Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Tyuni-Chakrata-Mussoorie-Chamba-Tehri-Kritinagar Motor Road Agreement signed
Project: UEAP-RB UID: 5332 Sanction Cost: 920.00  lakh Length: 24.000 KM.
District: Tehri Block: Chamba Constituency: Tehri Circle:
DEA: DEA UEAP Tehri DSC: DSC Scope: Design and Supervision Type: SH
Procurement:
Package No.: 1071        Package Name:  UEAP/PWD/C67        Tender Date: 16-10-2014        Current Status: Agreement signed        Achieved on Date: 25-02-2015

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C67      Contractor Name: SS Infratech
Start Date:  19-03-2015      Intended Completion Date:  06-09-2016     
Total Bond Cost: 68577981.3 (685.78 lakh)       
LD Analysis for Milestone1: calculated LD is Rs 6137731 for +179 days        LD Analysis for Milestone2: calculated LD is Rs 6137731 for +179 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence9.54 KM6.9101-08-201505-09-20159.54 KM9.54 KM0.916.91
2.R/Wall, B/ Wall Type Protection works900.00 m126.7615-07-201515-11-2015900.00 m900.00 m16.7126.76
3.GSB/RBI/G-10.30 KM4.3701-09-201501-10-20150.30 KM0.00 KM00.00
4.G-20.40 KM23.5915-08-201530-09-20150.40 KM0.32 KM2.4918.87
5.G-30.40 KM25.3020-08-201505-10-20150.40 KM0.32 KM2.6720.24
6.BM i/c Prime Coat, Tack Coat6.14 KM168.5310-09-201525-04-20166.14 KM6.14 KM22.2168.53
7.SDBC i/c Tackcoat6.14 KM134.9215-09-201525-04-20166.14 KM6.14 KM17.77134.92
8.Cause Way5.00 No11.8415-08-201501-11-20155.00 No3.00 No0.947.11
9.longitudinal Drain3585.00 m67.3220-08-201525-12-20153585.00 m2115.00 m5.2339.71
10.Crash Barrier500.00 m150.0110-12-201520-02-2016500.00 m500.00 m19.76150.01
11.Parapet450.00 No22.2915-10-201520-02-2016450.00 No370.00 No2.4118.33
12.Road Furniture1321.00 No17.3804-09-201525-08-20161321.00 No1200.00 No2.0815.79
Total Amount: 759.22 93.15   707.18
Remarks: No Remarks       Work Program Made On: 04-09-2015        Updation of work program on: 09-01-2017       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.16-September-201541.59  lakh
2.06-November-201524.17  lakh
3.05-March-201634.53  lakh
4.05-May-201622.02  lakh
5.15-June-201644.69  lakh
6.29-June-201634.90  lakh
7.19-August-201632.99  lakh
8.27-October-201687.72  lakh
9.09-December-201640.16  lakh
10.30-December-201647.45  lakh
11.08-March-201727.61  lakh
12.21-June-201728.42  lakh
13.24-September-201721.93  lakh
Total 488.18  lakh
% Payment 71.19 %
Advance Amount:  60.00  lakh        Recovered Amount:  60.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles
Environment & Social Compliances(Sub Project level): Sanitation Facility, Query, Borrow pits, DG set
Detailed report of this subproject
Quality
No. of Test Required : 734   No. of Test Done : 753    No. of Test Passed : 730   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.17
Number of Notice(s) issued: 68

Mobile Pic Upload

Number of Pics Available on Web Repository: 27
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.06-05-201739+180Tharmoplast paint lining work in progresKishan Singh RawatJEUEAP R&B Tehri See Pic
2.06-05-201739+00Tharmoplast paint liningKishan Singh RawatJEUEAP R&B Tehri See Pic
3.04-05-201731+900Base of causewayKishan Singh RawatJEUEAP R&B Tehri See Pic
4.17-03-201734+600Delineator work in progresKishan Singh RawatJEUEAP R&B Tehri See Pic
5.21-12-201628+600Laying of BC workShivendra PrakashAEUEAP- CA Tehri See Pic
6.21-12-201628+550Spreading tack coat for BC workShivendra PrakashAEUEAP- CA Tehri See Pic
7.21-12-201628+600Finishing surface of BC workShivendra PrakashAEUEAP- CA Tehri See Pic
8.21-12-201628+525Rolling on BC worksShivendra PrakashAEUEAP- CA Tehri See Pic
9.11-11-201639+200Finishing surface of BC worksShivendra PrakashAEUEAP- CA Tehri See Pic
10.11-11-201639+250Finishing surface of BC workShivendra PrakashAEUEAP- CA Tehri See Pic
11.11-11-201639+250Rolling on BC workShivendra PrakashAEUEAP- CA Tehri See Pic
12.10-11-201639+250Laying of BC workShivendra PrakashAEUEAP- CA Tehri See Pic
13.10-11-201638+600Finishing surface of BM workShivendra PrakashAEUEAP- CA Tehri See Pic
14.10-11-201638+600Measure thickness & found satisfactoryShivendra PrakashAEUEAP- CA Tehri See Pic
15.10-11-201636+600Compaction by RollarShivendra PrakashAEUEAP- CA Tehri See Pic
16.10-11-201638+600Laying of BM work is in progressShivendra PrakashAEUEAP- CA Tehri See Pic
17.10-11-201638+600Tack coat for BM workShivendra PrakashAEUEAP- CA Tehri See Pic
18.07-10-201636+850 pkg C-67Spreading lime on finishing surface of BC workShivendra PrakashAEUEAP- CA Tehri See Pic
19.07-10-201636+850 pkg C-67Finishing of the BC workShivendra PrakashAEUEAP- CA Tehri See Pic
20.07-10-201636+850 pkg C-67Laying of BC work..Shivendra PrakashAEUEAP- CA Tehri See Pic