Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Internal Motor Road of Muni Ki Reti & Tapowan Area Work Completed
Project: UEAP-RB UID: 5335 Sanction Cost: 550.00  lakh Length: 4.150 KM.
District: Tehri Block: Narendra Nagar Constituency: Narendra Nagar Circle:
DEA: DEA UEAP Tehri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Urban
Procurement:
Package No.: 1083        Package Name:  UEAP/PWD/C-79        Tender Date: 14-08-2015        Current Status: Agreement signed        Achieved on Date: 30-12-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C-79      Contractor Name: Maa Bhagwati Construction company
Start Date:  21-01-2016      Intended Completion Date:  30-05-2017      Original End Date:  20-06-2017
Total Bond Cost: 47565125.5 (475.65 lakh)       
LD Analysis for Milestone1: calculated LD is Rs 2853960 for 120 days        LD Analysis for Milestone2: calculated LD is Rs 4114459 for 173 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works550.00 m13.3515-03-201615-06-2016550.00 m550.00 m2.8113.35
2.G-21.91 KM34.0801-09-201615-05-20171.91 KM1.91 KM7.1734.08
3.G-31.91 KM21.5405-09-201616-05-20171.91 KM1.91 KM4.5321.54
4.PC/CC i/c Prime Coat, Tack Coat6.20 KM3.1515-11-201615-12-20166.20 KM6.20 KM0.663.15
5.BM i/c Prime Coat, Tack Coat2.40 KM37.8305-09-201615-12-20161.20 KM1.20 KM7.9537.83
6.SDBC i/c Tackcoat3.80 KM105.0610-09-201615-12-20163.42 KM3.42 KM22.09105.06
7.longitudinal Drain1100.00 m160.5315-03-201630-10-20161100.00 m1100.00 m33.75160.53
8.Road Furniture117.00 No11.4231-12-201630-05-2017117.00 No117.00 No2.411.42
9.Other Allied Works & Finishing Work 1.00 Job88.7020-07-201630-05-20171.00 Job1.00 Job18.6588.70
Total Amount: 475.66 100   475.66
Remarks: No Remarks       Work Program Made On: 06-09-2016        Updation of work program on: 13-07-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-August-201626.58  lakh
2.21-December-2016129.30  lakh
3.28-February-201740.33  lakh
4.17-June-201749.45  lakh
5.27-June-201745.96  lakh
6.31-August-201720.74  lakh
7.28-September-201743.95  lakh
Total 356.31  lakh
% Payment 74.91 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
Test Information not Available.
Quality Ranking in %: 97.86
Number of Notice(s) issued: 47

Mobile Pic Upload

Number of Pics Available on Web Repository: 22
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.04-03-20171.350P.c.c layingAmit Kumar 2AEUDRP AF S&B Bageshwar See Pic
2.21-02-20171.550Tiles layingAmit Kumar 2AEUDRP AF S&B Bageshwar See Pic
3.21-02-20171.625Tiles layingAmit Kumar 2AEUDRP AF S&B Bageshwar See Pic
4.21-02-20171.600ConcretingAmit Kumar 2AEUDRP AF S&B Bageshwar See Pic
5.03-02-2017Ch.1+580Core cutting on BCAsha RawatJEUEAP R&B Tehri See Pic
6.03-02-2017Ch.1+710Core cuttingAsha RawatJEUEAP R&B Tehri See Pic
7.05-12-20160+550Visit by Exn sir on C-79 pkg at Laxman jhulhaShivendra PrakashAEUEAP- CA Tehri See Pic
8.05-12-20160+750Visit by Exn sir on C-79 pkg at Laxman jhulhaShivendra PrakashAEUEAP- CA Tehri See Pic
9.05-12-20160+870Finishing work of BM at Laxman jhulaShivendra PrakashAEUEAP- CA Tehri See Pic
10.05-12-20160+850Compaction on BM work at Laxman JhulhaShivendra PrakashAEUEAP- CA Tehri See Pic
11.05-12-20160+850Measure thickness of BM & found satisfactory at Laxman JhulhaShivendra PrakashAEUEAP- CA Tehri See Pic
12.05-12-20160+900Compaction on BM at Laxman jhulhaShivendra PrakashAEUEAP- CA Tehri See Pic
13.05-12-20160+900Laying of BM at laxman jhulhaShivendra PrakashAEUEAP- CA Tehri See Pic
14.05-12-20160+900Spreading tackcoat for BM work at Laxman jhulhaShivendra PrakashAEUEAP- CA Tehri See Pic
15.28-11-20161+570Finishingof BC workShivendra PrakashAEUEAP- CA Tehri See Pic
16.28-11-20161+550Laying of BC workShivendra PrakashAEUEAP- CA Tehri See Pic
17.28-11-20161+500Rolling on BC workShivendra PrakashAEUEAP- CA Tehri See Pic
18.28-11-20160+800Spreading Tack coat for BC workShivendra PrakashAEUEAP- CA Tehri See Pic
19.25-11-20162+350BC work is going on start from bhadrakaliShivendra PrakashAEUEAP- CA Tehri See Pic
20.23-11-20165+200Laying BCAsha RawatJEUEAP R&B Tehri See Pic