Aglad Thatyur Motor Road (Chronic Slip Zone)
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5337 |
Sanction Cost: |
396.00 lakh |
Length:
|
0.200 KM. |
District: |
Tehri |
Block: |
Jaunpur |
Constituency: |
Dhanaulti |
Circle: |
|
DEA: |
DEA UEAP Tehri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1095
Package Name: 
UEAP/PWD/C91
Tender Date: 11-09-2015
Current Status: Agreement signed
Achieved on Date: 18-04-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C91
Contractor Name: Shiv Shankar Construction Company
|
Start Date: 12-05-2016
Intended Completion Date: 30-06-2017
Original End Date: 11-03-2017 |
Total Bond Cost: 37113251.2 (371.13 lakh)
Variation Cost: 5538382.15 (55.38 lakh) Hence Total Bond Cost is 42651633.35 (426.52 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 742280 for 40 days
LD Analysis for Milestone2: calculated LD is Rs 1020635 for 55 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.20 KM | 125.44 | 13-05-2016 | 31-12-2016 | 0.20 KM | 0.15 KM | 22.06 | 94.08 | 2. | R/Wall, B/ Wall Type Protection works | 200.00 m | 170.41 | 13-05-2016 | 30-06-2017 | 200.00 m | 200.00 m | 39.95 | 170.41 | 3. | Other Allied Works & Finishing Work | 4.00 Job | 130.67 | 13-05-2016 | 30-06-2017 | 4.00 Job | 2.00 Job | 15.32 | 65.33 |
Total Amount: |
426.52 |
|
77.33 |
329.82 |
|
Remarks:
No Remarks
Work Program Made On:
21-07-2017 } ?>
Updation of work program on:
31-07-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 05-October-2016 | 76.94 lakh | 2. | 01-December-2016 | 47.15 lakh | 3. | 28-March-2017 | 132.83 lakh | 4. | 07-June-2017 | 66.28 lakh | 5. | 19-July-2017 | 54.27 lakh | 6. | 31-August-2017 | 14.82 lakh | 7. | 25-September-2017 | 11.63 lakh |
Total |
403.92 lakh |
% Payment |
94.69 % |
|
Advance Amount: 37.00 lakh
Recovered Amount: 37.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
Staff not deputed yet
Environment & Social Compliances(Sub Project level):
No Pending Issue |
Detailed report of this subproject
|
|
Quality
|
Test Information not Available. |
Quality Ranking in %: 95.00 |
Number of Notice(s) issued: 48 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 37 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 07-09-2017 | Part a | Site condition | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
2. | 07-09-2017 | Part a | Present site condition | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
3. | 07-09-2017 | A Part | Site visit by se sir and THDC team | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
4. | 07-09-2017 | A Part | Present site condition of site | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
5. | 07-09-2017 | A Part | SMRD silip clearances | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
6. | 07-09-2017 | A Part | Bb | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
7. | 07-09-2017 | R | Hy | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
8. | 26-07-2017 | A Part | THDC site visit c-91 | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
9. | 17-07-2017 | A part | SRMD,Site Clearance part 'A' | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
10. | 17-07-2017 | Part A | SRMD,Site clearance part 'A' | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
11. | 17-07-2017 | Part A | SRMD,Site Clearance part 'A' | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
12. | 09-06-2017 | Part a | 3d net | Amit Kumar 2 | AE | UDRP AF S&B Bageshwar | See Pic |
13. | 09-06-2017 | Part b | Breast wall | Amit Kumar 2 | AE | UDRP AF S&B Bageshwar | See Pic |
14. | 09-06-2017 | Part b | Gabion laying | Amit Kumar 2 | AE | UDRP AF S&B Bageshwar | See Pic |
15. | 17-05-2017 | A part | 3D net | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
16. | 17-05-2017 | A part | Gabions wall | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
17. | 17-05-2017 | A part | Site visit C 91THDC Team | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
18. | 17-05-2017 | B part | site visit C-91 THDC team | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
19. | 17-05-2017 | A part | 3D net | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
20. | 17-05-2017 | B part | B/w | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
|
|