01-08-2014
Current Status: Agreement signed
Achieved on Date: 18-10-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C24
Contractor Name: Maa Bhagwati Construction company
|
Start Date: 10-11-2014
Intended Completion Date: 09-05-2016
|
Total Bond Cost: 82239229 (822.39 lakh)
Variation Cost: 4497068.00 (44.97 lakh) Hence Total Bond Cost is 86736297 (867.36 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 1110240 for 27 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 11.75 KM | 10.84 | 05-01-2015 | 09-05-2016 | 11.75 KM | 11.75 KM | 1.25 | 10.84 | 2. | R/Wall, B/ Wall Type Protection works | 1360.00 m | 156.25 | 15-12-2014 | 09-05-2016 | 1360.00 m | 1360.00 m | 18.01 | 156.25 | 3. | G-2 | 0.42 KM | 2.12 | 01-04-2015 | 09-05-2016 | 0.42 KM | 0.42 KM | 0.24 | 2.12 | 4. | G-3 | 0.42 KM | 1.87 | 01-04-2015 | 09-05-2016 | 0.42 KM | 0.42 KM | 0.22 | 1.87 | 5. | BM i/c Prime Coat, Tack Coat | 11.25 KM | 157.23 | 01-05-2015 | 15-04-2016 | 11.25 KM | 11.25 KM | 18.13 | 157.23 | 6. | SDBC i/c Tackcoat | 23.50 KM | 224.25 | 01-05-2015 | 25-04-2016 | 23.50 KM | 23.50 KM | 25.85 | 224.25 | 7. | Cause Way | 1.00 No | 3.65 | 01-06-2015 | 30-06-2015 | 1.00 No | 1.00 No | 0.42 | 3.65 | 8. | Culverts/Scupper | 21.00 No | 28.28 | 05-04-2015 | 31-08-2015 | 21.00 No | 21.00 No | 3.26 | 28.28 | 9. | longitudinal Drain | 17625.00 m | 86.36 | 01-03-2015 | 29-04-2016 | 17625.00 m | 17625.00 m | 9.96 | 86.36 | 10. | Crash Barrier | 4700.00 m | 101.52 | 25-02-2015 | 09-05-2016 | 4700.00 m | 4700.00 m | 11.7 | 101.52 | 11. | Parapet | 600.00 No | 30.95 | 15-04-2015 | 20-01-2016 | 600.00 No | 600.00 No | 3.57 | 30.95 | 12. | Road Furniture | 330.00 No | 64.05 | 01-01-2016 | 30-04-2016 | 330.00 No | 330.00 No | 7.38 | 64.05 |
Total Amount: |
867.37 |
|
100 |
867.37 |
|
Remarks:
Work Program Made On:
25-02-2015 } ?>
Updation of work program on:
25-07-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 25-March-2015 | 34.13 lakh | 2. | 27-May-2015 | 69.01 lakh | 3. | 29-June-2015 | 190.58 lakh | 4. | 18-September-2015 | 47.44 lakh | 5. | 24-October-2015 | 171.50 lakh | 6. | 05-December-2015 | 69.44 lakh | 7. | 22-January-2016 | 52.09 lakh | 8. | 23-February-2016 | 42.00 lakh | 9. | 30-March-2016 | 130.80 lakh | 10. | 27-June-2017 | 59.61 lakh |
Total |
866.6 lakh |
% Payment |
99.91 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 3.56 lakh
Balance to be Recovered -3.56 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 499 No. of Test Done : 563 No. of Test Passed : 545 No. of Test Failed : 1 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 94.57 |
Number of Notice(s) issued: 68 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 109 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 06-10-2015 | 0.100 | Excavation for Drain | Ajeet Singh | AE | UEAP R&B Uttarkashi | See Pic |
2. | 26-09-2015 | 10.200 | Sdbc laying | Ajeet Singh | AE | UEAP R&B Uttarkashi | See Pic |
3. | 25-09-2015 | 10.230 | B.m.laying | Ajeet Singh | AE | UEAP R&B Uttarkashi | See Pic |
4. | 25-09-2015 | 10+100 | BM laying | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
5. | 23-09-2015 | 10+400 to 10+675 | BM laying | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
6. | 28-07-2015 | 5+660 | End post of crass barior | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
7. | 01-07-2015 | 23+300 | 15 no Parapets completed | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
8. | 01-07-2015 | 15+350 | Scupper slab casting. | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
9. | 01-07-2015 | 23+00 | 8 no Parapets completed | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
10. | 01-07-2015 | 23+100 | 5 no Parapets completed | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
11. | 01-07-2015 | 22+600 | 16 no Parapets completed | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
12. | 01-07-2015 | 22+800 | 20 no Parapets completed | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
13. | 01-07-2015 | 21+300 to 21+100 | Slip zone | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
14. | 01-07-2015 | 21+600 to 22+00 | Slip area | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
15. | 01-07-2015 | 18+800 | 12 no Parapets completed | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
16. | 01-07-2015 | 21+100 | Slip | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
17. | 01-07-2015 | 15+700 | Slip area | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
18. | 01-07-2015 | 17+700 to 17+750 | Crash barrier | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
19. | 01-07-2015 | 18+400 | Crash barrier | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
20. | 01-07-2015 | 18+600 | 13 no Parapets completed | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
|
|