Ghansali-Koti-Akhodi Motor Road
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5329 |
Sanction Cost: |
1870.00 lakh |
Length:
|
44.000 KM. |
District: |
Tehri |
Block: |
Bhilangana |
Constituency: |
Ghanshali |
Circle: |
|
DEA: |
DEA UEAP Tehri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1062
Package Name: 
UEAP/PWD/C58
Tender Date: 20-09-2014
Current Status: Agreement signed
Achieved on Date: 23-04-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C58
Contractor Name: Sai construction
|
Start Date: 14-05-2015
Intended Completion Date: 13-11-2016
|
Total Bond Cost: 155959835.33 (1559.6 lakh)
Variation Cost: 58528005.19 (585.28 lakh) Hence Total Bond Cost is 214487840.52 (2144.88 lakh)
|
Sub Project Cost: 1278.16 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 3821020 for 49 days
LD Analysis for Milestone2: calculated LD is Rs 5068700 for 65 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 3.00 KM | 6.17 | 01-07-2015 | 31-10-2015 | 3.00 KM | 3.00 KM | 0.49 | 6.17 | 2. | R/Wall, B/ Wall Type Protection works | 1285.00 m | 286.12 | 01-07-2015 | 30-11-2015 | 1285.00 m | 1285.00 m | 22.65 | 286.12 | 3. | G-2 | 7.72 KM | 21.96 | 20-07-2015 | 31-10-2015 | 7.72 KM | 7.72 KM | 1.74 | 21.96 | 4. | G-3 | 7.72 KM | 22.60 | 01-09-2015 | 15-10-2015 | 7.72 KM | 7.72 KM | 1.79 | 22.60 | 5. | BM i/c Prime Coat, Tack Coat | 16.50 KM | 252.80 | 01-03-2016 | 15-05-2016 | 16.50 KM | 15.75 KM | 19.1 | 241.31 | 6. | SDBC i/c Tackcoat | 38.00 KM | 331.38 | 10-05-2016 | 30-06-2016 | 38.00 KM | 26.50 KM | 18.29 | 231.09 | 7. | Cause Way | 8.00 No | 13.59 | 15-07-2015 | 30-09-2015 | 8.00 No | 3.00 No | 0.4 | 5.10 | 8. | Culverts/Scupper | 6.00 No | 20.83 | 15-07-2015 | 31-10-2015 | 6.00 No | 1.00 No | 0.27 | 3.47 | 9. | longitudinal Drain | 11100.00 m | 227.07 | 01-07-2015 | 31-10-2015 | 11100.00 m | 9150.00 m | 14.82 | 187.18 | 10. | Crash Barrier | 1064.00 m | 6.54 | 15-07-2015 | 31-10-2015 | 1064.00 m | 0.00 m | 0 | 0.00 | 11. | Parapet | 1110.00 No | 33.22 | 15-05-2015 | 31-10-2015 | 1110.00 No | 523.00 No | 1.24 | 15.65 | 12. | Road Furniture | 1374.00 No | 41.01 | 15-10-2015 | 31-03-2016 | 1374.00 No | 645.00 No | 1.52 | 19.25 |
Total Amount: |
1263.29 |
|
82.32 |
1039.9 |
|
Remarks:
No Remarks
Work Program Made On:
30-07-2015 } ?>
Updation of work program on:
22-07-2016
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-August-2015 | 44.00 lakh | 2. | 13-October-2015 | 93.09 lakh | 3. | 07-November-2015 | 48.27 lakh | 4. | 12-January-2016 | 106.98 lakh | 5. | 10-February-2016 | 45.84 lakh | 6. | 18-March-2016 | 39.39 lakh | 7. | 04-May-2016 | 51.13 lakh | 8. | 30-May-2016 | 111.24 lakh | 9. | 20-July-2016 | 93.99 lakh | 10. | 30-September-2016 | 20.35 lakh | 11. | 17-October-2016 | 112.03 lakh | 12. | 27-October-2016 | 138.74 lakh | 13. | 25-November-2016 | 113.87 lakh | 14. | 28-December-2016 | 212.29 lakh | 15. | 21-April-2017 | 33.32 lakh | 16. | 18-June-2017 | 170.51 lakh | 17. | 21-July-2017 | 195.12 lakh |
Total |
1630.16 lakh |
% Payment | 127.54 % |
|
Advance Amount: 294.29 lakh
Recovered Amount: 294.29 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1190 No. of Test Done : 1225 No. of Test Passed : 1190 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.98 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 23 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 10-02-2017 | 4.100 | Bm and Bc work | Jitendra Kumar 2 | JE | UEAP R&B Tehri | See Pic |
2. | 10-02-2017 | 5.050 | Bm and Bc work | Jitendra Kumar 2 | JE | UEAP R&B Tehri | See Pic |
3. | 05-01-2016 | 49.700 | Breast wall work in progress | Jitendra Kumar 2 | JE | UEAP R&B Tehri | See Pic |
4. | 27-10-2015 | 6.750 | G-2 work in progress | Jitendra Kumar 2 | JE | UEAP R&B Tehri | See Pic |
5. | 27-10-2015 | 24.700 | Causeway wall complete | Jitendra Kumar 2 | JE | UEAP R&B Tehri | See Pic |
6. | 27-10-2015 | 49.900 | Causeway retaining wall excavation work in progress | Jitendra Kumar 2 | JE | UEAP R&B Tehri | See Pic |
7. | 25-10-2015 | 6.750 | Drain work in progress | Jitendra Kumar 2 | JE | UEAP R&B Tehri | See Pic |
8. | 23-10-2015 | 2.00 | Drain work in progress | Jitendra Kumar 2 | JE | UEAP R&B Tehri | See Pic |
9. | 19-10-2015 | 4.00 | Drain work in progress | Jitendra Kumar 2 | JE | UEAP R&B Tehri | See Pic |
10. | 08-10-2015 | 2.000 | Retaining wall complete | Jitendra Kumar 2 | JE | UEAP R&B Tehri | See Pic |
11. | 06-10-2015 | 51.00 | Construction of parapet | Jitendra Kumar 2 | JE | UEAP R&B Tehri | See Pic |
12. | 06-10-2015 | 41.850 | Retaining wall complete | Jitendra Kumar 2 | JE | UEAP R&B Tehri | See Pic |
13. | 05-10-2015 | 50.050 | Retaining wall complete | Jitendra Kumar 2 | JE | UEAP R&B Tehri | See Pic |
14. | 03-10-2015 | 50.700 | Construction of parapet | Jitendra Kumar 2 | JE | UEAP R&B Tehri | See Pic |
15. | 03-10-2015 | 50.600 | Retaining wall complete | Jitendra Kumar 2 | JE | UEAP R&B Tehri | See Pic |
16. | 19-09-2015 | 5.800 | BW Construction is going on | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
17. | 24-08-2015 | 0.600 | Kuccha drain under construction | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
18. | 24-08-2015 | 3.850 | B.W. construction under progress | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
19. | 24-08-2015 | 0.800 | Pucca drain under construction | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
20. | 24-08-2015 | 0.100 | Parapet construction under progress | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
|
|