Ghamiyala-Budakedar Motor Road
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5328 |
Sanction Cost: |
285.00 lakh |
Length:
|
KM. |
District: |
Tehri |
Block: |
Bhilangana |
Constituency: |
Ghanshali |
Circle: |
|
DEA: |
DEA UEAP Tehri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1062
Package Name: 
UEAP/PWD/C58
Tender Date: 20-09-2014
Current Status: Agreement signed
Achieved on Date: 23-04-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C58
Contractor Name: Sai construction
|
Start Date: 14-05-2015
Intended Completion Date: 13-11-2016
|
Total Bond Cost: 155959835.33 (1559.6 lakh)
Variation Cost: 58528005.19 (585.28 lakh) Hence Total Bond Cost is 214487840.52 (2144.88 lakh)
|
Sub Project Cost: 281.44 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 3821020 for 49 days
LD Analysis for Milestone2: calculated LD is Rs 5068700 for 65 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.80 KM | 2.13 | 01-07-2015 | 31-10-2015 | 0.80 KM | 0.80 KM | 0.79 | 2.13 | 2. | R/Wall, B/ Wall Type Protection works | 170.00 m | 50.44 | 01-07-2015 | 30-11-2015 | 170.00 m | 170.00 m | 18.8 | 50.44 | 3. | G-2 | 1.50 KM | 15.05 | 20-07-2015 | 31-10-2015 | 1.50 KM | 1.50 KM | 5.61 | 15.05 | 4. | G-3 | 1.50 KM | 16.51 | 01-09-2015 | 15-10-2015 | 1.50 KM | 1.50 KM | 6.16 | 16.51 | 5. | BM i/c Prime Coat, Tack Coat | 1.90 KM | 46.02 | 01-10-2015 | 15-12-2015 | 1.90 KM | 1.90 KM | 17.16 | 46.02 | 6. | SDBC i/c Tackcoat | 4.07 KM | 73.60 | 15-10-2015 | 31-12-2015 | 4.07 KM | 4.07 KM | 27.44 | 73.60 | 7. | Cause Way | 4.00 No | 5.10 | 15-07-2015 | 30-09-2015 | 4.00 No | 3.00 No | 1.43 | 3.82 | 8. | longitudinal Drain | 1200.00 m | 24.92 | 01-07-2015 | 31-10-2015 | 1200.00 m | 710.00 m | 5.5 | 14.75 | 9. | Crash Barrier | 400.00 m | 13.07 | 15-07-2015 | 31-10-2015 | 400.00 m | 0.00 m | 0 | 0.00 | 10. | Parapet | 190.00 No | 5.69 | 15-05-2015 | 31-10-2015 | 190.00 No | 167.00 No | 1.86 | 5.00 | 11. | Road Furniture | 1113.00 No | 15.70 | 15-10-2015 | 31-03-2016 | 1113.00 No | 1000.00 No | 5.26 | 14.10 |
Total Amount: |
268.23 |
|
90.01 |
241.42 |
|
Remarks:
No Remarks
Work Program Made On:
31-07-2015 } ?>
Updation of work program on:
10-01-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 13-October-2015 | 32.71 lakh | 2. | 07-November-2015 | 4.07 lakh | 3. | 10-February-2016 | 23.42 lakh | 4. | 18-March-2016 | 9.77 lakh | 5. | 04-May-2016 | 9.54 lakh | 6. | 20-July-2016 | 74.45 lakh | 7. | 30-September-2016 | 58.71 lakh | 8. | 21-July-2017 | 39.32 lakh |
Total |
251.99 lakh |
% Payment | 89.54 % |
|
Advance Amount: 294.29 lakh
Recovered Amount: 294.29 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
PUC vehicles
Environment & Social Compliances(Sub Project level):
Signs, Query, Borrow pits, DG set |
Detailed report of this subproject
|
|
Quality
|
No. of Test Required : 1190 No. of Test Done : 1225 No. of Test Passed : 1190 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 93.21 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 5 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 29-11-2015 | 14.450 | G-2 work in progress | Jitendra Kumar 2 | JE | UEAP R&B Tehri | See Pic |
2. | 05-10-2015 | 4.550 | Retaining wall complete | Jitendra Kumar 2 | JE | UEAP R&B Tehri | See Pic |
3. | 05-10-2015 | 14.450 | Under construction Retaining wall | Jitendra Kumar 2 | JE | UEAP R&B Tehri | See Pic |
4. | 24-08-2015 | 13.350 | RW under construction | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
5. | 24-08-2015 | 13.200 | R.W. Completed | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
|
|