Nainbag-Ghudakhuri-Andi Motor Road
Work Completed
|
Project: |
UEAP-RB |
UID: |
5334 |
Sanction Cost: |
870.00 lakh |
Length:
|
KM. |
District: |
Tehri |
Block: |
Jaunpur |
Constituency: |
Dhanaulti |
Circle: |
|
DEA: |
DEA UEAP Tehri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1073
Package Name: 
UEAP/PWD/C69
Tender Date: 16-10-2014
Current Status: Agreement signed
Achieved on Date: 13-02-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C69
Contractor Name: Dwarika Projects Limited
|
Start Date: 05-03-2015
Intended Completion Date: 04-09-2016
|
Total Bond Cost: 75068982 (750.69 lakh)
Variation Cost: 23589316.81 (235.89 lakh) Hence Total Bond Cost is 98658298.81 (986.58 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 788214 for 21 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 21.00 KM | 29.31 | 01-04-2015 | 31-01-2016 | 1.33 KM | 1.33 KM | 3.1 | 29.31 | 2. | R/Wall, B/ Wall Type Protection works | 1610.00 m | 227.65 | 01-06-2015 | 31-05-2016 | 1296.00 m | 1296.00 m | 24.05 | 227.65 | 3. | G-2 | 1.35 KM | 14.54 | 16-05-2015 | 31-05-2016 | 1.35 KM | 1.35 KM | 1.54 | 14.54 | 4. | G-3 | 1.64 KM | 15.85 | 16-05-2015 | 31-01-2016 | 1.64 KM | 1.64 KM | 1.68 | 15.85 | 5. | BM i/c Prime Coat, Tack Coat | 20.85 KM | 169.84 | 05-09-2015 | 31-05-2016 | 20.85 KM | 20.85 KM | 17.95 | 169.84 | 6. | SDBC i/c Tackcoat | 20.85 KM | 312.31 | 10-09-2015 | 31-05-2016 | 20.85 KM | 20.85 KM | 33 | 312.31 | 7. | Cause Way | 8.00 No | 12.77 | 01-07-2015 | 31-05-2016 | 7.00 No | 7.00 No | 1.35 | 12.77 | 8. | Culverts/Scupper | 4.00 No | 9.15 | 01-07-2015 | 01-12-2015 | 4.00 No | 4.00 No | 0.97 | 9.15 | 9. | longitudinal Drain | 16362.00 m | 95.12 | 01-07-2015 | 31-05-2016 | 15655.00 m | 15655.00 m | 10.05 | 95.12 | 10. | Crash Barrier | 150.00 m | 4.80 | 01-03-2016 | 30-06-2016 | 150.00 m | 150.00 m | 0.51 | 4.80 | 11. | Parapet | 688.00 No | 22.75 | 01-08-2015 | 01-10-2015 | 1122.00 No | 1122.00 No | 2.4 | 22.75 | 12. | Road Furniture | 1312.00 No | 30.31 | 01-03-2016 | 15-08-2016 | 1311.00 No | 1311.00 No | 3.2 | 30.31 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 2.03 | 14-04-2015 | 15-08-2016 | 1.00 Job | 1.00 Job | 0.21 | 2.03 |
Total Amount: |
946.43 |
|
100 |
946.43 |
|
Remarks:
No Remarks
Work Program Made On:
04-09-2015 } ?>
Updation of work program on:
12-09-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-June-2015 | 46.71 lakh | 2. | 26-August-2015 | 55.32 lakh | 3. | 13-October-2015 | 75.99 lakh | 4. | 04-November-2015 | 89.73 lakh | 5. | 30-December-2015 | 125.51 lakh | 6. | 28-March-2016 | 70.69 lakh | 7. | 10-May-2016 | 239.45 lakh | 8. | 22-June-2016 | 189.95 lakh | 9. | 28-July-2016 | 27.70 lakh | 10. | 22-July-2017 | 65.26 lakh |
Total |
986.31 lakh |
% Payment |
99.97 % |
|
Advance Amount: 165.49 lakh
Recovered Amount: 165.49 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
Test Information not Available. |
Quality Ranking in %: 90.44 |
Number of Notice(s) issued: 75 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 13 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 06-10-2015 | Plant lab in km 5+700 from nainbaag. | Binder content test for BC. | Asha rawat | JE | DEA ADB Dehradun | See Pic |
2. | 31-07-2015 | 22.500 | R.W. Completed | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
3. | 31-07-2015 | 17.800 | Causeway completed | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
4. | 29-07-2015 | 2.800 | R/W Joint mts. are being taken | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
5. | 18-05-2015 | Km 29.900 | R/w completed | Shankar Ram | SE | ADB Circle | See Pic |
6. | 18-05-2015 | Km 19.250 | Constn of causeway is in progress | Shankar Ram | SE | ADB Circle | See Pic |
7. | 18-05-2015 | Km 5.525 | B/w is in progress | Shankar Ram | SE | ADB Circle | See Pic |
8. | 18-05-2015 | B/w in km 4.585 completed | B/w completed | Shankar Ram | SE | ADB Circle | See Pic |
9. | 18-05-2015 | Km 3.975 | R/w and b/w completed | Shankar Ram | SE | ADB Circle | See Pic |
10. | 18-05-2015 | Km 2.900 | R/w in km2.9 is in progress | Shankar Ram | SE | ADB Circle | See Pic |
11. | 15-04-2015 | ch 22.500 | culvert abutment damaged | Deepak Yadav | SE | ADB Circle | See Pic |
12. | 15-04-2015 | ch 17.800 | causeway under construction | Deepak Yadav | SE | ADB Circle | See Pic |
13. | 14-04-2015 | Km 17.800 | Excavation for causeway is in progress | Shankar Ram | SE | ADB Circle | See Pic |
|
|