Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Ghamiyala-Budakedar Motor Road Agreement signed
Project: UEAP-RB UID: 5328 Sanction Cost: 285.00  lakh Length: KM.
District: Tehri Block: Bhilangana Constituency: Ghanshali Circle:
DEA: DEA UEAP Tehri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: MDR
Procurement:
Package No.: 1062        Package Name:  UEAP/PWD/C58        Tender Date: 20-09-2014        Current Status: Agreement signed        Achieved on Date: 23-04-2015

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C58      Contractor Name: Sai construction
Start Date:  14-05-2015      Intended Completion Date:  13-11-2016     
Total Bond Cost: 155959835.33 (1559.6 lakh)        Variation Cost: 58528005.19 (585.28 lakh)    Hence Total Bond Cost is   214487840.52 (2144.88 lakh) 
Sub Project Cost: 281.44  lakh       
LD Analysis for Milestone1: calculated LD is Rs 3821020 for 49 days        LD Analysis for Milestone2: calculated LD is Rs 5068700 for 65 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.80 KM2.1301-07-201531-10-20150.80 KM0.80 KM0.792.13
2.R/Wall, B/ Wall Type Protection works170.00 m50.4401-07-201530-11-2015170.00 m170.00 m18.850.44
3.G-21.50 KM15.0520-07-201531-10-20151.50 KM1.50 KM5.6115.05
4.G-31.50 KM16.5101-09-201515-10-20151.50 KM1.50 KM6.1616.51
5.BM i/c Prime Coat, Tack Coat1.90 KM46.0201-10-201515-12-20151.90 KM1.90 KM17.1646.02
6.SDBC i/c Tackcoat4.07 KM73.6015-10-201531-12-20154.07 KM4.07 KM27.4473.60
7.Cause Way4.00 No5.1015-07-201530-09-20154.00 No3.00 No1.433.82
8.longitudinal Drain1200.00 m24.9201-07-201531-10-20151200.00 m710.00 m5.514.75
9.Crash Barrier400.00 m13.0715-07-201531-10-2015400.00 m0.00 m00.00
10.Parapet190.00 No5.6915-05-201531-10-2015190.00 No167.00 No1.865.00
11.Road Furniture1113.00 No15.7015-10-201531-03-20161113.00 No1000.00 No5.2614.10
Total Amount: 268.23 90.01   241.42
Remarks: No Remarks       Work Program Made On: 31-07-2015        Updation of work program on: 10-01-2017       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.13-October-201532.71  lakh
2.07-November-20154.07  lakh
3.10-February-201623.42  lakh
4.18-March-20169.77  lakh
5.04-May-20169.54  lakh
6.20-July-201674.45  lakh
7.30-September-201658.71  lakh
8.21-July-201739.32  lakh
Total 251.99  lakh
% Payment89.54 %
Advance Amount:  294.29  lakh        Recovered Amount:  294.29  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles
Environment & Social Compliances(Sub Project level): Signs, Query, Borrow pits, DG set
Detailed report of this subproject
Quality
No. of Test Required : 1190   No. of Test Done : 1225    No. of Test Passed : 1190   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 93.21
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 5
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.29-11-201514.450G-2 work in progressJitendra Kumar 2JEUEAP R&B Tehri See Pic
2.05-10-20154.550Retaining wall completeJitendra Kumar 2JEUEAP R&B Tehri See Pic
3.05-10-201514.450Under construction Retaining wallJitendra Kumar 2JEUEAP R&B Tehri See Pic
4.24-08-201513.350RW under constructionAnuj Kumar SinghAEUEAP R&B Tehri See Pic
5.24-08-201513.200R.W. CompletedAnuj Kumar SinghAEUEAP R&B Tehri See Pic