Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Ghansali-Koti-Akhodi Motor Road Agreement signed
Project: UEAP-RB UID: 5329 Sanction Cost: 1870.00  lakh Length: 44.000 KM.
District: Tehri Block: Bhilangana Constituency: Ghanshali Circle:
DEA: DEA UEAP Tehri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: MDR
Procurement:
Package No.: 1062        Package Name:  UEAP/PWD/C58        Tender Date: 20-09-2014        Current Status: Agreement signed        Achieved on Date: 23-04-2015

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C58      Contractor Name: Sai construction
Start Date:  14-05-2015      Intended Completion Date:  13-11-2016     
Total Bond Cost: 155959835.33 (1559.6 lakh)        Variation Cost: 58528005.19 (585.28 lakh)    Hence Total Bond Cost is   214487840.52 (2144.88 lakh) 
Sub Project Cost: 1278.16  lakh       
LD Analysis for Milestone1: calculated LD is Rs 3821020 for 49 days        LD Analysis for Milestone2: calculated LD is Rs 5068700 for 65 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence3.00 KM6.1701-07-201531-10-20153.00 KM3.00 KM0.496.17
2.R/Wall, B/ Wall Type Protection works1285.00 m286.1201-07-201530-11-20151285.00 m1285.00 m22.65286.12
3.G-27.72 KM21.9620-07-201531-10-20157.72 KM7.72 KM1.7421.96
4.G-37.72 KM22.6001-09-201515-10-20157.72 KM7.72 KM1.7922.60
5.BM i/c Prime Coat, Tack Coat16.50 KM252.8001-03-201615-05-201616.50 KM15.75 KM19.1241.31
6.SDBC i/c Tackcoat38.00 KM331.3810-05-201630-06-201638.00 KM26.50 KM18.29231.09
7.Cause Way8.00 No13.5915-07-201530-09-20158.00 No3.00 No0.45.10
8.Culverts/Scupper 6.00 No20.8315-07-201531-10-20156.00 No1.00 No0.273.47
9.longitudinal Drain11100.00 m227.0701-07-201531-10-201511100.00 m9150.00 m14.82187.18
10.Crash Barrier1064.00 m6.5415-07-201531-10-20151064.00 m0.00 m00.00
11.Parapet1110.00 No33.2215-05-201531-10-20151110.00 No523.00 No1.2415.65
12.Road Furniture1374.00 No41.0115-10-201531-03-20161374.00 No645.00 No1.5219.25
Total Amount: 1263.29 82.32   1039.9
Remarks: No Remarks       Work Program Made On: 30-07-2015        Updation of work program on: 22-07-2016       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.26-August-201544.00  lakh
2.13-October-201593.09  lakh
3.07-November-201548.27  lakh
4.12-January-2016106.98  lakh
5.10-February-201645.84  lakh
6.18-March-201639.39  lakh
7.04-May-201651.13  lakh
8.30-May-2016111.24  lakh
9.20-July-201693.99  lakh
10.30-September-201620.35  lakh
11.17-October-2016112.03  lakh
12.27-October-2016138.74  lakh
13.25-November-2016113.87  lakh
14.28-December-2016212.29  lakh
15.21-April-201733.32  lakh
16.18-June-2017170.51  lakh
17.21-July-2017195.12  lakh
Total 1630.16  lakh
% Payment127.54 %
Advance Amount:  294.29  lakh        Recovered Amount:  294.29  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles
Environment & Social Compliances(Sub Project level): Query, Borrow pits
Detailed report of this subproject
Quality
No. of Test Required : 1190   No. of Test Done : 1225    No. of Test Passed : 1190   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 88.98
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 23
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.10-02-20174.100Bm and Bc workJitendra Kumar 2JEUEAP R&B Tehri See Pic
2.10-02-20175.050Bm and Bc workJitendra Kumar 2JEUEAP R&B Tehri See Pic
3.05-01-201649.700Breast wall work in progressJitendra Kumar 2JEUEAP R&B Tehri See Pic
4.27-10-20156.750G-2 work in progressJitendra Kumar 2JEUEAP R&B Tehri See Pic
5.27-10-201524.700Causeway wall completeJitendra Kumar 2JEUEAP R&B Tehri See Pic
6.27-10-201549.900Causeway retaining wall excavation work in progressJitendra Kumar 2JEUEAP R&B Tehri See Pic
7.25-10-20156.750Drain work in progressJitendra Kumar 2JEUEAP R&B Tehri See Pic
8.23-10-20152.00Drain work in progressJitendra Kumar 2JEUEAP R&B Tehri See Pic
9.19-10-20154.00Drain work in progressJitendra Kumar 2JEUEAP R&B Tehri See Pic
10.08-10-20152.000Retaining wall completeJitendra Kumar 2JEUEAP R&B Tehri See Pic
11.06-10-201551.00Construction of parapetJitendra Kumar 2JEUEAP R&B Tehri See Pic
12.06-10-201541.850Retaining wall completeJitendra Kumar 2JEUEAP R&B Tehri See Pic
13.05-10-201550.050Retaining wall completeJitendra Kumar 2JEUEAP R&B Tehri See Pic
14.03-10-201550.700Construction of parapetJitendra Kumar 2JEUEAP R&B Tehri See Pic
15.03-10-201550.600Retaining wall completeJitendra Kumar 2JEUEAP R&B Tehri See Pic
16.19-09-20155.800BW Construction is going onAnuj Kumar SinghAEUEAP R&B Tehri See Pic
17.24-08-20150.600Kuccha drain under constructionAnuj Kumar SinghAEUEAP R&B Tehri See Pic
18.24-08-20153.850B.W. construction under progressAnuj Kumar SinghAEUEAP R&B Tehri See Pic
19.24-08-20150.800Pucca drain under constructionAnuj Kumar SinghAEUEAP R&B Tehri See Pic
20.24-08-20150.100Parapet construction under progressAnuj Kumar SinghAEUEAP R&B Tehri See Pic