Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Kalsi -Chakrata Bond Terminated.
Project: UEAP-RB UID: 5401 Sanction Cost: 341.00  lakh Length: 12.000 KM.
District: Dehradun Block: Vikas Nagar Constituency: Chakrata Circle:
DEA: DEA UEAP Uttarkashi DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design & Supervision Type: MDR
Procurement:
Package No.: 1013        Package Name:  UEAP/PWD/C11        Tender Date: 03-02-2014        Current Status: Agreement signed        Achieved on Date: 09-06-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C11      Contractor Name: Mathiyan Construction Pvt Ltd
Start Date:  30-06-2014      Intended Completion Date:  26-09-2015     
Total Bond Cost: 53436503.32 (534.37 lakh)        Variation Cost: -44798837.32 (-447.99 lakh)    Hence Total Bond Cost is   8637666 (86.38 lakh) 
Sub Project Cost: 341.00  lakh        Variation Cost of Sub Project: -28669611.54  (-286.7 lakh)       Total Sub Project Cost:   54.3 lakh
LD Analysis for Milestone1: calculated LD is Rs 4034418 for 151 days        LD Analysis for Milestone2: calculated LD is Rs 4034418 for 151 days       
Component Wise Progress
No Physical Progress.
Remarks: No Remarks       Work Program Made On:        Updation of work program on:       
Work Program Status:Work Program Not Made Yet
Financial Progress
SNo. Date Payment
1.26-November-201443.34  lakh
2.05-November-201519.68  lakh
Previous Package Expenditure Total 63.02  lakh
SNo. Date Payment
1.26-November-201443.34  lakh
2.05-November-201519.68  lakh
Total 63.02  lakh
% Payment116.06 %
Advance Amount:  53.44  lakh        Recovered Amount:  6.50  lakh        Balance to be Recovered  46.94  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported( Work program not made hence analysis may not be realistic).
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): No Pending Issue
Environment & Social Compliances(Sub Project level): Borrow pits
Detailed report of this subproject
Quality
No. of Test Required : 36   No. of Test Done : 36    No. of Test Passed : 36   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.62
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 5
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.02-05-2015chdnDeepak YadavSEADB Circle See Pic
2.22-09-2014Km 11Cement Concrete PavementAshutosh KumarEEDEA ADB Uttarkashi See Pic
3.22-09-2014Km 4Retaining WallAshutosh KumarEEDEA ADB Uttarkashi See Pic
4.03-09-2014Start pointInformation boardAshutosh KumarEEDEA ADB Uttarkashi See Pic
5.03-09-2014Km 10Cement Concrete PavementAshutosh KumarEEDEA ADB Uttarkashi See Pic