Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Tyuni-Chakrata-Mussoorie-Chamba-Kirtinagar Work Completed
Project: UEAP-RB UID: 5402 Sanction Cost: 1939.00  lakh Length: 47.000 KM.
District: Dehradun Block: Kalsi Constituency: Chakrata Circle:
DEA: DEA UEAP Tehri DSC: DSC Scope: Design & Supervision Type: MDR
Procurement:
Package No.: 1026        Package Name:  UEAP/PWD/C23        Tender Date: 24-03-2014        Current Status: Agreement signed        Achieved on Date: 25-08-2014

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C23      Contractor Name: Raja Construction
Start Date:  17-09-2014      Intended Completion Date:  16-03-2016     
Total Bond Cost: 175103792 (1751.04 lakh)        Variation Cost: 10214844.28 (102.15 lakh)    Hence Total Bond Cost is   185318636.28 (1853.19 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 4027392 for 46 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence45.81 KM28.3716-11-201410-02-201645.81 KM45.81 KM1.5328.37
2.R/Wall, B/ Wall Type Protection works2009.00 m225.0202-11-201410-02-20161619.00 m1619.00 m12.14225.02
3.GSB/RBI/G-12.78 KM15.6420-12-201430-08-20152.78 KM2.78 KM0.8415.64
4.G-22.87 KM13.2520-12-201430-08-20152.87 KM2.87 KM0.7213.25
5.G-34.10 KM19.2020-12-201430-08-20154.10 KM4.10 KM1.0419.20
6.BM i/c Prime Coat, Tack Coat28.65 KM520.5205-03-201510-02-201628.65 KM28.65 KM28.09520.52
7.SDBC i/c Tackcoat44.45 KM490.5905-03-201510-02-201644.45 KM44.45 KM26.47490.59
8.Cause Way16.00 No58.8830-03-201531-01-201614.00 No14.00 No3.1858.88
9.Culverts/Scupper 57.00 No67.8015-11-201431-01-201657.00 No57.00 No3.6667.80
10.longitudinal Drain44500.00 m72.4620-02-201515-02-201644450.00 m44450.00 m3.9172.46
11.Crash Barrier6800.00 m200.4120-01-201520-08-20156800.00 m6800.00 m10.81200.41
12.Parapet1372.00 No40.0720-01-201510-02-20161269.00 No1269.00 No2.1640.07
13.Road Furniture8014.00 No84.6215-01-201616-02-201614513.00 No14513.00 No4.5784.62
14.Other Allied Works & Finishing Work 1.00 Job16.3717-09-201416-02-20161.00 Job1.00 Job0.8816.37
Total Amount: 1853.2 100   1853.2
Remarks: No Remarks       Work Program Made On: 25-02-2015        Updation of work program on: 21-08-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-January-201531.60  lakh
2.10-February-201541.82  lakh
3.19-March-201542.72  lakh
4.23-May-2015338.75  lakh
5.20-June-2015220.16  lakh
6.24-July-2015118.17  lakh
7.13-October-2015153.01  lakh
8.04-November-2015247.91  lakh
9.26-November-2015247.21  lakh
10.12-January-2016160.51  lakh
11.12-February-2016116.66  lakh
12.29-April-201682.42  lakh
13.29-June-201751.82  lakh
Total 1852.76  lakh
% Payment 100.01 %
Advance Amount:  236.61  lakh        Recovered Amount:  236.61  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1311   No. of Test Done : 1384    No. of Test Passed : 1354   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.51
Number of Notice(s) issued: 61

Mobile Pic Upload

Number of Pics Available on Web Repository: 42
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.21-10-201593.850KC drain has been completedAnuj Kumar SinghAEUEAP R&B Tehri See Pic
2.21-10-201599.800Measurement of WBM depthAnuj Kumar SinghAEUEAP R&B Tehri See Pic
3.06-10-201598+450Laying of BMAsha rawatJEDEA ADB Dehradun See Pic
4.27-09-2015CH-101+800BM WorkVikas VermaJEUEAP R&B Tehri See Pic
5.28-08-2015Ch.124.370Laying of WBM (G-1)Rajesh kumarPMDSC R&B ADB See Pic
6.28-08-2015Ch.124.390Laying of (WBM) G-1Rajesh kumarPMDSC R&B ADB See Pic
7.02-08-2015100.250Laying of WBM Grading -2.Rajesh kumarPMDSC R&B ADB See Pic
8.02-08-2015Ch.96.075Existing scrupper damageRajesh kumarPMDSC R&B ADB See Pic
9.02-08-201590.500Laying of sdbcRajesh kumarPMDSC R&B ADB See Pic
10.08-06-2015Chainage 88.200 laying of SDBCLaying of sdbcRajesh kumarPMDSC R&B ADB See Pic
11.08-06-2015127.450Construction of plum.Rajesh kumarPMDSC R&B ADB See Pic
12.25-05-2015ch 96.850r wall under constructionDeepak YadavSEADB Circle See Pic
13.25-05-2015124+407B/w plum concreteAsha rawatJEDEA ADB Dehradun See Pic
14.25-05-2015117+450Plum concrete workM AmirAEUEAP R&B Srinagar See Pic
15.24-04-2015Ch.107.980Laying of SDBC.Rajesh kumarPMDSC R&B ADB See Pic
16.24-04-2015115.250Plum concrete of parapetRajesh kumarPMDSC R&B ADB See Pic
17.31-03-2015Km-119'118'&km117Sdbc has been done in about 2.5 km lengthShankar Ram SEADB Circle See Pic
18.30-03-2015124.610Excavation of catchpitRajesh kumarPMDSC R&B ADB See Pic
19.30-03-2015104.050R wallRajesh kumarPMDSC R&B ADB See Pic
20.21-03-2015119Laying tack coat.Asha rawatJEDEA ADB Dehradun See Pic