Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bhaldina-Lambgaon Motor Road Work Completed
Project: UEAP-RB UID: 5333 Sanction Cost: 898.00  lakh Length: 16.000 KM.
District: Tehri Block: Pratapnagar Constituency: Pratapnagar Circle:
DEA: DEA UEAP Tehri DSC: DSC Scope: Design and Supervision Type: MDR
Procurement:
Package No.: 1072        Package Name:  UEAP/PWD/C68        Tender Date: 16-10-2014        Current Status: Agreement signed        Achieved on Date: 13-02-2015

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C68      Contractor Name: ESPAN Infrastructure Ltd
Start Date:  05-03-2015      Intended Completion Date:  04-09-2016     
Total Bond Cost: 76631713 (766.32 lakh)       
LD Analysis for Milestone1: calculated LD is Rs 7011828 for +183 days        LD Analysis for Milestone2: calculated LD is Rs 4904448 for 128 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence2.10 KM6.5701-04-201531-05-20152.10 KM2.10 KM1.016.57
2.R/Wall, B/ Wall Type Protection works1115.00 m146.7701-06-201531-10-20161115.00 m1115.00 m22.5146.77
3.G-26.28 KM43.2716-05-201515-07-20156.28 KM6.28 KM6.6343.27
4.G-36.28 KM44.1501-01-201629-02-20166.28 KM6.28 KM6.7744.15
5.BM i/c Prime Coat, Tack Coat8.75 KM212.5601-10-201515-11-20158.75 KM8.75 KM32.58212.56
6.SDBC i/c Tackcoat17.02 KM137.2101-04-201630-06-201617.02 KM17.02 KM21.03137.21
7.Cause Way1.00 No7.6901-06-201531-07-20151.00 No1.00 No1.187.69
8.Crash Barrier500.00 m16.0001-05-201631-07-2016500.00 m500.00 m2.4516.00
9.Parapet638.00 No28.3701-02-201631-07-2016638.00 No638.00 No4.3528.37
10.Road Furniture500.00 No9.7801-05-201631-07-2016500.00 No500.00 No1.59.78
Total Amount: 652.37 100   652.37
Remarks: No Remarks       Work Program Made On: 06-08-2015        Updation of work program on: 11-09-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.24-March-20150.16  lakh
2.20-June-201514.36  lakh
3.26-August-201520.68  lakh
4.08-October-201537.37  lakh
5.09-February-201618.92  lakh
6.29-March-201625.64  lakh
7.02-June-201625.61  lakh
8.24-June-2016172.07  lakh
9.12-July-201671.85  lakh
10.06-September-201634.62  lakh
11.28-March-2017148.38  lakh
12.29-March-2017168.33  lakh
13.04-May-201735.83  lakh
14.29-July-201726.19  lakh
15.29-September-201730.92  lakh
Total 830.93  lakh
% Payment 108.44 %
Advance Amount:  152.22  lakh        Recovered Amount:  152.22  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 904   No. of Test Done : 996    No. of Test Passed : 904   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.66
Number of Notice(s) issued: 68

Mobile Pic Upload

Number of Pics Available on Web Repository: 2
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.01-04-201713+600Core cuttingRoshan Singh RanaJEUEAP R&B Tehri See Pic
2.18-03-20179+800Cross barier inspectionRoshan Singh RanaJEUEAP R&B Tehri See Pic