Ghansali-Tehri-Pratapnagar Motor Raod
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5325 |
Sanction Cost: |
635.00 lakh |
Length:
|
28.000 KM. |
District: |
Tehri |
Block: |
Pratapnagar |
Constituency: |
Pratapnagar |
Circle: |
|
DEA: |
DEA UEAP Tehri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1061
Package Name: 
UEAP/PWD/C57
Tender Date: 20-09-2014
Current Status: Agreement signed
Achieved on Date: 24-03-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C57
Contractor Name: Dwarika Projects Limited
|
Start Date: 16-04-2015
Intended Completion Date: 12-10-2016
|
Total Bond Cost: 204556334.05 (2045.56 lakh)
Variation Cost: 22876323.81 (228.76 lakh) Hence Total Bond Cost is 227432657.86 (2274.33 lakh)
|
Sub Project Cost: 473.40 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 21273824 for 208 days
LD Analysis for Milestone2: calculated LD is Rs 18103206 for 177 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.18 KM | 2.11 | 01-05-2015 | 30-06-2016 | 1.18 KM | 1.18 KM | 0.46 | 2.11 | 2. | R/Wall, B/ Wall Type Protection works | 1601.00 m | 97.06 | 01-09-2015 | 30-09-2016 | 1601.00 m | 1601.00 m | 20.99 | 97.06 | 3. | G-2 | 0.98 KM | 6.63 | 31-07-2015 | 30-09-2015 | 0.98 KM | 0.98 KM | 1.43 | 6.63 | 4. | G-3 | 0.98 KM | 6.63 | 30-07-2015 | 30-09-2015 | 0.98 KM | 0.98 KM | 1.43 | 6.63 | 5. | BM i/c Prime Coat, Tack Coat | 2.73 KM | 60.78 | 01-10-2015 | 30-11-2015 | 2.73 KM | 2.73 KM | 13.14 | 60.78 | 6. | SDBC i/c Tackcoat | 6.92 KM | 111.74 | 01-03-2016 | 30-06-2016 | 6.92 KM | 6.92 KM | 24.16 | 111.74 | 7. | Cause Way | 3.00 No | 1.89 | 01-09-2015 | 29-02-2016 | 3.00 No | 3.00 No | 0.41 | 1.89 | 8. | longitudinal Drain | 2520.00 m | 163.41 | 01-09-2015 | 30-09-2016 | 2520.00 m | 2520.00 m | 35.33 | 163.41 | 9. | Parapet | 238.00 No | 8.31 | 01-01-2016 | 31-08-2016 | 238.00 No | 238.00 No | 1.8 | 8.31 | 10. | Road Furniture | 208.00 No | 3.93 | 01-07-2016 | 31-08-2016 | 208.00 No | 0.00 No | 0 | 0.00 |
Total Amount: |
462.49 |
|
99.15 |
458.56 |
|
Remarks:
No Remarks
Work Program Made On:
07-08-2015 } ?>
Updation of work program on:
22-07-2016
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 24-March-2015 | 0.10 lakh | 2. | 26-August-2015 | 20.86 lakh | 3. | 08-October-2015 | 14.48 lakh | 4. | 09-February-2016 | 20.34 lakh | 5. | 31-March-2016 | 14.61 lakh | 6. | 02-June-2016 | 58.27 lakh | 7. | 03-August-2016 | 26.61 lakh | 8. | 17-October-2016 | 18.30 lakh | 9. | 02-February-2017 | 116.87 lakh | 10. | 23-June-2017 | 57.16 lakh | 11. | 04-August-2017 | 35.35 lakh |
Total |
382.95 lakh |
% Payment | 80.89 % |
|
Advance Amount: 328.21 lakh
Recovered Amount: 328.21 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
PUC vehicles
Environment & Social Compliances(Sub Project level):
debris disposal, Query, DG set |
Detailed report of this subproject
|
|
Quality
|
No. of Test Required : 2075 No. of Test Done : 2207 No. of Test Passed : 2073 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.10 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 1 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 31-07-2015 | Km 8 | B/w banded | Asha rawat | JE | DEA ADB Dehradun | See Pic |
|
|