Tehri-Hindolakhal-Devprayag Motor Road
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5331 |
Sanction Cost: |
295.00 lakh |
Length:
|
KM. |
District: |
Tehri |
Block: |
Devaprayag |
Constituency: |
Deoprayag |
Circle: |
|
DEA: |
DEA UEAP Tehri |
DSC: |
|
DSC Scope: |
Design and Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1063
Package Name: 
UEAP/PWD/C59
Tender Date: 20-09-2014
Current Status: Agreement signed
Achieved on Date: 13-04-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C59
Contractor Name: Maa Bhagwati Construction company
|
Start Date: 19-03-2015
Intended Completion Date: 06-09-2016
|
Total Bond Cost: 84181618.77 (841.82 lakh)
Variation Cost: 8055000.74 (80.55 lakh) Hence Total Bond Cost is 92236619.51 (922.37 lakh)
|
Sub Project Cost: 262.97 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 4335373 for 103 days
LD Analysis for Milestone2: calculated LD is Rs 5219284 for +124 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 3.18 KM | 7.57 | 20-08-2015 | 30-10-2015 | 3.18 KM | 3.18 KM | 3.46 | 7.57 | 2. | R/Wall, B/ Wall Type Protection works | 1600.00 m | 72.68 | 05-08-2015 | 30-04-2016 | 730.00 m | 730.00 m | 33.19 | 72.68 | 3. | G-2 | 0.20 KM | 1.34 | 07-10-2015 | 20-10-2015 | 0.20 KM | 0.00 KM | 0 | 0.00 | 4. | G-3 | 0.20 KM | 1.37 | 15-10-2015 | 25-10-2015 | 0.20 KM | 0.00 KM | 0 | 0.00 | 5. | BM i/c Prime Coat, Tack Coat | 1.70 KM | 34.04 | 20-10-2015 | 20-11-2015 | 2.00 KM | 1.83 KM | 14.22 | 31.14 | 6. | SDBC i/c Tackcoat | 2.02 KM | 27.03 | 26-10-2015 | 25-11-2015 | 2.00 KM | 1.83 KM | 11.29 | 24.73 | 7. | Cause Way | 3.00 No | 5.96 | 15-09-2015 | 30-01-2016 | 4.00 No | 4.00 No | 2.72 | 5.96 | 8. | longitudinal Drain | 1920.00 m | 34.79 | 15-10-2015 | 30-08-2016 | 2920.00 m | 2920.00 m | 15.89 | 34.79 | 9. | Crash Barrier | 450.00 m | 9.68 | 01-10-2015 | 02-02-2017 | 0.45 m | 0.45 m | 4.42 | 9.68 | 10. | Parapet | 190.00 No | 5.11 | 15-10-2015 | 01-02-2017 | 143.00 No | 80.00 No | 1.31 | 2.86 | 11. | Road Furniture | 861.00 No | 8.53 | 20-12-2015 | 01-02-2017 | 861.00 No | 666.00 No | 3.01 | 6.60 | 12. | Other Allied Works & Finishing Work | 1.00 Job | 10.88 | 30-01-2016 | 28-02-2016 | 1.00 Job | 1.00 Job | 4.97 | 10.88 |
Total Amount: |
218.98 |
|
94.48 |
206.89 |
|
Remarks:
No Remarks
Work Program Made On:
31-07-2015 } ?>
Updation of work program on:
03-08-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 13-October-2015 | 28.18 lakh | 2. | 20-January-2016 | 48.41 lakh | 3. | 17-March-2016 | 17.68 lakh | 4. | 16-June-2016 | 4.43 lakh | 5. | 05-October-2016 | 3.13 lakh | 6. | 25-November-2016 | 99.64 lakh | 7. | 10-March-2017 | 24.18 lakh | 8. | 26-May-2017 | 28.63 lakh | 9. | 18-June-2017 | 6.70 lakh | 10. | 19-September-2017 | 22.44 lakh | 11. | 24-September-2017 | 37.56 lakh |
Total |
320.98 lakh |
% Payment | 122.06 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
PUC vehicles
Environment & Social Compliances(Sub Project level):
Sanitation Facility, Borrow pits, DG set |
Detailed report of this subproject
|
|
Quality
|
No. of Test Required : 588 No. of Test Done : 613 No. of Test Passed : 588 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.89 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 15 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 25-10-2016 | 38+450 | Sprading Tack coat for BM work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
2. | 25-10-2016 | 37+835 | Laying of BM work is in progress | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
3. | 25-10-2016 | 37+825 | Compaction of BM work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
4. | 25-10-2016 | 37+825 | Measure thickness of BM & found satisfactory | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
5. | 25-10-2016 | 37+800 | Laying of BM work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
6. | 25-10-2016 | 32+640 | Laying of BM work is in progress | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
7. | 25-10-2016 | 32+625 | Compaction of BM work is in progress | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
8. | 25-10-2016 | 31+400 | Tack coat is in progress for BM work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
9. | 25-10-2016 | 31+300 | Compaction by roller on BM work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
10. | 25-10-2016 | 31+300 | Measure thickness of BM & found satisfactory | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
11. | 25-10-2016 | 31+300 | Laying of BM is in progress | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
12. | 25-10-2016 | 31+350 | Tack coat for BM work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
13. | 25-10-2016 | 31+200 | Compaction by Rollar on BM work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
14. | 08-04-2016 | Hindolakhal Devprag motor marg 56+200 | Parapet work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
15. | 08-04-2016 | 59B chainage 56+200 | Parapet work has started | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
|
|