Tehri-Hindolakhal-Devprayag Motor Road (ic Tipri Roaddhar Motor Road)
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5330 |
Sanction Cost: |
695.00 lakh |
Length:
|
KM. |
District: |
Tehri |
Block: |
Jakhanidhar |
Constituency: |
Tehri |
Circle: |
|
DEA: |
DEA UEAP Tehri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1063
Package Name: 
UEAP/PWD/C59
Tender Date: 20-09-2014
Current Status: Agreement signed
Achieved on Date: 13-04-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C59
Contractor Name: Maa Bhagwati Construction company
|
Start Date: 19-03-2015
Intended Completion Date: 06-09-2016
|
Total Bond Cost: 84181618.77 (841.82 lakh)
Variation Cost: 8055000.74 (80.55 lakh) Hence Total Bond Cost is 92236619.51 (922.37 lakh)
|
Sub Project Cost: 578.85 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 4335373 for 103 days
LD Analysis for Milestone2: calculated LD is Rs 5219284 for +124 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.21 KM | 1.48 | 15-07-2015 | 15-10-2015 | 1.21 KM | 1.21 KM | 0.45 | 1.48 | 2. | R/Wall, B/ Wall Type Protection works | 2180.00 m | 7.87 | 15-07-2015 | 30-06-2016 | 2180.00 m | 2180.00 m | 2.41 | 7.87 | 3. | G-2 | 0.30 KM | 2.01 | 01-09-2015 | 15-09-2015 | 0.30 KM | 0.00 KM | 0 | 0.00 | 4. | G-3 | 0.30 KM | 2.01 | 05-09-2015 | 20-09-2015 | 0.03 KM | 0.03 KM | 0.62 | 2.01 | 5. | BM i/c Prime Coat, Tack Coat | 3.44 KM | 93.93 | 15-09-2015 | 25-09-2015 | 3.44 KM | 3.44 KM | 28.71 | 93.93 | 6. | SDBC i/c Tackcoat | 3.44 KM | 70.31 | 26-09-2015 | 07-10-2015 | 3.44 KM | 3.44 KM | 21.49 | 70.31 | 7. | Cause Way | 9.00 No | 23.85 | 01-09-2015 | 30-11-2015 | 9.00 No | 2.00 No | 1.62 | 5.30 | 8. | longitudinal Drain | 2500.00 m | 91.78 | 15-08-2015 | 31-12-2015 | 2500.00 m | 2500.00 m | 28.05 | 91.78 | 9. | Crash Barrier | 280.00 m | 6.02 | 15-09-2015 | 30-09-2015 | 280.00 m | 280.00 m | 1.84 | 6.02 | 10. | Parapet | 360.00 No | 13.11 | 15-10-2015 | 31-12-2015 | 360.00 No | 246.00 No | 2.74 | 8.96 | 11. | Road Furniture | 1166.00 No | 14.79 | 15-11-2015 | 30-06-2016 | 1166.00 No | 1046.00 No | 4.06 | 13.27 |
Total Amount: |
327.16 |
|
91.98 |
300.93 |
|
Remarks:
No Remarks
Work Program Made On:
31-07-2015 } ?>
Updation of work program on:
03-08-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 13-October-2015 | 33.76 lakh | 2. | 20-January-2016 | 23.47 lakh | 3. | 17-March-2016 | 56.64 lakh | 4. | 16-June-2016 | 148.48 lakh | 5. | 05-October-2016 | 30.83 lakh | 6. | 25-November-2016 | 62.88 lakh | 7. | 10-March-2017 | 47.56 lakh | 8. | 26-May-2017 | 9.70 lakh | 9. | 18-June-2017 | 29.41 lakh | 10. | 19-September-2017 | 25.12 lakh | 11. | 24-September-2017 | 17.56 lakh |
Total |
485.41 lakh |
% Payment | 83.86 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
PUC vehicles
Environment & Social Compliances(Sub Project level):
Sanitation Facility, Query, DG set |
Detailed report of this subproject
|
|
Quality
|
No. of Test Required : 588 No. of Test Done : 613 No. of Test Passed : 588 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.88 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 34 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 19-05-2017 | 0+300 | Parapet walls & Thermoplastic paint& BC surface. | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
2. | 10-02-2017 | 7+505 | Drain work | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
3. | 10-02-2017 | 3+750 | Parapet work | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
4. | 10-02-2017 | 38+40 | Exacavation | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
5. | 17-11-2016 | 24+450 | Rolling on BC work is in progress | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
6. | 17-11-2016 | 24+450 | Laying of BC on BM work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
7. | 17-11-2016 | 24+300 | Finishing of BC surface | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
8. | 05-10-2016 | 22+400 | R-wall is in progress | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
9. | 05-10-2016 | 7+100 | Excavation of drain work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
10. | 03-09-2016 | 8+250 | Drainage work is in progress.. | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
11. | 03-09-2016 | 8+150 | Drain work is in progress | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
12. | 03-09-2016 | 5+655 | MBCB work is in progress | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
13. | 17-07-2016 | 0+100 | Pakka drain work has started | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
14. | 10-06-2016 | 2+550 | Themoplast white line is in progress | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
15. | 03-06-2016 | 6+750 | Tack coat for BC work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
16. | 28-05-2016 | 4+300 | Rolling on BC | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
17. | 28-05-2016 | 4+350 | Tack coat for BC | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
18. | 26-05-2016 | 4+825 | BM Laying | Asha Rawat | JE | UEAP R&B Tehri | See Pic |
19. | 26-05-2016 | 4+820 | Tack coat spreading | Asha Rawat | JE | UEAP R&B Tehri | See Pic |
20. | 19-05-2016 | 2+025 | Finishing of BC work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
|
|