Internal Motor Road of Nagar Palika Tehri (Tehri to Baurari)
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5336 |
Sanction Cost: |
600.00 lakh |
Length:
|
10.500 KM. |
District: |
Tehri |
Block: |
Chamba |
Constituency: |
Tehri |
Circle: |
|
DEA: |
DEA UEAP Tehri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Urban |
|
Procurement: |
Package No.: 1084
Package Name: 
UEAP/PWD/C-80
Tender Date: 14-08-2015
Current Status: Agreement signed
Achieved on Date: 30-12-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C-80
Contractor Name: Maa Bhagwati Construction company
|
Start Date: 21-01-2016
Intended Completion Date: 30-05-2017
Original End Date: 20-06-2017 |
Total Bond Cost: 50455815.4 (504.56 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 832524 for 33 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.54 KM | 5.68 | 15-03-2016 | 20-04-2016 | 1.54 KM | 1.54 KM | 1.13 | 5.68 | 2. | G-2 | 2.48 KM | 11.90 | 15-05-2016 | 15-10-2016 | 2.48 KM | 2.48 KM | 2.36 | 11.90 | 3. | G-3 | 2.48 KM | 11.90 | 25-05-2016 | 15-10-2016 | 2.48 KM | 2.48 KM | 2.36 | 11.90 | 4. | PC/CC i/c Prime Coat, Tack Coat | 1.13 KM | 53.97 | 01-03-2016 | 15-11-2016 | 1.13 KM | 1.13 KM | 10.7 | 53.97 | 5. | BM i/c Prime Coat, Tack Coat | 7.88 KM | 175.50 | 04-06-2016 | 15-11-2016 | 7.88 KM | 7.88 KM | 34.78 | 175.50 | 6. | SDBC i/c Tackcoat | 7.88 KM | 130.95 | 06-06-2016 | 16-11-2016 | 7.88 KM | 7.88 KM | 25.95 | 130.95 | 7. | longitudinal Drain | 4000.00 m | 13.83 | 15-07-2016 | 15-05-2017 | 4000.00 m | 0.00 m | 0 | 0.00 | 8. | Crash Barrier | 600.00 m | 13.20 | 15-08-2016 | 20-08-2016 | 600.00 m | 600.00 m | 2.62 | 13.20 | 9. | Parapet | 250.00 No | 7.56 | 15-09-2016 | 20-05-2017 | 250.00 No | 230.00 No | 1.38 | 6.96 | 10. | Road Furniture | 640.00 No | 24.52 | 31-12-2016 | 30-05-2017 | 640.00 No | 630.00 No | 4.78 | 24.14 | 11. | Other Allied Works & Finishing Work | 1.00 Job | 55.55 | 20-07-2016 | 30-05-2017 | 1.00 Job | 1.00 Job | 11.01 | 55.55 |
Total Amount: |
504.56 |
|
97.06 |
489.75 |
|
Remarks:
No Remarks
Work Program Made On:
06-09-2016 } ?>
Updation of work program on:
21-07-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 24-June-2016 | 74.38 lakh | 2. | 24-August-2016 | 40.26 lakh | 3. | 25-October-2016 | 83.51 lakh | 4. | 25-November-2016 | 104.02 lakh | 5. | 28-February-2017 | 35.95 lakh | 6. | 26-May-2017 | 33.09 lakh | 7. | 18-June-2017 | 18.10 lakh | 8. | 05-September-2017 | 34.82 lakh |
Total |
424.13 lakh |
% Payment |
84.07 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
Staff not deputed yet
Environment & Social Compliances(Sub Project level):
No Pending Issue |
Detailed report of this subproject
|
|
Quality
|
Test Information not Available. |
Quality Ranking in %: 90.14 |
Number of Notice(s) issued: 47 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 10 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 22-05-2017 | 0+020 | Construction of parapets | Sugandh Singh Saini | JE | UEAP R&B Tehri | See Pic |
2. | 19-05-2017 | 0+485 | Interlocking tiles work | Sugandh Singh Saini | JE | UEAP R&B Tehri | See Pic |
3. | 19-05-2017 | 0+485 | Interlocking tiles work | Sugandh Singh Saini | JE | UEAP R&B Tehri | See Pic |
4. | 30-03-2017 | 3+00 | Interlocking tile work in progress | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
5. | 20-03-2017 | 3+075 | Interlocking tiles work | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
6. | 20-03-2017 | 3+100 | Interlocking tiels work progress | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
7. | 17-03-2017 | 2+625 | Interlocking tiles work | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
8. | 17-03-2017 | 2+725 | Interlocking tile work | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
9. | 07-03-2017 | 0+240 | Interlocking tile work | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
10. | 07-03-2017 | 0+200 | Interlocking tiles work | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
|
|