Kalsi -Chakrata
Bond Terminated.
|
Project: |
UEAP-RB |
UID: |
5401 |
Sanction Cost: |
341.00 lakh |
Length:
|
12.000 KM. |
District: |
Dehradun |
Block: |
Vikas Nagar |
Constituency: |
Chakrata |
Circle: |
|
DEA: |
DEA UEAP Uttarkashi |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design & Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1013
Package Name: 
UEAP/PWD/C11
Tender Date: 03-02-2014
Current Status: Agreement signed
Achieved on Date: 09-06-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C11
Contractor Name: Mathiyan Construction Pvt Ltd
|
Start Date: 30-06-2014
Intended Completion Date: 26-09-2015
|
Total Bond Cost: 53436503.32 (534.37 lakh)
Variation Cost: -44798837.32 (-447.99 lakh) Hence Total Bond Cost is 8637666 (86.38 lakh)
|
Sub Project Cost: 341.00 lakh
Variation Cost of Sub Project: -28669611.54 (-286.7 lakh)
Total Sub Project Cost:
54.3 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 4034418 for 151 days
LD Analysis for Milestone2: calculated LD is Rs 4034418 for 151 days
|
|
Component Wise Progress
|
No Physical Progress. |
Remarks:
No Remarks
Work Program Made On:
} ?>
Updation of work program on:
|
|
Work Program Status:Work Program Not Made Yet |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-November-2014 | 43.34 lakh | 2. | 05-November-2015 | 19.68 lakh |
Previous Package Expenditure Total |
63.02 lakh |
SNo. |
Date |
Payment |
1. | 26-November-2014 | 43.34 lakh | 2. | 05-November-2015 | 19.68 lakh |
Total |
63.02 lakh |
% Payment | 116.06 % |
|
Advance Amount: 53.44 lakh
Recovered Amount: 6.50 lakh
Balance to be Recovered 46.94 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported( Work program not made hence analysis may not be realistic). | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 36 No. of Test Done : 36 No. of Test Passed : 36 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.62 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 5 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 02-05-2015 | ch | dn | Deepak Yadav | SE | ADB Circle | See Pic |
2. | 22-09-2014 | Km 11 | Cement Concrete Pavement | Ashutosh Kumar | EE | DEA ADB Uttarkashi | See Pic |
3. | 22-09-2014 | Km 4 | Retaining Wall | Ashutosh Kumar | EE | DEA ADB Uttarkashi | See Pic |
4. | 03-09-2014 | Start point | Information board | Ashutosh Kumar | EE | DEA ADB Uttarkashi | See Pic |
5. | 03-09-2014 | Km 10 | Cement Concrete Pavement | Ashutosh Kumar | EE | DEA ADB Uttarkashi | See Pic |
|
|