Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Nainbag-Ghudakhuri-Andi Motor Road Work Completed
Project: UEAP-RB UID: 5334 Sanction Cost: 870.00  lakh Length: KM.
District: Tehri Block: Jaunpur Constituency: Dhanaulti Circle:
DEA: DEA UEAP Tehri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: MDR
Procurement:
Package No.: 1073        Package Name:  UEAP/PWD/C69        Tender Date: 16-10-2014        Current Status: Agreement signed        Achieved on Date: 13-02-2015

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C69      Contractor Name: Dwarika Projects Limited
Start Date:  05-03-2015      Intended Completion Date:  04-09-2016     
Total Bond Cost: 75068982 (750.69 lakh)        Variation Cost: 23589316.81 (235.89 lakh)    Hence Total Bond Cost is   98658298.81 (986.58 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 788214 for 21 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence21.00 KM29.3101-04-201531-01-20161.33 KM1.33 KM3.129.31
2.R/Wall, B/ Wall Type Protection works1610.00 m227.6501-06-201531-05-20161296.00 m1296.00 m24.05227.65
3.G-21.35 KM14.5416-05-201531-05-20161.35 KM1.35 KM1.5414.54
4.G-31.64 KM15.8516-05-201531-01-20161.64 KM1.64 KM1.6815.85
5.BM i/c Prime Coat, Tack Coat20.85 KM169.8405-09-201531-05-201620.85 KM20.85 KM17.95169.84
6.SDBC i/c Tackcoat20.85 KM312.3110-09-201531-05-201620.85 KM20.85 KM33312.31
7.Cause Way8.00 No12.7701-07-201531-05-20167.00 No7.00 No1.3512.77
8.Culverts/Scupper 4.00 No9.1501-07-201501-12-20154.00 No4.00 No0.979.15
9.longitudinal Drain16362.00 m95.1201-07-201531-05-201615655.00 m15655.00 m10.0595.12
10.Crash Barrier150.00 m4.8001-03-201630-06-2016150.00 m150.00 m0.514.80
11.Parapet688.00 No22.7501-08-201501-10-20151122.00 No1122.00 No2.422.75
12.Road Furniture1312.00 No30.3101-03-201615-08-20161311.00 No1311.00 No3.230.31
13.Other Allied Works & Finishing Work 1.00 Job2.0314-04-201515-08-20161.00 Job1.00 Job0.212.03
Total Amount: 946.43 100   946.43
Remarks: No Remarks       Work Program Made On: 04-09-2015        Updation of work program on: 12-09-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.26-June-201546.71  lakh
2.26-August-201555.32  lakh
3.13-October-201575.99  lakh
4.04-November-201589.73  lakh
5.30-December-2015125.51  lakh
6.28-March-201670.69  lakh
7.10-May-2016239.45  lakh
8.22-June-2016189.95  lakh
9.28-July-201627.70  lakh
10.22-July-201765.26  lakh
Total 986.31  lakh
% Payment 99.97 %
Advance Amount:  165.49  lakh        Recovered Amount:  165.49  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
Test Information not Available.
Quality Ranking in %: 90.44
Number of Notice(s) issued: 75

Mobile Pic Upload

Number of Pics Available on Web Repository: 13
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.06-10-2015Plant lab in km 5+700 from nainbaag.Binder content test for BC.Asha rawatJEDEA ADB Dehradun See Pic
2.31-07-201522.500R.W. CompletedAnuj Kumar SinghAEUEAP R&B Tehri See Pic
3.31-07-201517.800Causeway completedAnuj Kumar SinghAEUEAP R&B Tehri See Pic
4.29-07-20152.800R/W Joint mts. are being takenAnuj Kumar SinghAEUEAP R&B Tehri See Pic
5.18-05-2015Km 29.900R/w completedShankar Ram SEADB Circle See Pic
6.18-05-2015Km 19.250Constn of causeway is in progressShankar Ram SEADB Circle See Pic
7.18-05-2015Km 5.525B/w is in progressShankar Ram SEADB Circle See Pic
8.18-05-2015B/w in km 4.585 completedB/w completedShankar Ram SEADB Circle See Pic
9.18-05-2015Km 3.975R/w and b/w completedShankar Ram SEADB Circle See Pic
10.18-05-2015Km 2.900R/w in km2.9 is in progressShankar Ram SEADB Circle See Pic
11.15-04-2015ch 22.500culvert abutment damagedDeepak YadavSEADB Circle See Pic
12.15-04-2015ch 17.800causeway under constructionDeepak YadavSEADB Circle See Pic
13.14-04-2015Km 17.800Excavation for causeway is in progressShankar Ram SEADB Circle See Pic