Lambgaon-Pratapnagar Motor Road
Work Completed
|
Project: |
UEAP-RB |
UID: |
5326 |
Sanction Cost: |
295.00 lakh |
Length:
|
23.000 KM. |
District: |
Tehri |
Block: |
Pratapnagar |
Constituency: |
Pratapnagar |
Circle: |
|
DEA: |
DEA UEAP Tehri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1061
Package Name: 
UEAP/PWD/C57
Tender Date: 20-09-2014
Current Status: Agreement signed
Achieved on Date: 24-03-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C57
Contractor Name: Dwarika Projects Limited
|
Start Date: 16-04-2015
Intended Completion Date: 12-10-2016
|
Total Bond Cost: 204556334.05 (2045.56 lakh)
Variation Cost: 22876323.81 (228.76 lakh) Hence Total Bond Cost is 227432657.86 (2274.33 lakh)
|
Sub Project Cost: 221.76 lakh
Variation Cost of Sub Project: 22876323.81 (228.76 lakh)
Total Sub Project Cost:
450.52 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 21273824 for 208 days
LD Analysis for Milestone2: calculated LD is Rs 18103206 for 177 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 3.30 KM | 4.12 | 13-04-2015 | 30-05-2015 | 3.30 KM | 3.30 KM | 1.97 | 4.12 | 2. | R/Wall, B/ Wall Type Protection works | 1132.00 m | 45.21 | 01-06-2015 | 31-12-2015 | 1132.00 m | 1132.00 m | 21.63 | 45.21 | 3. | G-2 | 0.10 KM | 3.69 | 31-07-2015 | 30-09-2015 | 0.10 KM | 0.10 KM | 1.76 | 3.69 | 4. | G-3 | 0.10 KM | 3.99 | 31-07-2015 | 30-09-2015 | 0.10 KM | 0.10 KM | 1.91 | 3.99 | 5. | BM i/c Prime Coat, Tack Coat | 2.11 KM | 41.49 | 01-10-2015 | 30-11-2015 | 2.11 KM | 2.11 KM | 19.85 | 41.49 | 6. | SDBC i/c Tackcoat | 12.97 KM | 37.59 | 01-03-2016 | 30-06-2016 | 12.97 KM | 12.97 KM | 17.98 | 37.59 | 7. | longitudinal Drain | 11800.00 m | 49.01 | 01-09-2015 | 30-09-2016 | 11800.00 m | 11800.00 m | 23.45 | 49.01 | 8. | Crash Barrier | 150.00 m | 5.25 | 01-09-2015 | 30-09-2016 | 150.00 m | 150.00 m | 2.51 | 5.25 | 9. | Parapet | 138.00 No | 6.09 | 01-09-2015 | 30-09-2016 | 138.00 No | 138.00 No | 2.91 | 6.09 | 10. | Road Furniture | 400.00 No | 12.55 | 01-09-2015 | 30-09-2016 | 400.00 No | 400.00 No | 6.01 | 12.55 |
Total Amount: |
208.99 |
|
100 |
208.99 |
|
Remarks:
No Remarks
Work Program Made On:
09-08-2015 } ?>
Updation of work program on:
11-09-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 24-March-2015 | 0.10 lakh | 2. | 20-June-2015 | 7.30 lakh | 3. | 26-August-2015 | 4.89 lakh | 4. | 08-October-2015 | 24.41 lakh | 5. | 09-February-2016 | 12.91 lakh | 6. | 03-August-2016 | 91.12 lakh | 7. | 17-October-2016 | 171.31 lakh | 8. | 26-November-2016 | 73.81 lakh | 9. | 30-May-2017 | 21.41 lakh | 10. | 04-August-2017 | 84.46 lakh |
Total |
491.72 lakh |
% Payment | 109.14 % |
|
Advance Amount: 328.21 lakh
Recovered Amount: 328.21 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 2075 No. of Test Done : 2207 No. of Test Passed : 2073 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.47 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 1 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 09-03-2017 | Lambgaon/0+600 | Cross barier | Roshan Singh Rana | JE | UEAP R&B Tehri | See Pic |
|
|